Fire Sprinkler System Permit (Plan Review) in Town of Taos, New Mexico
Following the same trade-split framework documented throughout this file, fire sprinkler plan review and permitting in the Town of Taos is genuinely distinct from the Electrical/Plumbing/Mechanical trades: rather than being routed to the state Construction Industries Division (CID) like those trades (per §§ 16.12.070.2(D)/16.12.070.3(H)), fire sprinkler plan review is self-administered directly by the Town of Taos Fire Department's own fire marshal, using the Department's 'Fire Inspection Request Application' (case prefix 'FI20__-__'). The Town does not publish a separate, standalone 'Fire Sprinkler Permit' application distinct from this general Fire Inspection Request form — Residential Fire Sprinkler Plans, Commercial Fire Sprinkler Plans, and Commercial Fire Sprinkler Modification Plans are each individual checkbox line items with their own fees within that one form. Installation must comply with the 2015 International Fire Code (IFC), adopted by reference with local amendments at Town of Taos Code of Ordinances § 8.12.010, including IFC § 903 (Automatic Sprinkler Systems).
Verified 2026-07-22 · Source
When you need this permit
- Fire Inspection Request Application (Town of Taos Fire Department) with the applicable 'Plan Review Fees' checkbox selected: Residential Fire Sprinkler Plans, Commercial Fire Sprinkler Plans, or Commercial Fire Sprinkler Modification Plans
- A set of plans must be submitted for plan review — required submittal per the application's own checklist ('Set of Plans for Plan Review (Only for items listed under Plan Review Fees)')
- For Commercial Fire Sprinkler Plans, the total number of sprinkler devices must be listed on the application (governs the per-device fee component)
- Installation must comply with the 2015 International Fire Code as adopted and locally modified by Town of Taos Code of Ordinances § 8.12.010, including IFC § 903 Automatic Sprinkler Systems (the Town's only local modification to § 903 narrows an exception for telecommunications-equipment spaces, per Ordinance 15-01)
- For commercial, industrial, or large-scale-residential projects, all plans (including fire sprinkler plans submitted as part of that project) must be stamped by a licensed engineer and/or architect per Town of Taos Code of Ordinances § 16.12.070.3(E)
- A contractor performing the physical installation must separately hold a current New Mexico Construction Industries Division (CID) license for the applicable fire-suppression trade, a statewide licensing requirement distinct from this Town-administered plan-review/permit process
- Failure to secure a required fire-code permit is a citable offense under the Town's fire code citation program, carrying a $250.00 citation fee per violation, in addition to any permit fee — Town of Taos Code of Ordinances § 8.12.020
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Fire Marshal Plan Review
Town of Taos Fire Department reviews submitted sprinkler plans (and device count, for commercial) for compliance with the adopted 2015 International Fire Code, IFC § 903 Automatic Sprinkler Systems.
- 2
Sprinkler System Inspection
Physical inspection of the installed fire sprinkler system by the Town of Taos Fire Department; coordinated with the fire department's final-inspection sign-off required before a Certificate of Occupancy may be issued under § 16.12.070.4(C).
See the full Town of Taos inspection guide — scheduling & re-inspection fees →
Tips
- Unlike Electrical, Plumbing, and Mechanical/HVAC — which the Town routes entirely to the state CID per §§ 16.12.070.2(D)/16.12.070.3(H) — fire sprinkler plan review, permitting, and inspection within Taos are self-administered directly by the Town's own Fire Marshal/Fire Department, the same self-administration pattern documented for Building (not Electrical/Plumbing/Mechanical) in this file's other entries.
- There is no standalone 'Fire Sprinkler Permit' application distinct from the Fire Department's general Fire Inspection Request Application — Residential Fire Sprinkler Plans, Commercial Fire Sprinkler Plans, and Commercial Fire Sprinkler Modification Plans are each a checkbox line item with its own fee within that one form.
- Commercial projects need the total device count on hand before submitting — it directly drives the per-device fee component above 50 devices.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Town of Taos building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Town of Taos
Fire Sprinkler System Permit (Plan Review) in other cities
Compare fire sprinkler system permit (plan review) fees across New Mexico →
Look up this fee in a different city →
Now live
Build your Town of Taos project checklist
Describe your project once and get every permit, document, and fee it triggers in Town of Taos — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →