Fruit Heights does not publish a separate EV-charger/EVSE permit or fee. Installing an EV charger is electrical work and is processed under the city's general Electrical Permit — the same permit used for solar panel (PV) installations per the city's official Building Permits FAQ. No dedicated flat electrical-permit fee is published on the official Building Fee Schedule (verified directly 2026-07-19); the general valuation-based Building Permit Fee framework applies instead. EV chargers fall under this general Electrical Permit with no EV-specific line item or process published.

Reviewed 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in Fruit Heights
  • Electrical work regulated by the adopted 2017 NEC
  • Building Permit Application submitted online via the CivicReview portal (app.civicreview.com), the same portal used for other building-permit types

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Filing fee
Not published — contact the department

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Fruit Heights?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Inspection

    Scheduled via (801) 546-0861 ext. 2 per the official Building Permits page.

See the full Fruit Heights inspection guide — scheduling & re-inspection fees →

Tips

  • Fruit Heights has no separate EV-charger permit or fee line item — file the installation as a general Electrical Permit through the CivicReview portal.
  • Solar panel (PV) installation in Fruit Heights is also processed as an Electrical Permit, per the city's official Building Permits FAQ — the city treats several types of electrical-only work the same way.
  • Because no dedicated flat electrical-permit fee is published, confirm the applicable fee with the Building Department, (801) 546-0861 ext. 2, before applying.

Frequently asked questions

Fruit Heights requires an ev charger / evse permit for: Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in Fruit Heights; Electrical work regulated by the adopted 2017 NEC; Building Permit Application submitted online via the CivicReview portal (app.civicreview.com), the same portal used for other building-permit types. If your project isn't listed, confirm with Fruit Heights City Building Department at (801) 546-0861 ext. 2 before starting work.

Fruit Heights does not publish a plan-review timeline for this permit. Contact Fruit Heights City Building Department at (801) 546-0861 ext. 2 for current turnaround.

You'll need: Building Permit Application (CivicReview portal). See the required-documents checklist on this page for details on each.

Fruit Heights requires 1 inspection(s) for an ev charger / evse permit, in order: Electrical Inspection. Schedule each through Fruit Heights City Building Department ((801) 546-0861 ext. 2).

Apply through Fruit Heights City Building Department at 910 S Mountain Road, Fruit Heights, UT 84037. Phone: (801) 546-0861 ext. 2, email: ckunkel@fruitheights.gov. Office hours: Not published on the city's Building or Contact Us pages as of 2026-07-08; general city hall contact is (801) 546-0861.. Official information: https://www.fruitheights.gov/112/Building.

Fruit Heights, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide-mandatory edition per Utah Code § 15A-2-103(1)(a), effective July 1, 2026, binding on Fruit Heights as a Utah municipality per § 15A-1-204. Fruit Heights City's own official Building Permits page 'Design Criteria' section (fruitheights.gov/251/Building-Permits) still lists '2018 International Building Code' as of a live re-check on 2026-07-16 — a genuine lag on the city's own page; the statewide statute governs regardless.; 2021 International Residential Code (IRC) — current statewide edition per Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update. Fruit Heights' Design Criteria page lists '2015 International Residential Code' as of 2026-07-16 — a pre-existing lag on the city's page (predates and is unrelated to the 2026 flip), also superseded by the statewide-mandatory 2021 edition.; 2024 International Mechanical Code (IMC) — current statewide edition per Utah Code § 15A-2-103(1)(e), effective July 1, 2026. Fruit Heights' Design Criteria page lists '2018 Mechanical... Code' as of 2026-07-16 — a lag on the city's own page.; 2024 International Plumbing Code (IPC) — current statewide edition per Utah Code § 15A-2-103(1)(d), effective July 1, 2026. Fruit Heights' Design Criteria page lists '2018... Plumbing... Code' as of 2026-07-16 — a lag on the city's own page.; 2024 International Energy Conservation Code (IECC) — current statewide edition per Utah Code § 15A-2-103(1)(h), effective July 1, 2026. Fruit Heights' Design Criteria page lists '2018... Energy Code' as of 2026-07-16 — a lag on the city's own page.; 2023 National Electrical Code (NEC) — current statewide edition per Utah Code § 15A-2-103(1)(g); unchanged by the July 1, 2026 statewide update. Fruit Heights' Design Criteria page lists '2017 Electrical Code' as of 2026-07-16 — a pre-existing lag on the city's page (the statewide NEC cycle has advanced 2017→2020→2023 across multiple prior update cycles, predating and unrelated to the July 2026 IBC/IPC/IMC/IECC flip).; 2024 International Fuel Gas Code (IFGC), 2024 International Existing Building Code (IEBC), and the residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — adopted statewide per Utah Code § 15A-2-103(1)(f), (1)(i), and (1)(n) respectively; none of these titles are separately itemized on Fruit Heights' own Design Criteria page (which lists only Building, Residential, Mechanical, Plumbing, Energy, and Electrical), but all apply statewide regardless of the page's omission.; Note: the city's codified Municipal Code Title 9, Chapter 1 (Building Codes and Regulations; amlegal/city PDF, last amended 'July 2006') still references the legacy 'Uniform Building Code, current edition' and Utah Plumbing/Electrical codes by older nomenclature and has not been re-codified to reflect the state's IBC/IRC adoption cycle under Utah Code § 15A-2-103; the statewide statute is authoritative as a matter of law regardless of either the live Building Permits page's lag or Title 9 Chapter 1's older nomenclature, consistent with Title 9 Chapter 1 § 9-1-3's own provision that subsequent code editions are 'deemed adopted automatically... without further action of the city council.'. Local amendments apply — see the Fruit Heights overview page for the full list.

No. The city's official Building Permits page and Building Permit Fee Schedule publish no distinct EV-charger or EVSE line item. Installing an EV charger is filed as a general Electrical Permit through the same CivicReview portal used for other building-permit types.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fruit Heights building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.