Roosevelt building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Roosevelt, Utah.

Verified 2026-07-19 · Source

How to schedule

Inspections are requested through the building department below.

Address
255 South State Street, Roosevelt, UT 84066
Phone
(435) 722-5001 (Building Department); Fax (435) 722-5000
Office hours
Monday-Thursday, 7:30 a.m. to 5:30 p.m. (closed Fridays), per Roosevelt City's Building Department page.

Published scheduling rules

  • 24-hour advance notice required to schedule inspections, per the application form (Residential/Duplex Building Permit)
  • 24-hour advance notice required to schedule inspections (Commercial Building Permit)
  • 24-hour advance notice required to schedule inspections, per the application form (Commercial Tenant Improvement / Tenant Finish Permit)
  • 24-hour advance notice required to schedule inspections, per Roosevelt City's building permit application forms (Solar PV Installation Permit)
  • 24-hour advance notice required to schedule inspections, per the Commercial Building Permit Application (Fire Alarm System Permit)

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Footing/Foundation

    Per the statewide-adopted construction code; 24-hour advance notice required.

  2. 2

    Framing

    Structural framing inspection, subject to engineer/architect seal review for qualifying buildings.

  3. 3

    Final

    Final inspection prior to occupancy.

Applies to: Residential/Duplex Building Permit

  1. 1

    Footing/Foundation

    Per the statewide-adopted construction code; 24-hour advance notice required.

  2. 2

    Framing

    Structural framing inspection prior to insulation/drywall.

  3. 3

    Final

    Final inspection prior to occupancy.

Applies to: Street Right-of-Way Encroachment Permit

  1. 1

    Pre-Backfill Inspection

    Contractor must call for inspection at least 24 hours before backfilling, paving, or pouring concrete.

  2. 2

    Compaction Test

    A minimum of 96% compaction is required at each 8-inch lift, certified by a qualified person or engineer midway during backfill and on the surface; passing test results must be submitted to Public Works before paving the street cut.

  3. 3

    Final Inspection and Acceptance

    Final inspection and acceptance by Roosevelt City, at which point the contractor bond is released.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Rough-In Inspection

    Electrical, plumbing, and mechanical rough-in for interior tenant-finish work; 24-hour advance notice required.

  2. 2

    Final

    Final inspection prior to occupancy.

Applies to: Mobile Home Inspection Permit

  1. 1

    Foundation/Set Inspection

    Inspection of foundation and home-set prior to utility connection.

  2. 2

    Final

    Final inspection prior to occupancy.

Applies to: Solar PV Installation Permit

  1. 1

    Electrical Inspection

    Inspection of the PV system's electrical wiring, inverter, and grid-interconnection point by the Roosevelt City Building Department.

  2. 2

    Final

    Final inspection of the completed installation, including roof-mount structural attachment where applicable, prior to system energization.

Roosevelt building permits

Get alerts for Roosevelt

We'll email you when Roosevelt's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.