Street Right-of-Way Encroachment Permit — Roosevelt, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://www.rooseveltcity.gov/151/Building-Department
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Street Right-of-Way Encroachment Permit in Roosevelt, Utah
Required for any contractor work performed within Roosevelt City's public street right-of-way (e.g., utility cuts, excavation near public streets). Requires a minimum contractor bond and adherence to the City's Standard Specifications for the Construction of Public Works, rather than a flat application fee.
Verified 2026-07-19 · Source
When you need this permit
- Work performed within Roosevelt City's public street right-of-way
- Minimum $2,000.00 contractor bond (increased in multiples as determined by Public Works) Contractor
- Proof of insurance per Section 0135 29-1.5 of Roosevelt City Standard Specifications Contractor
- Water and Sewer Agreement approval, if applicable
- Compliance with Roosevelt City Standard Specifications for the Construction of Public Works (September 2015 update)
- 24-hour advance notice before backfilling, paving, or pouring concrete
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Pre-Backfill Inspection
Contractor must call for inspection at least 24 hours before backfilling, paving, or pouring concrete.
- 2
Compaction Test
A minimum of 96% compaction is required at each 8-inch lift, certified by a qualified person or engineer midway during backfill and on the surface; passing test results must be submitted to Public Works before paving the street cut.
- 3
Final Inspection and Acceptance
Final inspection and acceptance by Roosevelt City, at which point the contractor bond is released.
See the full Roosevelt inspection guide — scheduling & re-inspection fees →
Tips
- Road cuts must be paved within one (1) day of backfill (cold mix permitted temporarily if hot mix is unavailable, with hot mix applied later); a wintertime backfill option using compacted rock, geotextile fabric, and road base is available per the permit's Items to Review section.
- Material and workmanship are warranted for three (3) years (1,095 days) from the date of final inspection and acceptance — the bond is not released until then.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Roosevelt building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Roosevelt
Compare street right-of-way encroachment permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Roosevelt project checklist
Describe your project once and get every permit, document, and fee it triggers in Roosevelt — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →