Solar PV Installation Permit in Roosevelt, Utah

Roosevelt City has no distinct solar or photovoltaic (PV) permit application, checklist, or fee line item. A rooftop or ground-mounted solar PV installation is processed as part of the general Residential/Duplex or Commercial Building Permit (whichever applies to the property), using the same citywide valuation-based Building Permit Fee table (Resolution 2024-322), plus the standard $25.00 Electrical Inspection fee for the electrical/interconnection work.

Verified 2026-07-21 · Source

When you need this permit

  • Installation of a rooftop or ground-mounted solar photovoltaic (PV) system at a residential or commercial property within Roosevelt City limits
  • Utah-licensed general contractor's name and Utah State License #, or owner-builder designation, per the Residential/Duplex or Commercial Building Permit Application (whichever applies) Owner-builderContractor
  • Utah-licensed electrical contractor for the PV system's electrical/interconnection work
  • Structural documentation for roof-mounted arrays as required under the statewide-adopted construction code (2024 IBC/IRC family, per Utah Code § 15A-2-103)
  • 24-hour advance notice required to schedule inspections, per Roosevelt City's building permit application forms

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based)Roosevelt City Consolidated Fee Schedule, Resolution 2024-322, Building Department Fee Schedule — no distinct solar/PV valuation tier or fee line item exists; confirmed by direct fetch of the Building Department page and the Consolidated Fee Schedule PDF, plus a general web search, on 2026-07-21.
Same citywide valuation table as the Residential/Duplex and Commercial Building Permits: $23.50 for $1-$500, scaling to $5,608.75 for the first $1,000,000.00 plus $3.65 per additional $1,000.00 above that
Electrical InspectionRoosevelt City Consolidated Fee Schedule, Resolution 2024-322, 'Other Inspections and Fees' section — the same flat electrical inspection fee applied to other standalone electrical work (e.g., EV chargers) also governs a solar PV system's electrical/interconnection work, since no solar-specific fee category exists.
$25.00

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV Installation Permit permit actually take in Roosevelt?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Inspection

    Inspection of the PV system's electrical wiring, inverter, and grid-interconnection point by the Roosevelt City Building Department.

  2. 2

    Final

    Final inspection of the completed installation, including roof-mount structural attachment where applicable, prior to system energization.

See the full Roosevelt inspection guide — scheduling & re-inspection fees →

Tips

  • Roosevelt City has no separate solar/photovoltaic permit, application, or fee line — confirmed by direct fetch of the Building Department page (rooseveltcity.gov/151/Building-Department) and the Consolidated Fee Schedule (Resolution 2024-322), plus a general web search, on 2026-07-21. This matches the same conclusion already flagged in this file's residential-building-permit entry (checked 2026-07-19).
  • File a solar PV installation under whichever general building permit matches the property type — Residential/Duplex or Commercial — using the valuation-based Building Permit Fee table, plus the standard $25.00 Electrical Inspection fee for the electrical/interconnection work.
  • Confirm with the Building Department (435-722-5001) whether a roof-mounted array on an existing home requires the same structural review as new construction, since the city's own forms do not separately address retrofit solar installations.

Frequently asked questions

Roosevelt requires a solar pv installation permit for: Installation of a rooftop or ground-mounted solar photovoltaic (PV) system at a residential or commercial property within Roosevelt City limits; Utah-licensed general contractor's name and Utah State License #, or owner-builder designation, per the Residential/Duplex or Commercial Building Permit Application (whichever applies); Utah-licensed electrical contractor for the PV system's electrical/interconnection work; Structural documentation for roof-mounted arrays as required under the statewide-adopted construction code (2024 IBC/IRC family, per Utah Code § 15A-2-103); 24-hour advance notice required to schedule inspections, per Roosevelt City's building permit application forms. If your project isn't listed, confirm with Roosevelt City Building Department at (435) 722-5001 (Building Department); Fax (435) 722-5000 before starting work.

There is no dedicated solar fee. It is billed as a standard Building Permit Fee based on project valuation (starting at $23.50 for $1-$500 and scaling up per Resolution 2024-322's table) plus a flat $25.00 Electrical Inspection fee.

Roosevelt does not publish a plan-review timeline for this permit. Contact Roosevelt City Building Department at (435) 722-5001 (Building Department); Fax (435) 722-5000 for current turnaround.

You'll need: Residential/Duplex Building Permit Application or Commercial Building Permit Application. See the required-documents checklist on this page for details on each.

Roosevelt requires 2 inspection(s) for a solar pv installation permit, in order: Electrical Inspection, Final. Schedule each through Roosevelt City Building Department ((435) 722-5001 (Building Department); Fax (435) 722-5000).

Apply through Roosevelt City Building Department at 255 South State Street, Roosevelt, UT 84066. Phone: (435) 722-5001 (Building Department); Fax (435) 722-5000, email: djohnson@rooseveltcity.com (Dean Johnson, Building Inspector); deschler@rooseveltcity.gov (Drew Eschler, Planning and Zoning Division Manager, (435) 725-7206). Office hours: Monday-Thursday, 7:30 a.m. to 5:30 p.m. (closed Fridays), per Roosevelt City's Building Department page.. Official information: https://www.rooseveltcity.gov/151/Building-Department.

Roosevelt, Utah has adopted: Roosevelt City does not separately publish IBC/IRC/IPC/IMC/IFGC/IECC/IEBC/NEC edition years on its Building Department page or on its own permit application forms. Both the Commercial Building Permit Application and the Residential/Duplex Building Permit Application state only: 'Decisions relative to this application are subject to review by the chief executive officer of the municipal or county entity issuing this building permit and appeal under the International Building Code as adopted by Legislature' — i.e., the city defers to whatever edition the Utah Legislature has adopted statewide, without itemizing it locally.; 2024 International Building Code (IBC), including Appendices C and J — Utah Code § 15A-2-103(1)(a); current statewide edition as of 7/1/2026 (2021 edition governed through 6/30/2026).; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); unchanged by the 7/1/2026 statewide revision.; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); current statewide edition as of 7/1/2026.; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); current statewide edition as of 7/1/2026.; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); current statewide edition as of 7/1/2026.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — Utah Code § 15A-2-103(1)(h); current as of 7/1/2026.; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); current statewide edition as of 7/1/2026.; 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); statewide by statute, not separately itemized by Roosevelt.; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); statewide in force, unchanged by the 7/1/2026 revision.; Roosevelt City Standard Specifications and Drawings (originally published March 2014, updated September 2015) — governs public infrastructure construction (streets, water, sewer, storm drain), referenced by the Street Right-of-Way Encroachment Permit; this is a public-works construction standard, not a building-code edition adoption, and does not itemize IBC/IRC edition years.. Local amendments apply — see the Roosevelt overview page for the full list.

No. Roosevelt City does not publish a distinct solar or photovoltaic permit, application, or fee. A solar PV installation is submitted on the same Residential/Duplex or Commercial Building Permit Application used for other construction work, and is billed under the general valuation-based Building Permit Fee table (Resolution 2024-322) plus the standard $25.00 Electrical Inspection fee.

Sources & verification

Verified against official sources. Last reviewed 2026-07-21.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Roosevelt building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.