Required for new single-family dwelling and duplex construction, additions, remodels, basement finishes, detached garages, carports/patio covers, and sheds within Roosevelt City limits. Building valuation determines the base permit fee per the city's citywide valuation-based fee table (Resolution 2024-322); water impact, sewer connection, secondary water, electrical, and gas-line fees are billed as separate line items on the same application.

Verified 2026-07-20 · Source

When you need this permit

  • New single-family dwelling or duplex construction, addition, remodel, basement finish, detached garage, carport/patio cover, or shed within Roosevelt City limits
  • Duchesne County Assessor's Parcel Number for the job site
  • Utah-licensed general contractor's name and Utah State License #, or owner-builder designation Owner-builderContractor
  • Water meter size (3/4" or 1") and whether the property has an existing water meter and sewer service
  • 24-hour advance notice required to schedule inspections, per the application form

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — $1.00 to $500.00Roosevelt City Consolidated Fee Schedule, Resolution 2024-322, Building Department Fee Schedule (valuation table).
$23.50
Building Permit Fee — $501.00 to $2,000.00Roosevelt City Consolidated Fee Schedule, Resolution 2024-322.
$23.50 for the first $500.00 plus $3.05 for each additional $100.00 or fraction thereof
Building Permit Fee — $2,001.00 to $25,000.00Roosevelt City Consolidated Fee Schedule, Resolution 2024-322.
$69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00 or fraction thereof
Building Permit Fee — $25,001.00 to $50,000.00Roosevelt City Consolidated Fee Schedule, Resolution 2024-322.
$391.75 for the first $25,000.00 plus $10.10 for each additional $1,000.00 or fraction thereof
Building Permit Fee — $50,001.00 to $100,000.00Roosevelt City Consolidated Fee Schedule, Resolution 2024-322.
$643.75 for the first $50,000.00 plus $7.00 for each additional $1,000.00 or fraction thereof
Building Permit Fee — $100,001.00 to $500,000.00Roosevelt City Consolidated Fee Schedule, Resolution 2024-322.
$993.75 for the first $100,000.00 plus $5.60 for each additional $1,000.00 or fraction thereof
Building Permit Fee — $500,001.00 to $1,000,000.00Roosevelt City Consolidated Fee Schedule, Resolution 2024-322.
$3,233.75 for the first $500,000.00 plus $4.75 for each additional $1,000.00 or fraction thereof
Building Permit Fee — $1,000,001.00 and upRoosevelt City Consolidated Fee Schedule, Resolution 2024-322.
$5,608.75 for the first $1,000,000.00 plus $3.65 for each additional $1,000.00 or fraction thereof
Water Impact Fee (new connection, 3/4"-6" meter)Roosevelt City Consolidated Fee Schedule, Resolution 2024-322, Water Fee Schedule, City New Installation Fees.
$5,000.00 (includes $3,500.00 hookup fee, or actual cost if greater); $200.00 inspection fee only if a contractor performs the connection to the City's main line
Sewer Connection — Residential (Single Family Dwelling)Roosevelt City Consolidated Fee Schedule, Resolution 2024-322, Sewer Fee Schedule.
$4,000.00 (City); $5,000.00 (County, for properties outside city limits on Roosevelt sewer)
Sewer Connection — DuplexThe Residential/Duplex Building Permit Application lists 'Sewer Connection-Duplex' as its own fee line, but Resolution 2024-322's Sewer Fee Schedule only publishes 'Single Family Dwelling' ($4,000 City / $5,000 County) and 'Commercial, Each Building in Multiple Dwellings or P.U.D.' ($5,500 City / $6,000 County) tiers — which of these applies to a duplex is not stated; confirm with the Building Department before budgeting.
Not separately itemized in the published fee schedule
Secondary Water Connection FeeRoosevelt City Consolidated Fee Schedule, Resolution 2024-322, Secondary Water Rates.
$500.00, required if the property is located in an area where secondary water service is available
Electrical InspectionRoosevelt City Consolidated Fee Schedule, Resolution 2024-322, Other Inspections and Fees.
$25.00
ShedRoosevelt City Consolidated Fee Schedule, Resolution 2024-322 — the application form lists 'Shed' as its own fee line; the source document confirms a shed fee exists but the exact dollar figure could not be reliably read from the retrieved PDF text extraction. Confirm with the Building Department before budgeting.
Fee amount not legible in the source PDF's 'Other Inspections and Fees' section (OCR-garbled column adjacent to Electrical/Gas Line Inspection entries)

Review timeline

Plan reviewRoosevelt’s published plan-review target
17–17 business days

How long did your Residential/Duplex Building Permit permit actually take in Roosevelt?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation

    Per the statewide-adopted construction code; 24-hour advance notice required.

  2. 2

    Framing

    Structural framing inspection prior to insulation/drywall.

  3. 3

    Final

    Final inspection prior to occupancy.

See the full Roosevelt inspection guide — scheduling & re-inspection fees →

Tips

  • Water and sewer connection fees differ substantially between City-limits and County (outside-city, Roosevelt-sewer) properties — confirm which rate tier applies before budgeting.
  • The published Sewer Fee Schedule does not separately itemize a 'Duplex' connection tier despite the application form listing one — call the Building Department at (435) 722-5001 to confirm whether a duplex is billed at the Single Family or Commercial/Multiple Dwelling rate.
  • Roosevelt City does not publish a distinct solar/photovoltaic permit, checklist, or fee line — its Building Department page and Consolidated Fee Schedule (Resolution 2024-322) list only the general valuation-based Building Permit Fee table plus a flat $25.00 Electrical Inspection fee, with no solar-specific mention found after a direct check (2026-07-19). A rooftop or ground-mounted solar PV installation is therefore priced and processed under this general Residential/Duplex Building Permit (valuation-based fee) plus the standard Electrical Inspection.
  • The same gap applies to EV chargers: Roosevelt's Consolidated Fee Schedule (Resolution 2024-322) has no EV-charger-specific or electric-vehicle line item (re-checked 2026-07-20) — a home charger installation would be billed the same way as other electrical work, under the Residential/Duplex Building Permit plus the flat $25.00 Electrical Inspection fee, not a dedicated EV rate.

Frequently asked questions

Roosevelt requires a residential/duplex building permit for: New single-family dwelling or duplex construction, addition, remodel, basement finish, detached garage, carport/patio cover, or shed within Roosevelt City limits; Duchesne County Assessor's Parcel Number for the job site; Utah-licensed general contractor's name and Utah State License #, or owner-builder designation; Water meter size (3/4" or 1") and whether the property has an existing water meter and sewer service; 24-hour advance notice required to schedule inspections, per the application form. If your project isn't listed, confirm with Roosevelt City Building Department at (435) 722-5001 (Building Department); Fax (435) 722-5000 before starting work.

Per Roosevelt City's Consolidated Fee Schedule (Resolution 2024-322), the base Building Permit Fee is valuation-based, starting at $23.50 for projects valued $1-$500 and scaling up (e.g., $993.75 plus $5.60 per additional $1,000 for $100,001-$500,000 valuations). Separate line items apply for the Water Impact Fee ($5,000 new connection), Sewer Connection ($4,000 Single Family Dwelling, City rate), Secondary Water ($500 connection fee where available), and a $25 Electrical Inspection fee.

Roosevelt does not publish its own plan-review turnaround time. Under Utah Code § 10-20-909, the city must screen a complete application within 3 business days, then complete plan review of a one- or two-family dwelling or duplex within 14 business days after the screening period ends — a statutory ceiling of 17 business days total.

You'll need: Residential/Duplex Building Permit Application. See the required-documents checklist on this page for details on each.

Roosevelt requires 3 inspection(s) for a residential/duplex building permit, in order: Footing/Foundation, Framing, Final. Schedule each through Roosevelt City Building Department ((435) 722-5001 (Building Department); Fax (435) 722-5000).

Apply through Roosevelt City Building Department at 255 South State Street, Roosevelt, UT 84066. Phone: (435) 722-5001 (Building Department); Fax (435) 722-5000, email: djohnson@rooseveltcity.com (Dean Johnson, Building Inspector); deschler@rooseveltcity.gov (Drew Eschler, Planning and Zoning Division Manager, (435) 725-7206). Office hours: Monday-Thursday, 7:30 a.m. to 5:30 p.m. (closed Fridays), per Roosevelt City's Building Department page.. Official information: https://www.rooseveltcity.gov/151/Building-Department.

Roosevelt, Utah has adopted: Roosevelt City does not separately publish IBC/IRC/IPC/IMC/IFGC/IECC/IEBC/NEC edition years on its Building Department page or on its own permit application forms. Both the Commercial Building Permit Application and the Residential/Duplex Building Permit Application state only: 'Decisions relative to this application are subject to review by the chief executive officer of the municipal or county entity issuing this building permit and appeal under the International Building Code as adopted by Legislature' — i.e., the city defers to whatever edition the Utah Legislature has adopted statewide, without itemizing it locally.; 2024 International Building Code (IBC), including Appendices C and J — Utah Code § 15A-2-103(1)(a); current statewide edition as of 7/1/2026 (2021 edition governed through 6/30/2026).; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); unchanged by the 7/1/2026 statewide revision.; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); current statewide edition as of 7/1/2026.; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); current statewide edition as of 7/1/2026.; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); current statewide edition as of 7/1/2026.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — Utah Code § 15A-2-103(1)(h); current as of 7/1/2026.; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); current statewide edition as of 7/1/2026.; 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); statewide by statute, not separately itemized by Roosevelt.; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); statewide in force, unchanged by the 7/1/2026 revision.; Roosevelt City Standard Specifications and Drawings (originally published March 2014, updated September 2015) — governs public infrastructure construction (streets, water, sewer, storm drain), referenced by the Street Right-of-Way Encroachment Permit; this is a public-works construction standard, not a building-code edition adoption, and does not itemize IBC/IRC edition years.. Local amendments apply — see the Roosevelt overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Roosevelt building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.