Demolition Permit — Roosevelt, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://www.rooseveltcity.gov/151/Building-Department
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Roosevelt, Utah
Required for demolition of residential or commercial structures within Roosevelt City limits. No fee is charged, but utility and infrastructure clearances must be obtained before the permit is issued.
Verified 2026-07-19 · Source
When you need this permit
- Demolition of a residential or commercial building within Roosevelt City limits
- Clearances required prior to issuance: Questar (natural gas), Moon Lake Electric, Roosevelt City Water/Sewer, and Strata Networks
- Asbestos inspection required if applicable
- Water and sewer laterals must be capped at the back of the sidewalk unless being re-used
- City must be notified by calling (435) 722-5001 when demolition is complete
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Demolition Inspection
Confirms site clearance and that water/sewer laterals were properly capped at the back of the sidewalk (unless re-used).
See the full Roosevelt inspection guide — scheduling & re-inspection fees →
Tips
- All four utility clearances (Questar, Moon Lake Electric, Roosevelt City Water/Sewer, Strata Networks) plus an asbestos inspection (if applicable) must be obtained BEFORE the demolition permit is issued — plan for this lead time even though the permit itself is free.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Roosevelt building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Roosevelt
Demolition Permit in other cities
Compare demolition permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Roosevelt project checklist
Describe your project once and get every permit, document, and fee it triggers in Roosevelt — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →