Unincorporated Millard County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Millard County, Utah.

Verified 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
71 South 200 West, PO Box 854, Delta, UT 84624
Phone
(435) 864-1400
Office hours
Monday–Thursday 8:00 AM – 5:30 PM; Friday 8:00 AM – 12:00 PM

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Footing / Foundation

    Before concrete pour — verify rebar placement and size, footing steps and continuity, venting requirements, and damp proofing, per the same inspection sequence documented for residential permits in this county.

  2. 2

    Framing

    After framing, sheathing, and rough-in MEP — before insulation or wall cover.

  3. 3

    Final

    All work complete, ready for occupancy.

Applies to: Residential Building Permit

  1. 1

    Footing / Foundation

    Before concrete pour — verify rebar placement and size, footing steps and continuity, venting requirements, and damp proofing

  2. 2

    Framing

    After framing, sheathing, and rough-in MEP — before insulation or wall cover

  3. 3

    Final

    All work complete, ready for occupancy

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural (if applicable)

    Verified before close-in where the tenant improvement scope includes framing or structural changes.

  2. 2

    Final

    All work complete, ready for occupancy.

Applies to: Electrical / Mechanical / Plumbing / Stucco Permit

  1. 1

    Rough-In

    After wiring, piping, or ductwork installed, before walls closed

  2. 2

    Final

    All work complete and operational

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed

  2. 2

    Final

    All work complete and operational

Applies to: Solar / Solar PV Installation Permit

  1. 1

    Rough-In

    After PV wiring, conduit, and interconnection equipment installed, before walls closed (where applicable)

  2. 2

    Final

    All work complete and operational, including utility interconnection sign-off where required

Unincorporated Millard County building permits

Get alerts for Unincorporated Millard County

We'll email you when Unincorporated Millard County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.