EV Charger / EVSE Permit — Unincorporated Millard County, Utah · Requirements sheet
Verified 2026-07-20 · Source: https://millardcounty.gov/wp-content/uploads/2017/04/Mechanical_Electrical_Plumbing_Permit.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Unincorporated Millard County, Utah
Millard County does not publish a distinct EV charger, EVSE, or electric vehicle charging station permit or fee. EV charger/EVSE installation is electrical work and falls under the county's combined Electrical/Mechanical/Plumbing/Stucco permit application, at the $45 residential (or $75 commercial/pivot) Electrical line item. The county's permit application form does not publish a separate EV-specific fee item.
Verified 2026-07-20 · Source
When you need this permit
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
- New dedicated electrical circuit and/or panel capacity to serve the charger, covered under the general Electrical line item
- Compliance with the 2023 National Electrical Code (NEC) per Utah Code § 15A-2-103(1)(g)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
After wiring installed, before walls closed
- 2
Final
All work complete and operational
See the full Unincorporated Millard County inspection guide — scheduling & re-inspection fees →
Tips
- Millard County does not have a separate EV-charger permit — EV charger (EVSE) installation is treated as standard electrical work, pulled under the $45 residential (or $75 commercial/pivot) Electrical line item on the county's combined Electrical/Mechanical/Plumbing/Stucco permit form.
- A re-inspection fee may be charged if the project is not ready for inspection at the time the inspection is ordered, per the permit application form.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Millard County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Millard County
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →