Commercial Building Permit in Unincorporated Millard County, Utah

Required for new commercial construction in unincorporated Millard County, regulated by the statewide-adopted 2024 IBC (Utah Code § 15A-2-103(1)(a), effective July 1, 2026). Millard County Building Department (Building Official Adam Richins) does not publish a distinct commercial building permit page, application form, or valuation-based fee schedule separate from the general process used for the Residential Building Permit — no published, dedicated commercial fee schedule appears on the county website, in any linked Building Forms PDF, or in the county's 2026 Adopted Budget, the same situation as for residential permits.

Reviewed 2026-08-02 · Source

When you need this permit

  • New commercial construction in unincorporated Millard County
  • Any structural modification, alteration, repair, move, demolition, or occupancy change of a commercial structure (UCA 17-27a-802)
  • Certified water source and adequate electrical service, consistent with the general building-permit conditions documented for residential permits in this county
  • All contractors/subcontractors must hold a current Utah State Contractor's license Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit Fee
As with the Residential Building Permit, the county publishes no dedicated valuation-based fee schedule for commercial construction — only flat fees for demolition and… Show full citationAs with the Residential Building Permit, the county publishes no dedicated valuation-based fee schedule for commercial construction — only flat fees for demolition and electrical/mechanical/plumbing/stucco permits are published countywide. Contact the Building Official (435-864-1400) directly for a project-specific commercial fee quote.
Not published — no dedicated commercial or general valuation-based fee schedule was located on millardcounty.gov, in any linked Building Forms PDF, or in the county's 2026 Adopted Budget as of 2026-07-19
Demolition Permit (as reference point for county-published flat fees)Millard County Demolition Application/Permit form (millardcounty.gov) — same flat fee applies to demolition of commercial or residential structures; listed for reference only.
$25.00 + 1% state surcharge ($0.25) = $25.25 total
Electrical Permit (Commercial or Pivot)
Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form; Show full citationMillard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form; the county's published fee schedule distinguishes a higher 'Commercial or Pivot' electrical rate ($75) from the residential rate ($45) (see the Electrical/Mechanical/Plumbing/Stucco Permit entry) — this is the ONE place the county's published fees do split by commercial vs. residential use.
$75.00

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in Unincorporated Millard County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing / Foundation

    Before concrete pour — verify rebar placement and size, footing steps and continuity, venting requirements, and damp proofing, per the same inspection sequence used for residential permits in this county.

  2. 2

    Framing

    After framing, sheathing, and rough-in MEP — before insulation or wall cover.

  3. 3

    Final

    All work complete, ready for occupancy.

See the full Unincorporated Millard County inspection guide — scheduling & re-inspection fees →

Tips

  • Millard County Building Department does not publish a dedicated commercial fee schedule online — this was confirmed by an exhaustive search of the county website, all linked Building Forms PDFs, and the county's 2026 Adopted Budget, mirroring the identical gap already documented for the county's Residential Building Permit. Call the Building Official (435-864-1400) directly for a project-specific commercial fee estimate.
  • The county's published fee schedule DOES distinguish a commercial rate from residential for one specific permit type — the standalone Electrical Permit ($75 commercial/pivot vs. $45 residential) — suggesting the county is capable of publishing commercial-specific rates but has simply not done so for the core Building Permit Fee.
  • Millard County Building Department also performs Delta City's building inspections under a 2020 interlocal arrangement — a commercial project in Delta may be reviewed by the same county staff; Fillmore City is NOT covered and continues to use Sunrise Engineering.

Frequently asked questions

Unincorporated Millard County requires a commercial building permit for: New commercial construction in unincorporated Millard County; Any structural modification, alteration, repair, move, demolition, or occupancy change of a commercial structure (UCA 17-27a-802); Certified water source and adequate electrical service, consistent with the general building-permit conditions documented for residential permits in this county; All contractors/subcontractors must hold a current Utah State Contractor's license. If your project isn't listed, confirm with Millard County Building Department at (435) 864-1400 before starting work.

Millard County has not published a commercial (or residential) valuation-based fee schedule online, despite an exhaustive search of the county website, Building Forms PDFs, and 2026 Adopted Budget. Contact the Building Official, Adam Richins, at 435-864-1400 for a project-specific fee estimate.

Unincorporated Millard County does not publish a plan-review timeline for this permit. Contact Millard County Building Department at (435) 864-1400 for current turnaround.

You'll need: Building Permit Pre-Application Worksheet; Construction Plans and Specifications; Legal Description & Plat Map; Zoning Designation. Depending on your project, Unincorporated Millard County may also ask for: Encroachment Permit from Millard County Road Department. See the required-documents checklist on this page for details on each.

Unincorporated Millard County requires 3 inspection(s) for a commercial building permit, in order: Footing / Foundation, Framing, Final. Schedule each through Millard County Building Department ((435) 864-1400).

Apply through Millard County Building Department at 71 South 200 West, PO Box 854, Delta, UT 84624. Phone: (435) 864-1400, email: buildingofficial@millardcounty.org. Office hours: Monday–Thursday 8:00 AM – 5:30 PM; Friday 8:00 AM – 12:00 PM. Official information: https://millardcounty.gov/your-government/county-departments/building-inspection/.

Unincorporated Millard County, Utah has adopted: 2021 International Residential Code (IRC) with State of Utah Amendments — per Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update. Millard County Building Inspection Department page (adopted codes list) also lists 2021 IRC.; 2024 International Building Code (IBC) with State of Utah Amendments — per Utah Code § 15A-2-103(1)(a), effective since July 1, 2026, superseding the 2021 IBC. NOTE: the Millard County Building Inspection Department page still lists 2021 IBC — the county page lags the statewide statutory update; the statute is controlling.; 2024 International Plumbing Code (IPC) with State of Utah Amendments — per Utah Code § 15A-2-103(1)(d), effective since July 1, 2026, superseding the 2021 IPC. NOTE: the county page still lists 2021 IPC — page lag, statute controls.; 2024 International Mechanical Code (IMC) with State of Utah Amendments — per Utah Code § 15A-2-103(1)(e), effective since July 1, 2026, superseding the 2021 IMC. NOTE: the county page still lists 2021 IMC — page lag, statute controls.; 2023 National Electrical Code (NEC) per Utah Code § 15A-2-103(1)(g), statewide in force and NOT changed by the July 1, 2026 update — NOTE: this is a separate, pre-existing discrepancy: Millard County's own Building Inspection page lists 2020 NEC (unrelated to the 2021→2024 code-edition transition affecting the other codes below). Contractors/homeowners should confirm current applicability with the Building Official as the county page lags the statewide amendment.; 2024 International Fuel Gas Code (IFGC) with State of Utah Amendments — per Utah Code § 15A-2-103(1)(f), effective since July 1, 2026, superseding the 2021 IFGC. NOTE: the county page still lists 2021 IFGC — page lag, statute controls.; 2024 International Energy Conservation Code (IECC), Residential & Commercial — per Utah Code § 15A-2-103(1)(h), effective since July 1, 2026, superseding the 2021 IECC. The statute adopts a single IECC edition with no residential/commercial split. NOTE: the county's own page still lists the 2021 IECC — page lag; the statute controls.; 2024 International Existing Building Code (IEBC) — per Utah Code § 15A-2-103(1)(i), effective since July 1, 2026. Not separately listed on the Millard County Building Inspection Department page (which has no IEBC entry at all) — included here because § 15A-2-103 adopts it statewide regardless of the county page's omission.; 2024 residential provisions of the International Swimming Pool and Spa Code (ISPSC) — per Utah Code § 15A-2-103(1)(n), effective since July 1, 2026. Not separately listed on the Millard County Building Inspection Department page (which has no ISPSC entry at all) — included here because § 15A-2-103 adopts it statewide regardless of the county page's omission.; Utah Wildland Urban Interface Code; NOTE: The July 1, 2026 statewide code-edition transition (2024 IBC/IPC/IMC/IFGC/IECC replacing 2021 editions, per Utah Code § 15A-2-103 version effective 7/1/2026) is in effect, and the statute version taking effect 1/1/2027 carries identical code editions. The 2021 IRC is unchanged by this transition. The International Fire Code is NOT adopted by § 15A-2-103 (it is addressed separately in Title 15A Chapter 5)..

Sources & verification

Key facts verified against official sources. Last reviewed 2026-08-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Millard County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Unincorporated Millard County.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.

Unincorporated Millard County's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Unincorporated Millard County yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Unincorporated Millard County lands. Privacy.