Commercial Tenant Improvement / Tenant Finish Permit — Monticello, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://www.monticelloutah.org/media/Consolidated%20fee%20Schedule/signed-ordinance-2026-06-consolidated-fee-schedule-update.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Tenant Improvement / Tenant Finish Permit in Monticello, Utah
Required for tenant improvement / tenant finish work inside an existing commercial building in Monticello (e.g., interior build-out following a shell permit, or remodel of existing commercial space). Monticello's Consolidated Fee Schedule maintains no separate tenant-improvement fee tier — tenant improvement work is billed under the same valuation-based Building Permit Fee table and the same $65.00-per-hour Commercial Plan Review fee as new commercial construction.
Verified 2026-07-19 · Source
When you need this permit
- Tenant improvement / tenant finish work, remodel, or change of occupancy inside an existing commercial building
- Utah law requires commercial building plans to be designed, drawn, and stamped by a Utah Licensed Architect or Engineer (Utah Code §§ 58-22-305 and 58-3a-304 — the exemption from stamped plans applies only to one- and two-family dwellings, not commercial structures)
- All commercial project work must be performed by licensed contractors — commercial owners may not act as their own contractor Contractor
- Legal description and San Juan County property tax parcel number
- Building permit application listing all contractors/subcontractors with current Utah Contractor license Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Framing / Structural / MEP Rough-In
Scope-dependent rough-in inspection(s) prior to close-in, per the Building Official.
- 2
Final Inspection
Final inspection and closeout prior to occupancy of the improved space.
See the full Monticello inspection guide — scheduling & re-inspection fees →
Tips
- Tenant improvement work in Monticello is not a separate fee category — it is billed under the identical valuation-based Building Permit Fee table and $65/hour Commercial Plan Review fee as ground-up commercial construction.
- Confirm with the Building Official whether your specific tenant-finish scope (e.g., non-structural interior partition changes only) requires architect/engineer-stamped plans, since Utah's stamped-plans exemption for one-/two-family dwellings does not apply to commercial space regardless of scope size.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Monticello building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Monticello.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Monticello
Commercial Tenant Improvement / Tenant Finish Permit in other cities
Compare commercial tenant improvement / tenant finish permit fees across Utah →
Look up this fee in a different city →