Residential Building Permit in Monticello, Utah
Required for new single-family and two-family residential construction, moving a trailer or pre-built home onto a lot, and any addition, remodeling, or demolition in Monticello. Fees are valuation-based per the city's Consolidated Fee Schedule; plan review must be completed within the statutory 14-business-day window (after a 3-business-day completeness screening period) required by Utah Code § 10-20-909 for one- and two-family dwellings and townhomes — Monticello's own New Residential Building Permit Checklist explicitly states this statutory figure to applicants.
Verified 2026-07-19 · Source
When you need this permit
- New single-family or two-family residential construction, moving a trailer/pre-built home onto a lot, or any addition, remodel, or demolition
- Complete set of plans drawn to scale, submitted to the Building Official for review (per the city's Plan Requirements sheet); plans for single-family residences generally need not be architect/engineer-stamped unless the Building Official deems it necessary given project scope/design
- Legal description and San Juan County property tax parcel number
- Building permit application filled out completely and signed by the owner or agent, listing all contractors/subcontractors with current Utah Contractor license (name, license number, licensed trades, expiration date), address, phone, and email Contractor
- Property must be deeded in the applicant's name and recorded in the San Juan County Recorder's Office before permit issuance (or a notarized statement from the legal owner granting permission to build)
- Owner-builders performing their own work on a personal, non-commercial single-family residence must submit the Owner Build Certification and Agreement prior to beginning construction, per the Utah Construction Trades Licensing Act; all commercial project work must be performed by licensed contractors — commercial owners may not act as their own contractor in Utah Owner-builderContractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Building Inspection
Conducted by the Monticello Building Official (Megan Gallegos, Assistant City Manager, 435-587-2271 ext. 15). Per Utah Code § 10-20-909(2)(b)-(c), if the city cannot provide a building inspection within 3 business days after receiving the inspection request, the applicant may engage a third-party inspection firm from the state's approved list (Utah Code § 15A-1-105), unless the applicant requested a later date.
- 2
Final Inspection
Final inspection and closeout coordinated through the Building Official prior to occupancy; no separate published Certificate of Occupancy timeline was found on the city's official pages as of 2026-07-08.
See the full Monticello inspection guide — scheduling & re-inspection fees →
Tips
- Monticello's Building and Zoning office is open Monday–Thursday 8:00 AM–4:30 PM and Friday 8:00 AM–12:00 PM (shortened Friday hours) — plan permit-office visits accordingly.
- The property must already be deeded in the applicant's name and recorded with the San Juan County Recorder's Office (or accompanied by a notarized owner-permission statement) before Monticello will issue a building permit — this is a local prerequisite on top of the state's plan-review completeness checklist.
- Investigation fees equal to the standard permit fee are charged in addition to normal permit fees if construction work begins before a permit is obtained, per the city's official Building Permits page.
- Owner-builders acting as their own contractor on a personal single-family residence must file the Owner Build Certification and Agreement before construction begins; unlicensed-contractor violations can be a class A misdemeanor plus an administrative fine up to $2,000 per day, per the Utah Construction Trades Licensing Act as cited on the city's page. Owner-builder
- Monticello's fee schedule has no separate flat fee for standalone electrical, plumbing, or mechanical trade permits (unlike some Utah cities) — those trades are covered under the same valuation-based Building Permit Fee table plus the flat Building Inspection Fee and Plan Review fee.
- Monticello has no distinct solar-PV permit type or fee line: the city's Consolidated Fee Schedule (signed ordinance 2026-06, as of 04/14/2026) contains no 'solar' entry anywhere in its Building Permit Fees or Miscellaneous Items sections, so rooftop or ground-mounted solar installations are permitted and charged through this same valuation-based Building Permit (confirmed against the full fee schedule PDF directly, 2026-07-19).
- Monticello likewise has no distinct EV charger / EVSE permit type or fee: the same signed ordinance 2026-06 Consolidated Fee Schedule PDF was re-checked directly (fetched and searched 2026-07-20) and contains zero mentions of 'EV,' 'electric vehicle,' 'charging station,' or 'EVSE.' Consistent with this file's note that Monticello has no separate standalone electrical trade-permit fee line, a residential EV charger install is expected to be priced under this same valuation-based Building Permit Fee table; confirm directly with the Building and Zoning office before applying.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Monticello building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Monticello
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Monticello project checklist
Describe your project once and get every permit, document, and fee it triggers in Monticello — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.