New Commercial Shell Building Permit — Pleasant Grove, Utah · Requirements sheet
Verified 2026-07-03 · Source: https://www.pgcityutah.gov/departments/community_development/fee_schedule.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
New Commercial Shell Building Permit in Pleasant Grove, Utah
Required for new commercial shell construction in Pleasant Grove, regulated by the state-adopted 2024 IBC (Utah Code § 15A-2-103(1)(a), effective 7/1/2026; with related Utah amendments referenced on the city's Building Division page, which itself still lists the 2021 IBC as of live re-check 2026-07-16).
Verified 2026-07-03 · Source
When you need this permit
- New commercial shell construction
- Electronic copy of plans and engineering
- Site plan to scale
- Structural engineering plan review
- Gas line layout with pipe sizes called out
- Heat loss analysis
- SWPPP (Storm Water Pollution Prevention Plan)
- Contractor license number or Owner-Builder Certification Form Owner-builderContractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footing
Before concrete pour, per standard IBC inspection sequence.
- 2
Framing
After framing, sheathing, and roof installed.
- 3
Final
All work complete before occupancy.
See the full Pleasant Grove inspection guide — scheduling & re-inspection fees →
Tips
- The $500 submittal fee applies specifically to new commercial shell construction; Commercial Remodel/Tenant Improvement is billed separately at $250.
- No published commercial-specific plan-review turnaround time exists; the 14-business-day figure on the city's page applies only to single-family residential per Utah Code § 10-6-160.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pleasant Grove building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Pleasant Grove.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Pleasant Grove
Compare new commercial shell building permit fees across Utah →
Look up this fee in a different city →