Sign Permit in La Verkin, Utah

Required for placing, constructing, erecting, or modifying a sign on a zone lot in La Verkin, per City Code title 10, chapter 11 (Sign Regulations). The property owner must secure and maintain a sign permit; fees are itemized separately in the Consolidated Fee Schedule under a dedicated 'Signs' category.

Verified 2026-07-19 · Source

When you need this permit

  • A permit is required if a sign requiring a permit under chapter 11 is to be placed, constructed, erected, or modified on a zone lot (La Verkin City Code 10-11-4)
  • The property owner must maintain the sign permit in force at all times
  • No sign permit will be issued for an existing or proposed sign unless it is consistent with chapter 11's requirements
  • Flag poles greater than 25 feet in height require a building permit including plans and specifications stamped by a licensed structural and electrical engineer
  • Off-premises nonconforming sign permits must be renewed annually, with disclosure of sign/property ownership, lease terms, construction cost and date, appraised fair market value, and depreciation schedule

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Initial Inspection (per zone lot)City of La Verkin Consolidated Fee Schedule (updated March 7, 2024), "Signs" section: "Initial inspection per zone lot, $75.00"
$75.00
Re-inspectionCity of La Verkin Consolidated Fee Schedule, "Signs" section
$42.00
Addition FeeCity of La Verkin Consolidated Fee Schedule, "Signs" section: "Addition fee, $50.00, per sign"
$50.00 per sign
Temporary Signs Extending Over Public Right-of-Way (private property)City of La Verkin Consolidated Fee Schedule, "Signs" section: "signs extending over public right of way temporary, private property, $25.00, per sign"
$25.00 per sign

Review timeline

Plan reviewLa Verkin’s published plan-review target
5–5 business days

How long did your Sign Permit permit actually take in La Verkin?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Initial Inspection

    Per zone lot, per the Consolidated Fee Schedule's Signs fee category

See the full La Verkin inspection guide — scheduling & re-inspection fees →

Tips

  • La Verkin's sign fees are itemized separately from general building permit fees in the Consolidated Fee Schedule's dedicated 'Signs' category: $75 initial inspection, $42 re-inspection, $50 per-sign addition fee, and $25 per-sign for temporary signs extending over the public right-of-way on private property.
  • The building inspector has 5 days to review a sign permit application for completeness and, if incomplete, must notify the applicant of specific deficiencies within that same window, per City Code 10-11-4(B).
  • Flag poles over 25 feet require a full building permit with engineer-stamped plans, not just the standard sign permit.
  • Off-premises nonconforming signs need annual permit renewal with detailed ownership and financial disclosures.

Frequently asked questions

La Verkin requires a sign permit for: A permit is required if a sign requiring a permit under chapter 11 is to be placed, constructed, erected, or modified on a zone lot (La Verkin City Code 10-11-4); The property owner must maintain the sign permit in force at all times; No sign permit will be issued for an existing or proposed sign unless it is consistent with chapter 11's requirements; Flag poles greater than 25 feet in height require a building permit including plans and specifications stamped by a licensed structural and electrical engineer; Off-premises nonconforming sign permits must be renewed annually, with disclosure of sign/property ownership, lease terms, construction cost and date, appraised fair market value, and depreciation schedule. If your project isn't listed, confirm with City of La Verkin Building Department (Building Inspection Division) at (435) 635-2581 before starting work.

Yes. The Consolidated Fee Schedule lists a dedicated 'Signs' category: $75 for the initial inspection per zone lot, $42 for re-inspection, $50 per sign for an addition fee, and $25 per sign for temporary signs extending over the public right-of-way on private property.

City Code 10-11-4(B) requires the building inspector to review an application for completeness within 5 days of receipt and, if incomplete, notify the applicant of specific deficiencies within that same period. No separate timeline for full plan approval is published.

You'll need: Sign Permit Application. Depending on your project, La Verkin may also ask for: Engineered Plans (flag poles over 25 feet only). See the required-documents checklist on this page for details on each.

La Verkin requires 1 inspection(s) for a sign permit, in order: Initial Inspection. Schedule each through City of La Verkin Building Department (Building Inspection Division) ((435) 635-2581).

Apply through City of La Verkin Building Department (Building Inspection Division) at 435 North Main Street, La Verkin, UT 84745. Phone: (435) 635-2581. Official information: https://www.laverkin.gov/forms.

La Verkin, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide-mandatory edition per Utah Code § 15A-2-103(1)(a), effective July 1, 2026. La Verkin City Code Title 9, Chapter 1, § 9-1-2 'Building Code Adopted' locally codifies 'the 2021 edition of the international building code' (last amended by Ord. 2024-06, 2-21-2024 — before the 2026 statewide flip); confirmed by a direct read of the full ordinance text via the Browser pane on 2026-07-16. codelibrary.amlegal.com/codes/laverkinut is in fact fully readable (the entire Chapter 1 text renders on a standard page load) — a prior note in this file calling it an unrenderable React app was incorrect and has been corrected. The city's own ordinance has not yet been updated to the 2024 edition; the statewide statute governs regardless, as La Verkin is bound as a Utah municipality under § 15A-1-204.; 2021 International Residential Code (IRC) — current statewide edition per Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update. La Verkin City Code § 9-1-3 'Residential Code Adopted' also names the 2021 edition (confirmed via direct read 2026-07-16) — city ordinance and statute agree here.; 2023 National Electrical Code (NEC) — current statewide edition per Utah Code § 15A-2-103(1)(g); unchanged by the July 1, 2026 statewide update. La Verkin City Code § 9-1-4 'Electrical Code Adopted' locally codifies the '2020 version of the national electrical code' (confirmed via direct read 2026-07-16) — a pre-existing lag on the city's own ordinance, predating and unrelated to the July 2026 flip (the statewide NEC cycle had already advanced past 2020 in an earlier update).; 2024 International Plumbing Code (IPC) — current statewide edition per Utah Code § 15A-2-103(1)(d), effective July 1, 2026. La Verkin City Code § 9-1-5 'Plumbing Code Adopted' locally codifies the '2021 version' (confirmed via direct read 2026-07-16) — not yet updated to the 2024 edition.; 2024 International Fuel Gas Code (IFGC) — current statewide edition per Utah Code § 15A-2-103(1)(f), effective July 1, 2026. La Verkin City Code § 9-1-6 'Fuel Gas Code Adopted' locally codifies the '2021 version' (confirmed via direct read 2026-07-16) — not yet updated to the 2024 edition.; 2024 International Mechanical Code (IMC) — current statewide edition per Utah Code § 15A-2-103(1)(e), effective July 1, 2026. La Verkin City Code § 9-1-7 'Mechanical Code Adopted' locally codifies the '2021 version' (confirmed via direct read 2026-07-16) — not yet updated to the 2024 edition.; International Fire Code (IFC) — La Verkin City Code § 9-1-8 'Fire Code Adopted' locally codifies 'the 2021 edition of the international fire code, as amended and adopted by the state,' referencing the state fire code at Utah Code Title 15A, Chapter 5 (confirmed via direct read 2026-07-16), enforced in coordination with Hurricane Valley Fire Special Service District. Utah Code § 15A-2-103 does not itemize the IFC — the state fire code is a separate provision under Title 15A, Chapter 5, not part of the § 15A-2-103(1) construction-code list, so the IFC edition is unaffected by the § 15A-2-103 July 1, 2026 flip.; International Wildland-Urban Interface Code — La Verkin City Code § 9-1-9 'Wildland-Urban Interface Code Adopted' locally codifies the '2020 edition' (confirmed via direct read 2026-07-16), which differs from the statewide baseline 2006 edition (with Division of Forestry, Fire, and State Lands amendments) available for local adoption under Utah Code § 15A-2-103(2) — a separate statutory provision from Subsection (1) and unaffected by the July 1, 2026 flip to the Subsection (1) codes.; 2024 International Energy Conservation Code (IECC) — current statewide edition per Utah Code § 15A-2-103(1)(h), effective July 1, 2026. La Verkin City Code § 9-1-10 'Energy Conservation Code Adopted' locally codifies the '2018 version' (confirmed via direct read 2026-07-16) — a substantial pre-existing lag on the city's own ordinance (predating even the prior 2021 statewide IECC cycle), unrelated to the July 2026 flip.; 2024 International Existing Building Code (IEBC) — current statewide edition per Utah Code § 15A-2-103(1)(i), effective July 1, 2026. La Verkin City Code § 9-1-12 'Existing Building Code Adopted' locally codifies the '2021 edition' (confirmed via direct read 2026-07-16) — not yet updated to the 2024 edition.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — current statewide edition per Utah Code § 15A-2-103(1)(n), effective July 1, 2026. La Verkin City Code § 9-1-13 'Swimming Pool And Spa Code Adopted' locally codifies the '2021 edition' (confirmed via direct read 2026-07-16) — not yet updated to the 2024 edition.; Modular Building Institute Standards 1200 and 1205 — adopted statewide per Utah Code § 15A-2-103(1)(o); La Verkin City Code Title 9, Chapter 1 does not separately address modular buildings, but the statewide standard applies regardless.. Local amendments apply — see the La Verkin overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the La Verkin building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.