Change of Use / Certificate of Occupancy Permit in Plain City, Utah
Plain City does not publish a standalone 'Change of Use Permit' application, checklist, or fee — no such document appears on the Forms & Applications page or the Consolidated Fee Schedule (Resolution #2024-07). Instead, a change in the use of land or of an existing building is governed by two general provisions of Plain City Code Title 10, Chapter 1: §10-1-7 (Certificate Of Occupancy), which requires that 'no land shall be used or occupied and no building hereafter structurally altered or erected shall be used or in use until a certificate of occupancy shall have been issued by the chief building official stating that the building or structure or the proposed use thereof, or the use of land, complies with the provisions of this title,' and §10-1-8 (Issuance Of Licenses And Permits), which bars any city official from issuing a permit or license that would conflict with the zoning title. In practice, a change of use in an existing commercial building is processed through the same 'Site Plan Application (Existing Commercial Building)' track documented in this file's Commercial Tenant Improvement entry (Doc 508, 7-day advance submittal before a Planning Commission meeting), paired with a Commercial Business License Application (Doc 383) if a business use is involved — that license application independently confirms Site Plan Approval from the Planning Commission is a prerequisite and requires sign-off from both the Fire Marshal and the Building Inspector before issuance. Unlike several other gap entries in this file, a real, distinct, published fee for this exact existing-building site-plan scenario does exist: Plain City's Fee Schedule (Resolution #2024-07, Exhibit A, Filing Fees section) lists 'Site Plan - existing building with no remodel — $100.00,' separate from the $200.00 new-building Site Plan fee, plus the $60.00/year Commercial Business License base fee if a business is being established.
Verified 2026-07-22 · Source
When you need this permit
- A change in the use of land, or of an existing building/structure, that does not involve new construction — processed as a same-track variant of Plain City's existing-building Site Plan review
- Site Plan Application (Existing Commercial Building) submitted at least 7 days prior to a Planning Commission meeting (2nd and 4th Thursdays of the month), per the official Doc 508 packet — the form itself asks generally 'what is being proposed' and is not restricted by its own text to same-use scenarios, though its packet title reads '(Existing Commercial Building - same use, minimal remodeling)'
- A detailed site plan showing parking, landscaping, the building footprint, and the proposed floor plan for the new use/business, including restrooms, windows, and outside doors, per the Doc 508 form
- Commercial Business License Application (Doc 383), if the new use is a business — requires prior Site Plan Approval from the Planning Commission, and sign-off from both the Fire Marshal and the Building Inspector before the license issues
- Certificate of Occupancy issued by the Chief Building Official under Plain City Code §10-1-7, confirming the new use of land or the building complies with Title 10 (Zoning Regulations)
- No permit or license affecting the change of use may be issued by any Plain City official if it would conflict with the zoning title, per Plain City Code §10-1-8
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final / Certificate of Occupancy Verification
Plain City Code §10-1-7 requires the Chief Building Official to issue a certificate of occupancy confirming the new use of land or building complies with Title 10 before that use may commence; no distinct change-of-use inspection sequence is separately published in the Required Inspections list (Doc 483).
See the full Plain City inspection guide — scheduling & re-inspection fees →
Tips
- Plain City has no separately named 'Change of Use Permit' — a change of use in an existing building is processed through the same Site Plan Application (Existing Commercial Building) track as a tenant improvement (7-day advance submittal, $100.00 fee), not the 30-day/$200.00 new-construction track.
- If the change of use involves a business, the Commercial Business License Application (Doc 383) is required in addition to the site plan — and that application's 'FOR OFFICE USE ONLY' section shows sign-off lines for the Fire Marshal, Building Inspector, Planning Commission, and City Council, confirming multiple departments review a use change even though no single 'change of use' fee is charged beyond the $100.00 site-plan fee and $60.00/year license fee.
- Plain City Code §10-1-7 requires a certificate of occupancy any time land or a building's use changes, and §10-1-8 bars any city official from issuing a permit or license that conflicts with the zoning title — together these are the actual legal levers enforcing a change-of-use review in the absence of a dedicated change-of-use permit application.
- The Site Plan Application (Existing Commercial Building) form itself is titled '(same use, minimal remodeling)' but its content is a generic existing-building site plan with a free-text 'what is being proposed' field — Plain City publishes no second, alternate application for an actual change of use, so this is the only applicable form found.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Plain City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Plain City
Change of Use / Certificate of Occupancy Permit in other cities
Compare change of use / certificate of occupancy permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Plain City project checklist
Describe your project once and get every permit, document, and fee it triggers in Plain City — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →