Solar PV Installation Permit — Plain City, Utah · Requirements sheet
Verified 2026-07-21 · Source: https://www.plaincityutah.gov/DocumentCenter/View/476/Residential-Solar-Plan-Submittal-Requirements
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV Installation Permit in Plain City, Utah
Plain City has a genuinely distinct Residential Solar Photovoltaic (PV) System Plan Submittal Requirements checklist (Doc 476) — a separate, solar-specific plan submittal list distinct from the general Residential Building Permit checklist (Doc 475) — but the underlying permit is still applied for and issued as a standard Building Permit Application through the city's Online Building Permit Portal, not as a separately named or separately priced permit type. No distinct dollar-figure solar-specific fee line is published, and Plain City's Consolidated Fee Schedule (Resolution #2024-07, Exhibit A, revision 06/06/2024) has no 'solar,' 'photovoltaic,' 'PV,' or general building-permit valuation line item anywhere in it. However, an independent second-pass re-chase (2026-07-21) found the actual governing fee mechanism the first pass missed: Plain City Municipal Code § 9-1-4, 'FEE SCHEDULE' (Title 9, Building Code, amd. Ord. 2025-08, 6-19-2025), expressly adopts Table 1-A of the 1997 Uniform Building Code as the valuation-based fee table governing all IBC-authorized building permit fees citywide — it is simply incorporated by reference in the municipal code rather than restated in the standalone Consolidated Fee Schedule resolution. See the fees array for the full table.
Verified 2026-07-21 · Source
When you need this permit
- Building Permit Application: property address, lot number, subdivision name; contractor name/phone/address and Utah State contractor's license number, or owner's name/phone/address if owner-contracted; valuation of project (cost of materials and labor) Contractor
- Site Plan: detailed site plan showing the location of the home, the electrical meter panel, any backfed sub-panelboards, and all PV system components on the property
- Mounting System detail: module mounting system specifications including required support spacing based on local wind and snow loads; note whether roof rafters are engineered trusses; type/size of roof rafters; type of roof covering (shingles, metal, or tile) and number of layers; spec sheets for any integrated grounding/bonding in the racking system
- One-Line Diagram: detailed diagram showing the type of PV system (single inverter with one or more module strings, a micro-inverter system, or an AC module system), the exact number and layout of modules and how they are connected (series or parallel), all wire types and sizes, conduit types and sizes, detailed grounding wiring/connections, the location of all circuits and system components on or in the house, and the ratings of all fuses or breakers
- Electrical Panel to be Backfed: identify which home electrical panel the PV system will backfeed and its location/rating, with photos of the service panel (including a photo of its interior label) and photos of the labels of any sub-panel that will be backfed
- Module Spec Sheets: PV module (solar panel) spec sheets showing STC-rated watts (Pmp), volts (Vmp), amps (Imp), open circuit voltage (Voc), and short circuit current (Isc); modules must be UL 1703 listed
- Inverter Spec Sheets: inverter manufacturer spec sheets showing the amount of watts/volts the inverter can safely handle and its max rated AC output amps/voltage; utility-tied inverters must be listed as 'utility interactive' meeting UL 1741 with ground fault protection
- Total Array Power (not required for micro-inverter systems): total watts, amps, volts, open circuit voltage (Voc at the coldest possible outside temperature, per NEC 690.7), and short circuit current the array can produce
- System Components: information on all other system components and how they will be installed, showing that all equipment is listed and rated for its voltage type (AC or DC) and amount of current it could be subjected to
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Power-To-Panel / Electrical
Electrical inspection of the PV system's backfed panel connection, done when wiring is complete enough for circuits to function once the power company energizes the meter base; all grounding systems must be in place, per Plain City's official Required Inspections list. No solar-specific inspection sequence is separately published — Plain City's Required Inspections list (Doc 483) contains no mention of solar, photovoltaic, or PV.
- 2
Final
Done when all items are complete and the installation is ready for occupancy/use; no personal items may be in the structure until occupancy is issued, per the Required Inspections list.
See the full Plain City inspection guide — scheduling & re-inspection fees →
Tips
- Plain City requires the Residential Solar Plan Submittal Requirements checklist (Doc 476) be reviewed and signed off item-by-item with the plan submittal — the document itself warns that 'building plans submitted without each item on this list are subject to longer review periods.'
- PV modules must be UL 1703 listed and utility-tied inverters must be UL 1741 listed ('utility interactive') with ground fault protection, per Doc 476 — have manufacturer spec sheets ready showing these listings before submitting.
- The solar plan submittal checklist requires photos of the existing service panel (including its interior label) and of any sub-panel to be backfed — not just a written description.
- No distinct solar permit fee is published anywhere on plaincityutah.gov, and the Consolidated Fee Schedule (Resolution #2024-07, Exhibit A) has no 'solar,' 'photovoltaic,' 'PV,' or base building-permit valuation line item — but that resolution isn't the whole story. Plain City Municipal Code § 9-1-4 (amd. Ord. 2025-08, 6-19-2025) adopts Table 1-A of the 1997 Uniform Building Code as the actual governing valuation-based fee formula for all building permits citywide, solar included; it's just cited by reference in the code rather than restated in the fee resolution. Submit your project's estimated valuation to the Building Department at (801) 731-4908 for the calculated figure.
- There is no separate solar-specific inspection in Plain City's official Required Inspections list (Doc 483) — a PV installation is verified through the same general Power-To-Panel/Electrical and Final inspections used for other electrical work.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-21.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Plain City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Plain City
Solar PV Installation Permit in other cities
Compare solar pv installation permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Plain City project checklist
Describe your project once and get every permit, document, and fee it triggers in Plain City — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →