Roy building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Roy, Utah.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
5051 South 1900 West, Roy, UT 84067
Phone
801-774-1040
Office hours
Monday–Thursday 8:00 a.m. to 5:00 p.m.; Friday 8:00 a.m. to Noon, per Roy City's own Building Official page (royutah.gov/_T21_R4.php), fetched 2026-07-03.

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Footing / Foundation

    Before concrete pour, per standard IBC inspection sequence enforced by Roy City; scheduled through the CityInspect / My City Inspector portal.

  2. 2

    Underground / Under-Slab MEP

    Plumbing, electrical, and mechanical rough-in below slab, before fill or pour.

  3. 3

    Framing / Four-Way Rough-In

    After framing, sheathing, roof, and MEP rough-in complete.

  4. 4

    Insulation

    After insulation installed, before drywall/wall coverings.

  5. 5

    Final / Certificate of Occupancy

    All work complete; scheduled via the online portal prior to occupancy.

Applies to: Residential Building Permit (One & Two Family Dwellings)

  1. 1

    Footing / Foundation

    Standard sequence per adopted 2021 IBC/IRC inspection points; scheduled through the CityInspect / My City Inspector portal.

  2. 2

    Framing

    After framing, sheathing, and MEP rough-in complete.

  3. 3

    Insulation

    After insulation installed, before drywall.

  4. 4

    Final

    All work complete; scheduled via the online portal prior to occupancy.

Applies to: Fire Sprinkler System Permit

  1. 1

    Flow Test

    One of the included inspections for a Fire Sprinkler System Permit.

  2. 2

    Hydrostatic Test

    One of the included inspections for a Fire Sprinkler System Permit.

  3. 3

    Final Inspection

    Final inspection of the installed fire sprinkler system.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Rough-In

    Wall framing and MEP rough-in for the TI/remodel scope, before closing walls.

  2. 2

    Final / Certificate of Occupancy

    Completed TI/remodel work verified before occupancy sign-off.

Applies to: Electrical / Plumbing / Mechanical Permit

  1. 1

    Rough-In

    Trade-specific rough-in inspection before closing walls.

  2. 2

    Final

    Final trade inspection scheduled via the CityInspect portal.

Applies to: Residential Addition / Remodel Permit

  1. 1

    Framing

    Wall framing and MEP rough-in for the addition/remodel area.

  2. 2

    Final

    Completed addition/remodel work verified before close-out.

Applies to: Residential Deck Permit

  1. 1

    Footing

    Before concrete pour for deck footings.

  2. 2

    Framing/Final

    Deck framing and guardrail/handrail compliance verified before final sign-off.

Applies to: Residential Reroof Permit

  1. 1

    Deck/Substrate

    After tear-off, before underlayment.

  2. 2

    Final

    Completed reroof inspection scheduled via the CityInspect portal.

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing.

  2. 2

    Solar Final

    Completed solar installation inspection scheduled via the CityInspect portal.