Fire Alarm System Permit in Roy, Utah

Roy City Fire Department (Fire Marshal's office) reviews and permits new fire alarm system installations as a distinct line item in the city's Consolidated Fee Schedule, separate from the general building permit and from fire sprinkler system permits. Fees cover one plan review and one inspection; re-reviews and additional inspections are billed at the same rate as the initial fee.

Verified 2026-07-20 · Source

When you need this permit

  • Fire Alarm Installation Plan Review must be submitted to and approved by Roy City Fire Department before permit issuance — per the Consolidated Fee Schedule (Ordinance 26-7), Fire Alarm Systems table
  • Fire Alarm System Permit fee includes one inspection; additional inspections are billed at the initial review fee rate

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Fire Alarm Installation Plan ReviewIncludes 1 plan review. Fire Alarm Installation Re-review is billed at the same rate ('Same as initial review fee'). Per Roy City Consolidated Fee Schedule (Ordinance 26-7), Fire Alarm Systems table, confirmed live at royutah.gov 2026-07-20 via direct page-image render to resolve column alignment (re-confirmed independently 2026-07-20 by re-rendering the live PDF, page 8, to a 200dpi PNG: the 'Fire Alarm Systems' table reads exactly 'Fire Alarm Installation Plan Review — $100.00').
$100.00
Fire Alarm System PermitIncludes 1 inspection. Fire Alarm System Plan Additional Inspections are billed at the same rate ('Same as initial review fee'). Same source as above.
$100.00

Review timeline

Plan review
Not published — contact the department

How long did your Fire Alarm System Permit permit actually take in Roy?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Fire Alarm Inspection

    Included inspection tied to the Fire Alarm System Permit fee; additional inspections billed separately per the fee schedule.

See the full Roy inspection guide — scheduling & re-inspection fees →

Tips

  • Roy City's fire alarm plan review ($100) and permit ($100) fees are flat, not size-tiered — unlike its fire sprinkler system fees, which scale by square footage.
  • This fee is separate from Roy City's general Fire Inspection Fees (Commercial $200, Alarm Inspections (1-hr) $100, Sprinkler Inspections (1-hr) $100) that appear elsewhere in the same fee schedule under recurring/annual fire inspections — confirm with Roy City Fire Department which fee applies to a new installation versus an annual inspection.

Frequently asked questions

Roy requires a fire alarm system permit for: Fire Alarm Installation Plan Review must be submitted to and approved by Roy City Fire Department before permit issuance — per the Consolidated Fee Schedule (Ordinance 26-7), Fire Alarm Systems table; Fire Alarm System Permit fee includes one inspection; additional inspections are billed at the initial review fee rate. If your project isn't listed, confirm with Roy City Community Development Department, Building Permits & Inspections at 801-774-1040 before starting work.

Per Roy City's Consolidated Fee Schedule (Ordinance 26-7), Fire Alarm Systems table: $100.00 for the plan review (includes 1 review) and $100.00 for the permit (includes 1 inspection). Re-reviews and additional inspections are billed at the same $100 rate.

Roy does not publish a plan-review timeline for this permit. Contact Roy City Community Development Department, Building Permits & Inspections at 801-774-1040 for current turnaround.

You'll need: Fire Alarm Installation Plan Review submittal. See the required-documents checklist on this page for details on each.

Roy requires 1 inspection(s) for a fire alarm system permit, in order: Fire Alarm Inspection. Schedule each through Roy City Community Development Department, Building Permits & Inspections (801-774-1040).

Apply through Roy City Community Development Department, Building Permits & Inspections at 5051 South 1900 West, Roy, UT 84067. Phone: 801-774-1040, email: ced@royutah.gov. Office hours: Monday–Thursday 8:00 a.m. to 5:00 p.m.; Friday 8:00 a.m. to Noon, per Roy City's own Building Official page (royutah.gov/_T21_R4.php), fetched 2026-07-03.. Official information: https://www.royutah.gov/departments/building_permits___inspections/index.php.

Roy, Utah has adopted: GOVERNING LAW: Utah Code § 15A-2-103 (le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), version effective 7/1/2026 (amended by Ch. 47, 2026 General Session), sets the statewide-mandatory construction code suite (Utah Code § 15A-1-204 — binds every municipality; local amendments permitted, a different edition is not). Roy City's Building Permits & Inspections page still displays the pre-7/1/2026 edition list; re-checked live 2026-07-16, page text is byte-identical to the earlier fetch: 'Roy City has adopted minimum design and construction requirements found in the state amended 2021 IBC, IPC, IMC, IFGC and IRC, as well as the 2020 NEC.' State law governs regardless of the page's lag; each line below states current law first, then the page's as-published (stale or omitted) text.; 2024 International Building Code (IBC), state-amended — per Utah Code § 15A-2-103(1)(a), effective 7/1/2026. Roy City's Building Permits & Inspections page still lists 'the state amended 2021 IBC' (live re-check 2026-07-16).; 2021 International Residential Code (IRC), state-amended, including Appendix AQ — per Utah Code § 15A-2-103(1)(b)/(c); this edition did NOT change in the 7/1/2026 flip. Matches Roy City's page, which lists 'the state amended ... IRC' as 2021 (live re-check 2026-07-16).; 2024 International Plumbing Code (IPC), state-amended — per Utah Code § 15A-2-103(1)(d), effective 7/1/2026. Roy City's page still lists 'the state amended 2021 ... IPC' (live re-check 2026-07-16).; 2024 International Mechanical Code (IMC), state-amended — per Utah Code § 15A-2-103(1)(e), effective 7/1/2026. Roy City's page still lists 'the state amended 2021 ... IMC' (live re-check 2026-07-16).; 2024 International Fuel Gas Code (IFGC), state-amended — per Utah Code § 15A-2-103(1)(f), effective 7/1/2026. Roy City's page still lists 'the state amended 2021 ... IFGC' (live re-check 2026-07-16).; 2023 National Electrical Code (NEC) — per Utah Code § 15A-2-103(1)(g); this edition did NOT change in the 7/1/2026 flip. Roy City's page still lists 'the 2020 NEC' (live re-check 2026-07-16) — this is a PRE-EXISTING discrepancy that predates and is unrelated to the 2026-07-01 code-cycle flip (the 2023 NEC has been state law since before this project's original review), of the same kind documented for American Fork's Solar Checklist and Provo's Building FAQ. Reported here as-published rather than corrected, per grounded-data policy of not inventing a fact the city's own source does not state.; 2024 International Energy Conservation Code (IECC), one statewide edition (no residential/commercial split) — per Utah Code § 15A-2-103(1)(h), effective 7/1/2026. Not mentioned anywhere on Roy City's Building Permits & Inspections page, its permit-information handouts, or its Consolidated Fee Schedule as of live re-check 2026-07-16; added here as a statute-sourced omission (applies statewide regardless of city publication), not fabricated.; 2024 International Existing Building Code (IEBC) — per Utah Code § 15A-2-103(1)(i), effective 7/1/2026. Not mentioned on any Roy City source reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — per Utah Code § 15A-2-103(1)(n), effective 7/1/2026. Not mentioned on any Roy City source reviewed as of live re-check 2026-07-16, despite the city offering a Residential Swimming Pools permit info page; added as a statute-sourced omission.; Modular Building Institute (MBI) Standards 1200 and 1205 — per Utah Code § 15A-2-103(1)(o), statewide-mandated for modular units. Not mentioned on any Roy City source reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; No International Fire Code (IFC) entry: § 15A-2-103 does not adopt the IFC — it is separately governed under Title 15A Chapter 5, outside the scope of this section. Roy City's page does not list an IFC edition either, so there is no mis-citation to correct here.; Roy City Design Criteria (site-specific structural values published alongside the adopted-codes statement on the same Building Permits & Inspections page): Ground Snow Load 40 psf; Wind Speed 120 mph, Exposure B or C; Seismic Design Category D0; Frost Depth 30 inches below grade.. Local amendments apply — see the Roy overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Roy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.