EV Charger / EVSE Permit in Roy, Utah

Roy City's Consolidated Fee Schedule (Ordinance No. 26-7) has no distinct "EV Charger" or "EVSE" line item. Under "Other Permits/OTC," it lists a single combined "Mechanical, Plumbing, and Electrical Permits" fee of $50.00 plus State Fee ($25 permit fee + $25 inspection fee), which is the fee category EV charger/EVSE installation falls under as electrical work.

Verified 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in Roy City
  • Work performed per Roy City's adopted electrical code

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Mechanical, Plumbing, and Electrical PermitRoy City Consolidated Fee Schedule (Ordinance No. 26-7), "Other Permits/OTC" section: "Mechanical, Plumbing, and Electrical Permits — $50.00 + State Fee ($25+$25 inspection fee)." No distinct EV Charger or EVSE fee category exists anywhere in the schedule (confirmed via full-text search of the document).
$50.00 + State Fee ($25 permit fee + $25 inspection fee)

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Roy?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Inspection

    Inspection of the charger circuit, panel, and grounding by Roy City Building Permits & Inspections.

See the full Roy inspection guide — scheduling & re-inspection fees →

Tips

  • Roy has no separate EV Charger fee category — file under the combined Mechanical, Plumbing, and Electrical Permit ($50.00 + State Fee).

Frequently asked questions

Roy requires an ev charger / evse permit for: Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in Roy City; Work performed per Roy City's adopted electrical code. If your project isn't listed, confirm with Roy City Community Development Department, Building Permits & Inspections at 801-774-1040 before starting work.

No. Roy City's Consolidated Fee Schedule has no distinct EV Charger line item; EVSE installation is billed under the combined Mechanical, Plumbing, and Electrical Permit fee of $50.00 plus a State Fee ($25 permit + $25 inspection).

Roy does not publish a plan-review timeline for this permit. Contact Roy City Community Development Department, Building Permits & Inspections at 801-774-1040 for current turnaround.

You'll need: Mechanical, Plumbing, and Electrical Permit Application. See the required-documents checklist on this page for details on each.

Roy requires 1 inspection(s) for an ev charger / evse permit, in order: Electrical Inspection. Schedule each through Roy City Community Development Department, Building Permits & Inspections (801-774-1040).

Apply through Roy City Community Development Department, Building Permits & Inspections at 5051 South 1900 West, Roy, UT 84067. Phone: 801-774-1040, email: ced@royutah.gov. Office hours: Monday–Thursday 8:00 a.m. to 5:00 p.m.; Friday 8:00 a.m. to Noon, per Roy City's own Building Official page (royutah.gov/_T21_R4.php), fetched 2026-07-03.. Official information: https://www.royutah.gov/departments/building_permits___inspections/index.php.

Roy, Utah has adopted: GOVERNING LAW: Utah Code § 15A-2-103 (le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), version effective 7/1/2026 (amended by Ch. 47, 2026 General Session), sets the statewide-mandatory construction code suite (Utah Code § 15A-1-204 — binds every municipality; local amendments permitted, a different edition is not). Roy City's Building Permits & Inspections page still displays the pre-7/1/2026 edition list; re-checked live 2026-07-16, page text is byte-identical to the earlier fetch: 'Roy City has adopted minimum design and construction requirements found in the state amended 2021 IBC, IPC, IMC, IFGC and IRC, as well as the 2020 NEC.' State law governs regardless of the page's lag; each line below states current law first, then the page's as-published (stale or omitted) text.; 2024 International Building Code (IBC), state-amended — per Utah Code § 15A-2-103(1)(a), effective 7/1/2026. Roy City's Building Permits & Inspections page still lists 'the state amended 2021 IBC' (live re-check 2026-07-16).; 2021 International Residential Code (IRC), state-amended, including Appendix AQ — per Utah Code § 15A-2-103(1)(b)/(c); this edition did NOT change in the 7/1/2026 flip. Matches Roy City's page, which lists 'the state amended ... IRC' as 2021 (live re-check 2026-07-16).; 2024 International Plumbing Code (IPC), state-amended — per Utah Code § 15A-2-103(1)(d), effective 7/1/2026. Roy City's page still lists 'the state amended 2021 ... IPC' (live re-check 2026-07-16).; 2024 International Mechanical Code (IMC), state-amended — per Utah Code § 15A-2-103(1)(e), effective 7/1/2026. Roy City's page still lists 'the state amended 2021 ... IMC' (live re-check 2026-07-16).; 2024 International Fuel Gas Code (IFGC), state-amended — per Utah Code § 15A-2-103(1)(f), effective 7/1/2026. Roy City's page still lists 'the state amended 2021 ... IFGC' (live re-check 2026-07-16).; 2023 National Electrical Code (NEC) — per Utah Code § 15A-2-103(1)(g); this edition did NOT change in the 7/1/2026 flip. Roy City's page still lists 'the 2020 NEC' (live re-check 2026-07-16) — this is a PRE-EXISTING discrepancy that predates and is unrelated to the 2026-07-01 code-cycle flip (the 2023 NEC has been state law since before this project's original review), of the same kind documented for American Fork's Solar Checklist and Provo's Building FAQ. Reported here as-published rather than corrected, per grounded-data policy of not inventing a fact the city's own source does not state.; 2024 International Energy Conservation Code (IECC), one statewide edition (no residential/commercial split) — per Utah Code § 15A-2-103(1)(h), effective 7/1/2026. Not mentioned anywhere on Roy City's Building Permits & Inspections page, its permit-information handouts, or its Consolidated Fee Schedule as of live re-check 2026-07-16; added here as a statute-sourced omission (applies statewide regardless of city publication), not fabricated.; 2024 International Existing Building Code (IEBC) — per Utah Code § 15A-2-103(1)(i), effective 7/1/2026. Not mentioned on any Roy City source reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — per Utah Code § 15A-2-103(1)(n), effective 7/1/2026. Not mentioned on any Roy City source reviewed as of live re-check 2026-07-16, despite the city offering a Residential Swimming Pools permit info page; added as a statute-sourced omission.; Modular Building Institute (MBI) Standards 1200 and 1205 — per Utah Code § 15A-2-103(1)(o), statewide-mandated for modular units. Not mentioned on any Roy City source reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; No International Fire Code (IFC) entry: § 15A-2-103 does not adopt the IFC — it is separately governed under Title 15A Chapter 5, outside the scope of this section. Roy City's page does not list an IFC edition either, so there is no mis-citation to correct here.; Roy City Design Criteria (site-specific structural values published alongside the adopted-codes statement on the same Building Permits & Inspections page): Ground Snow Load 40 psf; Wind Speed 120 mph, Exposure B or C; Seismic Design Category D0; Frost Depth 30 inches below grade.. Local amendments apply — see the Roy overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Roy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.