Change of Use / Occupancy Permit in Washington Terrace, Utah
Washington Terrace has no standalone change-of-use permit, certificate-of-occupancy application, or associated fee line distinct from its general Building Permit. Municipal Code § 15.02.010 (Ordinance 2009-02) expressly lists 'occupancy' as its own independent permit trigger, alongside construction, alteration, repair, removal, and modification: 'A building permit or comprehensive construction permit is required for the construction, alteration, repair, removal, modification, or occupancy of any structure within the city limits.' A pure use/occupancy change with no construction scope is therefore filed and processed as the same Building/Excavation Permit used for new construction, nominally valued under the ICC 'Building Valuation Data' mechanism in § 15.02.020 — a mechanism that is inherently tied to construction cost and does not itemize a fee for an occupancy change involving little or no construction value, which is a genuine gap in the city's published fee structure rather than a $0 fee. Separately, Municipal Code § 15.14.130(7) confirms the city does formally issue a 'permanent certif[icate] of occupancy' following final inspection (referenced there only as a security-forfeiture trigger for excavation permits), and § 15.16.010 bars utility companies from connecting service to a structure 'until approval is granted by the building official' — both confirming occupancy approval is a real, distinct step in the city's process even though it is not sold as its own permit product. Most occupants of commercial space undergoing a use change will also separately need a City of Washington Terrace business license (base fee $102.00 plus a category-specific 'disproportionate' fee, per the FY 2026-27 Consolidated Fee Schedule's Business Licenses table).
Verified 2026-07-22 · Source
When you need this permit
- A change in use or occupancy classification of an existing structure, with or without accompanying construction, triggers the same building-permit requirement as new construction, per Municipal Code § 15.02.010
- Obtain any required land use authority approval before permit application, per § 15.02.010(1)
- Complete a building permit application filed with the Chief Building Official, per § 15.02.010(2)
- Comply with the adopted International Existing Building Code (Municipal Code § 15.06.010) where the change of use involves an existing building rather than new construction
- Submit the site to regular inspection until final occupancy is authorized, per § 15.02.010(7)
- Utility service to the structure cannot be connected or continued without building-official approval, per § 15.16.010
- A new City of Washington Terrace business license is separately required for most new commercial occupants, per the FY 2026-27 Consolidated Fee Schedule's Business Licenses table
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Building/Occupancy Inspection
Scheduled by calling (801) 395-8288 or (801) 393-8681, weekdays 9am-4pm, with 24-hour advance notice required; verifies the space complies with the adopted IBC/IEBC for the new occupancy classification before final occupancy is authorized, per Municipal Code § 15.02.010(7).
See the full Washington Terrace inspection guide — scheduling & re-inspection fees →
Tips
- There is no standalone change-of-use or certificate-of-occupancy permit product in Washington Terrace — Municipal Code § 15.02.010 treats 'occupancy' as its own trigger under the same general Building/Excavation Permit used for new construction, so apply through that same process.
- Because the city's only published fee mechanism (§ 15.02.020) is tied to ICC construction valuation, a pure occupancy change with little or no construction cost has no clearly published dollar figure — confirm the fee directly with the Building Department (801-395-8288) rather than assuming it is free.
- Don't forget the separate Business License requirement — most new commercial tenants changing use will owe a $102 base license fee plus a category-specific disproportionate fee, tracked independently of the building-permit/change-of-use process.
- Utility companies are barred by Municipal Code § 15.16.010 from connecting service to a structure until the building official grants approval — in practice this is one of the city's real enforcement levers over occupancy changes even without a dedicated CO permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Washington Terrace building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Washington Terrace
Change of Use / Occupancy Permit in other cities
Compare change of use / occupancy permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Washington Terrace project checklist
Describe your project once and get every permit, document, and fee it triggers in Washington Terrace — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →