EV Charger / EVSE Permit in Washington Terrace, Utah
Washington Terrace has not published a distinct EV-charger permit or fee category. The city's FY 2026-27 Consolidated Fee Schedule lists 'Electrical' as one of its 'Building Permits - Over-the-Counter' categories (alongside HVAC, Plumbing, Gas line, Roofing, Siding, and Window & Door), with the fee set by reference to the current ICC Building Permit Fee Schedule per note 3.2 — the same valuation mechanism used for all other building permits. EV charger/EVSE installation is electrical work filed under this over-the-counter Electrical permit category.
Verified 2026-07-20 · Source
When you need this permit
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property, filed as an 'Electrical' over-the-counter building permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Washington Terrace City FY 2026-27 Consolidated Fee Schedule (Resolution 26-08, adopted 6/26), 'Building Permits - Over-the-Counter' table lists 'Electrical' as a category with no dollar figure,… Show full citationHide
Washington Terrace City FY 2026-27 Consolidated Fee Schedule (Resolution 26-08, adopted 6/26), 'Building Permits - Over-the-Counter' table lists 'Electrical' as a category with no dollar figure, subject to note 3.2: 'Refer to the permit fee schedule released in the current International Code Council (ICC).' No distinct EV-charger line item exists.Review timeline
Inspection process
- 1
Electrical Inspection
Scheduled through the Washington Terrace Building, Planning & Inspection Department; a (Re)Inspection No-Show Fee and Reinspection Fee apply per the Consolidated Fee Schedule if missed or failed.
See the full Washington Terrace inspection guide — scheduling & re-inspection fees →
Tips
- Washington Terrace has no dedicated EV-charger permit or fee category — file the install as an over-the-counter 'Electrical' building permit, valued under the same ICC-referenced Building Permit Fee Schedule as other trade permits.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Online permit portal
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Washington Terrace building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Washington Terrace's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Washington Terrace yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Washington Terrace lands. Privacy.
Other permits in Washington Terrace
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →