Commercial Tenant Improvement Permit in Cheyenne, Wyoming

Verified

Required for interior build-out, remodeling, or change-of-use work in commercial spaces in Cheyenne. Valuation-based, and commercial plan review runs a longer 21-business-day timeline than residential.

Verified 2026-07-01 · Source

Varies by project valuation — see Building and Construction Permit Fee table under residential-building-permitBuilding and Construction Permit Fee — valuation-based

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Building and Construction Permit Fee — valuation-basedVaries by project valuation — see Building and Construction Permit Fee table under residential-building-permitCity of Cheyenne Schedule of Fees (Ordinance 4254); same table applies to commercial and residential work
Change of Use Permit (minimum fee)$250.00City of Cheyenne Schedule of Fees — Misc. Building and Construction Permit Fees (Ordinance 4254)
Commercial Master Plan Code Review$250.00City of Cheyenne Schedule of Fees — Misc. Building and Construction Permit Fees (Ordinance 4254)
Subsequent Code Reviews of Commercial Master Plan25% of the original feeCity of Cheyenne Schedule of Fees (Ordinance 4254)
Temporary Certificate of Occupancy — Commercial Structures$1,250.00City of Cheyenne Schedule of Fees — Misc. Building and Construction Permit Fees (Ordinance 4254)
Plan Review Fee65% of the Building Permit FeeCity of Cheyenne Schedule of Fees (Ordinance 4254)

Review timeline

1021 business days

Cheyenne’s published plan-review target

Inspection process

  1. 1

    Rough-In (MEP)

    Mechanical, electrical, plumbing rough-in before walls closed

  2. 2

    Fire/Life Safety

    Fire alarm, sprinkler, and egress verification as applicable — reviewed in coordination with Cheyenne Fire Rescue

  3. 3

    Final

    All work complete, ready for Certificate of Occupancy

Tips

Frequently asked questions

How long does commercial plan review take in Cheyenne?
Up to 21 business days after a complete application is submitted, per the Building Safety Department's Plan Review Information handout. Residential review is faster, at up to 10 business days.

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cheyenne building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Cheyenne

Related guides

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.