Skip to main content
PermitBase

Tombstone building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Tombstone, Arizona.

Verified 2026-07-07 · Source

How to schedule

Inspections are requested through the building department below.

Address
611 E. Allen Street, Tombstone, AZ 85638 (City Hall: 613 E. Allen Street, Tombstone, AZ 85638)
Phone
520-457-3415
Office hours
Monday - Friday, 8:00 AM - 5:00 PM (City of Tombstone Building Inspector page and Building Permit Application, Rev. 1/2024). Building Official/Inspector: Robert Hendrickson. Applications are submitted in person or by mail to the Building Department (P.O. Box 339, Tombstone, AZ 85638); the City does not appear to offer an online e-permitting portal as of the last verification — all forms found are static PDFs requiring paper/email submittal. Inspections are scheduled by calling 520-457-3415. Projects within the Schieffelin Historic District require Historic Preservation Commission (HPC) approval BEFORE building permit submission/approval, per the Building Permit Application's own header notice.

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Land Clearing

    Before and after any land clearing

  2. 2

    Foundation Pad

    Before work begins on the completed foundation pad

  3. 3

    Pre-Concrete / Sub-Floor

    Before placing concrete work or laying sub-floors or framed first floors

  4. 4

    Framing / Drywall / Lathing

    After nailing and before covering framing, drywall, or lathing, including exterior sheathing and roof decking

  5. 5

    Rough-In (Plumbing, Mechanical, Electrical)

    Combined rough-in inspection for all three trades

  6. 6

    Gas Piping Test

    After installation of gas lines, confirming the gas piping test

  7. 7

    Pre-Tape/Paint Drywall

    After nailing of drywall and before taping and painting

  8. 8

    Final Plumbing, Mechanical, Electrical

    Final inspection of all three trades

  9. 9

    Final Interior

    Completed interior work verified

  10. 10

    Final Exterior

    Completed exterior work verified

  11. 11

    Certificate of Occupancy

    Required before the building may be occupied or used — the same published 11-stage sequence applies to commercial and residential work alike; the application publishes no separate commercial inspection track

Applies to: Residential Building Permit (New Construction)

  1. 1

    Land Clearing

    Before and after any land clearing

  2. 2

    Foundation Pad

    Before work begins on the completed foundation pad

  3. 3

    Pre-Concrete / Sub-Floor

    Before placing concrete work or laying sub-floors or framed first floors

  4. 4

    Framing / Drywall / Lathing

    After nailing and before covering framing, drywall, or lathing, including exterior sheathing and roof decking

  5. 5

    Rough-In (Plumbing, Mechanical, Electrical)

    Combined rough-in inspection for all three trades

  6. 6

    Gas Piping Test

    After installation of gas lines, confirming the gas piping test

  7. 7

    Pre-Tape/Paint Drywall

    After nailing of drywall and before taping and painting

  8. 8

    Final Plumbing, Mechanical, Electrical

    Final inspection of all three trades

  9. 9

    Final Interior

    Completed interior work verified

  10. 10

    Final Exterior

    Completed exterior work verified

  11. 11

    Certificate of Occupancy

    Required before the structure may be occupied or used

Applies to: Change of Use / Certificate of Occupancy

  1. 1

    Certificate of Occupancy Inspection

    The building inspector inspects the building or premises before issuing the certificate; for an existing building requested under Section 10-17-3(C) the inspector certifies, after inspection, the extent and kind of use and whether that use conforms to the chapter

  2. 2

    Construction Inspections (if work is performed)

    Any construction, reconstruction, alteration or repair accompanying the change of use is inspected under the City's building permit. Re-inspections are $100.00 per hour and inspections outside normal business hours (7:00 AM–3:30 PM) are $100.00 per hour with a two-hour minimum (Fee Schedule effective 11/14/2025).

  3. 3

    Final Certificate of Occupancy

    The building inspector issues a final certificate of occupancy after the change in use has been completed, provided the building or premises and the proposed use conform with all requirements of the chapter (Section 10-17-3(A))

Applies to: Plumbing Permit

  1. 1

    Rough-In

    After pipes installed, before walls closed; part of the combined Plumbing/Mechanical/Electrical rough-in stage

  2. 2

    Gas Piping Test

    After installation of gas lines, dedicated gas piping test inspection

  3. 3

    Final

    Fixtures connected and verified per the 1988 UPC as adopted; part of the combined Final Plumbing/Mechanical/Electrical stage

Applies to: Residential Addition / Remodel Permit

  1. 1

    Pre-Concrete / Framing

    Before concrete pour or before covering new framing/drywall for the addition/remodel scope

  2. 2

    Rough-In (Plumbing, Mechanical, Electrical)

    Where applicable to the remodel scope

  3. 3

    Final

    Completed work verified against approved plans

Applies to: Electric Vehicle (EV) Charger / Charging Station Permit

  1. 1

    Rough-In

    EV charger circuit wiring, box placement, and panel connections before walls are closed, per the same combined electrical rough-in stage documented in the Electrical Permit entry.

  2. 2

    Final

    Charger installed and connections verified per the 1988 NEC as adopted.

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring, box placement, and panel connections before walls are closed; part of the combined Plumbing/Mechanical/Electrical rough-in inspection stage

  2. 2

    Final

    Devices installed and connections verified per the 1988 NEC as adopted; part of the combined Final Plumbing/Mechanical/Electrical inspection stage

Applies to: Manufactured Building / Manufactured Home Installation Permit

  1. 1

    Set/Placement Inspection

    First of the two inspections included in the flat fee, verifying placement/foundation/tie-down compliance

  2. 2

    Final/Utility Connection Inspection

    Second of the two inspections included in the flat fee, verifying utility connections and final site compliance

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and equipment placement before walls closed; part of the combined Plumbing/Mechanical/Electrical rough-in stage

  2. 2

    Final

    Equipment operational, clearances verified; part of the combined Final Plumbing/Mechanical/Electrical stage

Applies to: Residential/Commercial Solar Photovoltaic (PV) Permit

  1. 1

    Rough-In (Electrical/Interconnection)

    Array wiring, disconnect placement, and conduit before energizing; part of the combined Plumbing/Mechanical/Electrical rough-in inspection stage documented elsewhere in this record.

  2. 2

    Final Electrical

    Devices installed and connections verified per the adopted NEC before utility interconnection; part of the combined Final Plumbing/Mechanical/Electrical inspection stage.

Applies to: Sign Permit

  1. 1

    Sign Inspection

    All signs existing at the time of passage of Chapter 14, and any signs erected in the future that require a permit, are subject to inspection (Tombstone City Code Section 10-14-17). The $100.00 one-sign fee covers the initial inspection plus one additional inspection; further inspections are $50.00 each (Fee Schedule effective 11/14/2025).

  2. 2

    Historic Preservation Inspector Sign-off

    The HPC Certificate of Appropriateness application carries a 'For Office Use Only' block with a Building Official Recommendation (Recommended / Not Recommended for Approval) and a signature line for the Historic Preservation Inspector (HPC Application, Rev. 3/3/2026)

Final inspection only: Demolition Permit

Re-inspection fees

Commercial Building PermitRe-Inspection / After-Hours Inspection · City of Tombstone Fee Schedule (effective 11/14/2025), 'Inspections Not Included in Building Permit' section.
$100.00 per hour (re-inspection); $100.00 per hour with 2-hour minimum for inspections outside normal business hours (7:00 AM-3:30 PM)

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Tombstone building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Tombstone building permits

Get alerts for Tombstone

We'll email you when Tombstone's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.