Residential Building Permit (New Construction) — Tombstone, Arizona · Requirements sheet
Verified 2026-07-07 · Source: https://cityoftombstoneaz.gov/building-inspector/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction) in Tombstone, Arizona
Required for new single-family residential construction within Tombstone city limits. Reviewed against the City's own 2006 IRC/IBC adoption (Tombstone City Code Section 3-1-1). Applications use the City's single unified Building Permit Application (covering residential and commercial work alike) and are submitted in person or by mail to the Building Department. Properties within the Schieffelin Historic District require Historic Preservation Commission (HPC) Certificate of Appropriateness approval BEFORE the building permit may be submitted/approved.
Verified 2026-07-07 · Source
When you need this permit
- Building permit required for new single-family dwelling construction within Tombstone city limits, per Tombstone City Code Section 3-1-1 (Adoption of Building Codes)
- Plans reviewed against the City's adopted 2006 IRC/IBC (Tombstone City Code Section 3-1-1) — an older code cycle than most Arizona peer cities, confirmed via the codified City Code and the AZBO statewide directory
- Minimum one project drawing set at 1/4 inch = 1 foot scale (minimum 8.5x11 sheet), including Plat Plan, Floor Plan, Exterior Elevations, Crosscut Sections, Mechanical Plan, Plumbing Plan, and Electrical Plan (see localAmendments for full detail)
- A.R.S. Title 32 contractor-licensing compliance required: identify as a licensed ROC contractor or claim a specific Owner/Builder exemption (32-1121A.5 or 32-1121A.6); the Handyman Exemption (32-1121A.14) does NOT apply to any project requiring a building permit Owner-builderContractor
- Properties within the Schieffelin Historic District (checkbox on the application itself) require HPC Certificate of Appropriateness approval BEFORE building permit submission/approval
- Permit expires 6 months from issuance; extension of up to 60 additional days available upon application
- 11-stage inspection sequence required, scheduled by calling 520-457-3415, culminating in a Certificate of Occupancy before the structure may be occupied
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
City of Tombstone Fee Schedule, effective November 14, 2025 (adopted by Resolution No. Show full citationHide
City of Tombstone Fee Schedule, effective November 14, 2025 (adopted by Resolution No. 10-2025, passed October 14, 2025). Valuations calculated from price-per-square-foot construction costs as published biannually by the International Code Council. NOTE: the source document contains internal arithmetic/labeling inconsistencies in three tiers (the $50,001+, $100,001+, $500,001+, and $1,000,000.01+ rows all say 'for the first $2,000.00' where context indicates this should read the first $50,000 / $100,000 / $500,000 / $1,000,000 respectively, matching the tier's own bracket boundary) — the bracket boundaries and per-unit marginal rates are transcribed exactly as published; the 'for the first $X' base amounts are reproduced as literally printed by the City despite the apparent labeling typo, since no corrected version was located.Review timeline
Inspection process
- 1
Land Clearing
Before and after any land clearing
- 2
Foundation Pad
Before work begins on the completed foundation pad
- 3
Pre-Concrete / Sub-Floor
Before placing concrete work or laying sub-floors or framed first floors
- 4
Framing / Drywall / Lathing
After nailing and before covering framing, drywall, or lathing, including exterior sheathing and roof decking
- 5
Rough-In (Plumbing, Mechanical, Electrical)
Combined rough-in inspection for all three trades
- 6
Gas Piping Test
After installation of gas lines, confirming the gas piping test
- 7
Pre-Tape/Paint Drywall
After nailing of drywall and before taping and painting
- 8
Final Plumbing, Mechanical, Electrical
Final inspection of all three trades
- 9
Final Interior
Completed interior work verified
- 10
Final Exterior
Completed exterior work verified
- 11
Certificate of Occupancy
Required before the structure may be occupied or used
See the full Tombstone inspection guide — scheduling & re-inspection fees →
Tips
- Tombstone's Building Permit Application is a single unified form (residential and commercial alike) with a bolded, underlined notice at the top: properties within the Schieffelin Historic District need HPC Certificate of Appropriateness approval BEFORE the building permit is even submitted for approval — plan for the HPC's own review timeline (21 days for the inspector's report to reach the Commission, then a Commission vote) as an added front-end step, not a parallel one.
- Tombstone's adopted building code cycle (2006 IBC/IRC, 1988 NEC, 1988 UPC) is unusually old compared to Cochise County peers (Bisbee: 2018 codes/2017 NEC; Benson: 2024 codes/2023 NEC as of 2026) — confirmed via both the codified City Code text and the AZBO statewide directory search; no updated code-adoption ordinance was found despite the City Code being current through Ord. 2025-06 (Oct. 14, 2025), meaning the 2025-06 ordinance amended a different Title, not the Building Code chapter.
- Plan review timeline: as of July 2026, the City of Tombstone does not publish a permit-specific plan review turnaround time (business or calendar days) anywhere in its public materials. The City's Building Permit Application (Rev. 1/2024) describes required drawings and inspections but states no review-day figure. The City's November 14, 2025 Fee Schedule (adopted via Resolution No. 10-2025) itemizes plan review fees in detail (65% of permit fee, hourly rates, etc.) but never states a turnaround time. Tombstone City Code Title 3 (Building Code, hosted at amlegal.com) sets permit expiration (6 months + 60-day extension) but contains no plan-review SLA. A.R.S. Section 9-835 (a statute requiring municipalities to establish and post their own time frame per license/permit type on their own website) has produced no dedicated Tombstone time-frame chart or posting on cityoftombstoneaz.gov, unlike larger AZ cities (e.g., Buckeye) that publish one; note A.R.S. 9-835 itself does not supply a statutory default number if a municipality hasn't posted one — it only requires municipalities to post their own. Neither the Planning & Zoning page nor the Building Inspector page references a turnaround time. This is a genuine gap in the City's published materials. Call the Building Official (Robert Hendrickson, 520-457-3415, buildingofficial@cityoftombstoneaz.gov) for a current estimate.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Tombstone building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Tombstone's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Tombstone yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Tombstone lands. Privacy.
Other permits in Tombstone
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Arizona →
Look up this fee in a different city →