Required for new single-family residential construction within Tombstone city limits. Reviewed against the City's own 2006 IRC/IBC adoption (Tombstone City Code Section 3-1-1). Applications use the City's single unified Building Permit Application (covering residential and commercial work alike) and are submitted in person or by mail to the Building Department. Properties within the Schieffelin Historic District require Historic Preservation Commission (HPC) Certificate of Appropriateness approval BEFORE the building permit may be submitted/approved.

Verified 2026-07-07 · Source

When you need this permit

  • Building permit required for new single-family dwelling construction within Tombstone city limits, per Tombstone City Code Section 3-1-1 (Adoption of Building Codes)
  • Plans reviewed against the City's adopted 2006 IRC/IBC (Tombstone City Code Section 3-1-1) — an older code cycle than most Arizona peer cities, confirmed via the codified City Code and the AZBO statewide directory
  • Minimum one project drawing set at 1/4 inch = 1 foot scale (minimum 8.5x11 sheet), including Plat Plan, Floor Plan, Exterior Elevations, Crosscut Sections, Mechanical Plan, Plumbing Plan, and Electrical Plan (see localAmendments for full detail)
  • A.R.S. Title 32 contractor-licensing compliance required: identify as a licensed ROC contractor or claim a specific Owner/Builder exemption (32-1121A.5 or 32-1121A.6); the Handyman Exemption (32-1121A.14) does NOT apply to any project requiring a building permit Owner-builderContractor
  • Properties within the Schieffelin Historic District (checkbox on the application itself) require HPC Certificate of Appropriateness approval BEFORE building permit submission/approval
  • Permit expires 6 months from issuance; extension of up to 60 additional days available upon application
  • 11-stage inspection sequence required, scheduled by calling 520-457-3415, culminating in a Certificate of Occupancy before the structure may be occupied

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on ValuationCity of Tombstone Fee Schedule, effective November 14, 2025 (adopted by Resolution No. 10-2025, passed October 14, 2025). Valuations calculated from price-per-square-foot construction costs as published biannually by the International Code Council. NOTE: the source document contains internal arithmetic/labeling inconsistencies in three tiers (the $50,001+, $100,001+, $500,001+, and $1,000,000.01+ rows all say 'for the first $2,000.00' where context indicates this should read the first $50,000 / $100,000 / $500,000 / $1,000,000 respectively, matching the tier's own bracket boundary) — the bracket boundaries and per-unit marginal rates are transcribed exactly as published; the 'for the first $X' base amounts are reproduced as literally printed by the City despite the apparent labeling typo, since no corrected version was located.
$0 ($0-$500.99); $52.00 for the first $500 plus $4.40 per additional $100 or fraction ($501-$2,000.99); $92.00 for the first $2,000 plus $17.60 per additional $1,000 or fraction ($2,001-$25,000.99); $496.00 for the first $25,000 plus $13.20 per additional $1,000 or fraction ($25,001-$50,000.99); $826.80 for the first $50,000 plus $9.13 per additional $1,000 or fraction ($50,001-$100,000.99); $1,283.00 for the first $100,000 plus $7.37 per additional $1,000 or fraction ($100,001-$500,000.99); $4,231.30 for the first $500,000 plus $6.27 per additional $1,000 or fraction ($500,001-$1,000,000); $7,366.30 for the first $1,000,000 plus $4.84 per additional $1,000 or fraction ($1,000,000.01 and up)
General Plan Review (includes 1st and 2nd review)City of Tombstone Fee Schedule (effective 11/14/2025), Building Official section.
65% of the Building Permit Fee
Standard Plan ReviewCity of Tombstone Fee Schedule (effective 11/14/2025).
$50.00 per permit
Hourly Plan Review (additional reviews, changes/revisions to approved plans, deferred submittals)City of Tombstone Fee Schedule (effective 11/14/2025).
$100.00 per hour
Permit Renewal (within 1 year of expiration)City of Tombstone Fee Schedule (effective 11/14/2025).
$500.00 + $10.00 per acre

Review timeline

Plan review
Not published — contact the department

How long did your Residential Building Permit (New Construction) permit actually take in Tombstone?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Land Clearing

    Before and after any land clearing

  2. 2

    Foundation Pad

    Before work begins on the completed foundation pad

  3. 3

    Pre-Concrete / Sub-Floor

    Before placing concrete work or laying sub-floors or framed first floors

  4. 4

    Framing / Drywall / Lathing

    After nailing and before covering framing, drywall, or lathing, including exterior sheathing and roof decking

  5. 5

    Rough-In (Plumbing, Mechanical, Electrical)

    Combined rough-in inspection for all three trades

  6. 6

    Gas Piping Test

    After installation of gas lines, confirming the gas piping test

  7. 7

    Pre-Tape/Paint Drywall

    After nailing of drywall and before taping and painting

  8. 8

    Final Plumbing, Mechanical, Electrical

    Final inspection of all three trades

  9. 9

    Final Interior

    Completed interior work verified

  10. 10

    Final Exterior

    Completed exterior work verified

  11. 11

    Certificate of Occupancy

    Required before the structure may be occupied or used

See the full Tombstone inspection guide — scheduling & re-inspection fees →

Tips

  • Tombstone's Building Permit Application is a single unified form (residential and commercial alike) with a bolded, underlined notice at the top: properties within the Schieffelin Historic District need HPC Certificate of Appropriateness approval BEFORE the building permit is even submitted for approval — plan for the HPC's own review timeline (21 days for the inspector's report to reach the Commission, then a Commission vote) as an added front-end step, not a parallel one.
  • Tombstone's adopted building code cycle (2006 IBC/IRC, 1988 NEC, 1988 UPC) is unusually old compared to Cochise County peers (Bisbee: 2018 codes/2017 NEC; Benson: 2024 codes/2023 NEC as of 2026) — confirmed via both the codified City Code text and the AZBO statewide directory search; no updated code-adoption ordinance was found despite the City Code being current through Ord. 2025-06 (Oct. 14, 2025), meaning the 2025-06 ordinance amended a different Title, not the Building Code chapter.
  • CONFIRMED GAP — plan review timeline: as of this review (July 2026), the City of Tombstone does not appear to publish a permit-specific plan review turnaround time (business or calendar days) anywhere in its public materials. Chase trail: (1) fetched the City's Building Permit Application (Rev. 1/2024) directly — describes required drawings and inspections but states no review-day figure; (2) fetched the City's November 14, 2025 Fee Schedule (adopted via Resolution No. 10-2025) — itemizes plan review FEES (65% of permit fee, hourly rates, etc.) in detail but never states a turnaround time; (3) fetched Tombstone City Code Title 3 Building Code chapter sections directly via r.jina.ai proxy (amlegal.com returns HTTP 403 to plain fetches) — found permit expiration (6 months + 60-day extension) but no plan-review SLA; (4) searched specifically for the City's A.R.S. Section 9-835 licensing-time-frame posting (a statute requiring municipalities to establish AND POST their own time frame per license/permit type on their own website) — no dedicated Tombstone time-frame chart or posting was located on cityoftombstoneaz.gov, unlike larger AZ cities (e.g., Buckeye) that publish one; note A.R.S. 9-835 itself does NOT supply a statutory default number if a municipality hasn't posted one, it only requires municipalities to post their own; (5) checked the Planning & Zoning page and Building Inspector page — neither references a turnaround time. This is a genuine, exhaustively chased confirmed gap, not an extraction failure. Call the Building Official (Robert Hendrickson, 520-457-3415, buildingofficial@cityoftombstoneaz.gov) for a current estimate.

Frequently asked questions

Only if the property is within the Schieffelin Historic Preservation District. The City's own Building Permit Application requires applicants to check a box confirming whether the property is within the District; if so, a Certificate of Appropriateness from the HPC must be obtained BEFORE the building permit can be submitted/approved. Outside the District, the standard building permit process applies without HPC review.

In Tombstone, the published Building Permit Fee — Based on Valuation is: $0 ($0-$500.99); $52.00 for the first $500 plus $4.40 per additional $100 or fraction ($501-$2,000.99); $92.00 for the first $2,000 plus $17.60 per additional $1,000 or fraction ($2,001-$25,000.99); $496.00 for the first $25,000 plus $13.20 per additional $1,000 or fraction ($25,001-$50,000.99); $826.80 for the first $50,000 plus $9.13 per additional $1,000 or fraction ($50,001-$100,000.99); $1,283.00 for the first $100,000 plus $7.37 per additional $1,000 or fraction ($100,001-$500,000.99); $4,231.30 for the first $500,000 plus $6.27 per additional $1,000 or fraction ($500,001-$1,000,000); $7,366.30 for the first $1,000,000 plus $4.84 per additional $1,000 or fraction ($1,000,000.01 and up). Additional published fees: General Plan Review (includes 1st and 2nd review) — 65% of the Building Permit Fee; Standard Plan Review — $50.00 per permit; Hourly Plan Review (additional reviews, changes/revisions to approved plans, deferred submittals) — $100.00 per hour; Permit Renewal (within 1 year of expiration) — $500.00 + $10.00 per acre. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

As of July 2026, the City of Tombstone does not appear to publish a permit-specific plan review turnaround time on its public website, in its Building Permit Application, in its November 2025 Fee Schedule, or in its codified City Code. There is no verifiable published business-day or calendar-day figure — call the Building Official at 520-457-3415 for a current estimate.

You'll need: Building Permit Application (City of Tombstone, Rev. 1/2024); Project Drawing Set (Plat Plan, Floor Plan, Exterior Elevations, Crosscut Sections, Mechanical/Plumbing/Electrical Plans). Depending on your project, Tombstone may also ask for: HPC Application / Historic District Sign and Construction Application. See the required-documents checklist on this page for details on each.

Tombstone requires 11 inspection(s) for a residential building permit (new construction), in order: Land Clearing, Foundation Pad, Pre-Concrete / Sub-Floor, Framing / Drywall / Lathing, Rough-In (Plumbing, Mechanical, Electrical), Gas Piping Test, Pre-Tape/Paint Drywall, Final Plumbing, Mechanical, Electrical, Final Interior, Final Exterior, Certificate of Occupancy. Schedule each through City of Tombstone Building Department (520-457-3415).

Apply through City of Tombstone Building Department at 611 E. Allen Street, Tombstone, AZ 85638 (City Hall: 613 E. Allen Street, Tombstone, AZ 85638). Phone: 520-457-3415, email: buildingofficial@cityoftombstoneaz.gov. Office hours: Monday - Friday, 8:00 AM - 5:00 PM (City of Tombstone Building Inspector page and Building Permit Application, Rev. 1/2024). Building Official/Inspector: Robert Hendrickson. Applications are submitted in person or by mail to the Building Department (P.O. Box 339, Tombstone, AZ 85638); the City does not appear to offer an online e-permitting portal as of this review — all forms found are static PDFs requiring paper/email submittal. Inspections are scheduled by calling 520-457-3415. Projects within the Schieffelin Historic District require Historic Preservation Commission (HPC) approval BEFORE building permit submission/approval, per the Building Permit Application's own header notice.. Official information: https://cityoftombstoneaz.gov/building-inspector/.

Tombstone, Arizona has adopted: Arizona has no statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9). The City of Tombstone is a home-rule city that independently adopts and administers its own construction codes through its own Building Department; it does not defer building permitting to Cochise County despite its small size (2020 Census population 1,307). Source: Tombstone City Code, Title 3 (Building Regulations), Chapter 1 (Building Code), codelibrary.amlegal.com/codes/tombstoneaz (current through Ord. 2025-06, passed 10-14-2025).; 2006 International Residential Code (IRC) and 2006 International Building Code (IBC), adopted by reference as 'the Uniform Building Code' of the City, per Tombstone City Code Section 3-1-1 (Adoption of Building Codes). NOTE: this is a genuinely old code cycle (2006, not a current ICC edition) — confirmed independently via two sources: (1) the codified City Code text itself (accessed via r.jina.ai proxy of codelibrary.amlegal.com/codes/tombstoneaz/latest/tombstone_az/0-0-0-1834, since amlegal.com returns HTTP 403 to a plain fetch), and (2) the Arizona Building Officials (AZBO) statewide directories, which as of the most recent editions searched (2018/2021) listed Tombstone's adopted codes as 2006 IBC/IRC/IMC/IPC and 2005 NEC. The current Building Permit Application (Rev. 1/2024) also cites 'Tombstone City Code, 3-1-1: Adoption of the Uniform Building Code' and references 'Uniform Building Code Permit Requirements' by name, consistent with the 2006-cycle adoption never having been updated to a current ICC edition. Source: Tombstone City Code Section 3-1-1; AZBO Directory (2018, 2021 editions); City of Tombstone Building Permit Application (Rev. 1/2024).; National Electrical Code of 1988, as copyrighted by the National Fire Protection Association, adopted by reference (Tombstone City Code Section 3-1-4, Electrical Code). This is a very old NEC edition (1988) relative to current AZ municipal practice (most Cochise County peers are on 2017 or 2020 NEC) — confirmed via direct code-section fetch; no more recent NEC adoption ordinance was located despite a search for 'building code' + ordinance amendments through the current Ord. 2025-06 code-currency marker. Source: Tombstone City Code Section 3-1-4.; Uniform Plumbing Code, 1988 edition, as copyrighted by the International Association of Plumbing and Mechanical Officials, adopted by reference (Tombstone City Code Section 3-1-5, Plumbing Code) — notably NOT an ICC/IPC adoption but the IAPMO's competing UPC model code, at its 1988 edition. Source: Tombstone City Code Section 3-1-5.; No IMC (mechanical), IFGC (fuel gas), IFC (fire), or IEBC (existing building) adoption was located anywhere in the codified Tombstone City Code Title 3 chapters reviewed, in the current Building Permit Application, or in the AZBO directory search results for Tombstone. This appears to be a genuine gap in the City's own published code structure (mechanical and gas work is folded into the 2006 IBC/IRC's own built-in mechanical/fuel-gas chapters rather than a standalone locally-adopted IMC/IFGC) rather than an extraction failure — the Building Permit Application's own 'Mechanical Plan' and 'Plumbing Plan' submittal-requirement sections cite no separate code title beyond the 'Uniform Building Code' umbrella term used throughout the form. Source: Tombstone City Code Title 3; City of Tombstone Building Permit Application (Rev. 1/2024).; Terminology construction: wherever 'a municipality' appears in the adopted building code, it is held to mean the City of Tombstone; 'corporation counsel' means the city attorney/legal advisor (Tombstone City Code Section 3-1-2, Construction of Terms). Source: Tombstone City Code Section 3-1-2.; Building Official / administrative authority is vested in the office of the City Clerk under the codified ordinance structure, with authority to designate deputies for inspections and other required duties (Tombstone City Code Section 3-1-6); in current practice, the City separately staffs a dedicated Building Official/Inspector position (Robert Hendrickson) rather than routing this through the Clerk's office day-to-day. Source: Tombstone City Code Section 3-1-6 (codified structure); City of Tombstone Building Inspector page (current practice).; Manufactured homes, mobile homes, and factory-built buildings: construction/installation standards for the home itself are regulated directly by the State of Arizona (Department of Fire, Building and Life Safety / Office of Manufactured Housing, A.R.S. Title 41-4001 et seq.), consistent with statewide practice; the City separately issues its own Manufactured Building Permit (flat fee $300.00, including 2 inspections, per the City's November 14, 2025 Fee Schedule) for local placement/site compliance, using its own dedicated Manufactured Building Permit Application form. Source: City of Tombstone Fee Schedule (effective 11/14/2025); Manufactured Building Permit Application (City of Tombstone).. Local amendments apply — see the Tombstone overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Tombstone building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.