Manufactured Building / Manufactured Home Installation Permit in Tombstone, Arizona

Required for placement of manufactured/mobile homes within Tombstone city limits, using the City's own dedicated Manufactured Building Permit Application separate from the general Building Permit Application. Billed as a flat fee including two inspections.

Verified 2026-07-07 · Source

When you need this permit

  • Manufactured Building Permit required for placement of a manufactured/mobile home within Tombstone city limits, using the City's dedicated Manufactured Building Permit Application form
  • Construction/factory-build standards for the home itself are regulated directly by the State of Arizona (Department of Fire, Building and Life Safety / Office of Manufactured Housing, A.R.S. Title 41-4001 et seq.); the City's permit addresses local placement/site compliance
  • Failure to obtain the permit before placement can be cause for revocation of a City of Tombstone Business License, a $300.00 fine, up to six months' imprisonment, or a combination, per the general Building Permit Application's permit-requirement notice

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Manufactured Home (includes 2 inspections)City of Tombstone Fee Schedule (effective 11/14/2025), listed under 'Other' Building Permit fees — flat rate inclusive of two inspections.
$300.00

Review timeline

Plan review
Not published — contact the department

How long did your Manufactured Building / Manufactured Home Installation Permit permit actually take in Tombstone?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Set/Placement Inspection

    First of the two inspections included in the flat fee, verifying placement/foundation/tie-down compliance

  2. 2

    Final/Utility Connection Inspection

    Second of the two inspections included in the flat fee, verifying utility connections and final site compliance

See the full Tombstone inspection guide — scheduling & re-inspection fees →

Tips

  • The Manufactured Home permit is a flat $300 fee inclusive of two inspections, distinct from and not calculated against the general valuation-based Building Permit fee table.
  • As of July 2026, the City of Tombstone does not publish a permit-specific plan review or inspection-scheduling turnaround time for manufactured home placements anywhere in its public materials — call the Building Official at 520-457-3415 for a current estimate.
  • The City of Tombstone's own Forms & Permits page (cityoftombstoneaz.gov/forms-permits/) currently links to a Manufactured Building Permit Application PDF at wp-content/uploads/2017/02/Manufactured-Building-Permit-Application.pdf that returns a 404 — a genuinely broken link on the City's own site, not a citation error on our part (confirmed via direct fetch and via Wayback Machine, which has no archived snapshot of that path either). The $300 fee (includes 2 inspections) and requirements documented here come from the City's Fee Schedule and general Building Permit Application, which remain live.

Frequently asked questions

Tombstone requires a manufactured building / manufactured home installation permit for: Manufactured Building Permit required for placement of a manufactured/mobile home within Tombstone city limits, using the City's dedicated Manufactured Building Permit Application form; Construction/factory-build standards for the home itself are regulated directly by the State of Arizona (Department of Fire, Building and Life Safety / Office of Manufactured Housing, A.R.S. Title 41-4001 et seq.); the City's permit addresses local placement/site compliance; Failure to obtain the permit before placement can be cause for revocation of a City of Tombstone Business License, a $300.00 fine, up to six months' imprisonment, or a combination, per the general Building Permit Application's permit-requirement notice. If your project isn't listed, confirm with City of Tombstone Building Department at 520-457-3415 before starting work.

$300.00 flat fee, inclusive of two inspections, per the City of Tombstone Fee Schedule (effective 11/14/2025). Use the City's dedicated Manufactured Building Permit Application, separate from the general Building Permit Application form.

Tombstone does not publish a plan-review timeline for this permit. Contact City of Tombstone Building Department at 520-457-3415 for current turnaround.

You'll need: Manufactured Building Permit Application. See the required-documents checklist on this page for details on each.

Tombstone requires 2 inspection(s) for a manufactured building / manufactured home installation permit, in order: Set/Placement Inspection, Final/Utility Connection Inspection. Schedule each through City of Tombstone Building Department (520-457-3415).

Apply through City of Tombstone Building Department at 611 E. Allen Street, Tombstone, AZ 85638 (City Hall: 613 E. Allen Street, Tombstone, AZ 85638). Phone: 520-457-3415, email: buildingofficial@cityoftombstoneaz.gov. Office hours: Monday - Friday, 8:00 AM - 5:00 PM (City of Tombstone Building Inspector page and Building Permit Application, Rev. 1/2024). Building Official/Inspector: Robert Hendrickson. Applications are submitted in person or by mail to the Building Department (P.O. Box 339, Tombstone, AZ 85638); the City does not appear to offer an online e-permitting portal as of this review — all forms found are static PDFs requiring paper/email submittal. Inspections are scheduled by calling 520-457-3415. Projects within the Schieffelin Historic District require Historic Preservation Commission (HPC) approval BEFORE building permit submission/approval, per the Building Permit Application's own header notice.. Official information: https://cityoftombstoneaz.gov/building-inspector/.

Tombstone, Arizona has adopted: Arizona has no statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9). The City of Tombstone is a home-rule city that independently adopts and administers its own construction codes through its own Building Department; it does not defer building permitting to Cochise County despite its small size (2020 Census population 1,307). Source: Tombstone City Code, Title 3 (Building Regulations), Chapter 1 (Building Code), codelibrary.amlegal.com/codes/tombstoneaz (current through Ord. 2025-06, passed 10-14-2025).; 2006 International Residential Code (IRC) and 2006 International Building Code (IBC), adopted by reference as 'the Uniform Building Code' of the City, per Tombstone City Code Section 3-1-1 (Adoption of Building Codes). NOTE: this is a genuinely old code cycle (2006, not a current ICC edition) — confirmed independently via two sources: (1) the codified City Code text itself (accessed via r.jina.ai proxy of codelibrary.amlegal.com/codes/tombstoneaz/latest/tombstone_az/0-0-0-1834, since amlegal.com returns HTTP 403 to a plain fetch), and (2) the Arizona Building Officials (AZBO) statewide directories, which as of the most recent editions searched (2018/2021) listed Tombstone's adopted codes as 2006 IBC/IRC/IMC/IPC and 2005 NEC. The current Building Permit Application (Rev. 1/2024) also cites 'Tombstone City Code, 3-1-1: Adoption of the Uniform Building Code' and references 'Uniform Building Code Permit Requirements' by name, consistent with the 2006-cycle adoption never having been updated to a current ICC edition. Source: Tombstone City Code Section 3-1-1; AZBO Directory (2018, 2021 editions); City of Tombstone Building Permit Application (Rev. 1/2024).; National Electrical Code of 1988, as copyrighted by the National Fire Protection Association, adopted by reference (Tombstone City Code Section 3-1-4, Electrical Code). This is a very old NEC edition (1988) relative to current AZ municipal practice (most Cochise County peers are on 2017 or 2020 NEC) — confirmed via direct code-section fetch; no more recent NEC adoption ordinance was located despite a search for 'building code' + ordinance amendments through the current Ord. 2025-06 code-currency marker. Source: Tombstone City Code Section 3-1-4.; Uniform Plumbing Code, 1988 edition, as copyrighted by the International Association of Plumbing and Mechanical Officials, adopted by reference (Tombstone City Code Section 3-1-5, Plumbing Code) — notably NOT an ICC/IPC adoption but the IAPMO's competing UPC model code, at its 1988 edition. Source: Tombstone City Code Section 3-1-5.; No IMC (mechanical), IFGC (fuel gas), IFC (fire), or IEBC (existing building) adoption was located anywhere in the codified Tombstone City Code Title 3 chapters reviewed, in the current Building Permit Application, or in the AZBO directory search results for Tombstone. This appears to be a genuine gap in the City's own published code structure (mechanical and gas work is folded into the 2006 IBC/IRC's own built-in mechanical/fuel-gas chapters rather than a standalone locally-adopted IMC/IFGC) rather than an extraction failure — the Building Permit Application's own 'Mechanical Plan' and 'Plumbing Plan' submittal-requirement sections cite no separate code title beyond the 'Uniform Building Code' umbrella term used throughout the form. Source: Tombstone City Code Title 3; City of Tombstone Building Permit Application (Rev. 1/2024).; Terminology construction: wherever 'a municipality' appears in the adopted building code, it is held to mean the City of Tombstone; 'corporation counsel' means the city attorney/legal advisor (Tombstone City Code Section 3-1-2, Construction of Terms). Source: Tombstone City Code Section 3-1-2.; Building Official / administrative authority is vested in the office of the City Clerk under the codified ordinance structure, with authority to designate deputies for inspections and other required duties (Tombstone City Code Section 3-1-6); in current practice, the City separately staffs a dedicated Building Official/Inspector position (Robert Hendrickson) rather than routing this through the Clerk's office day-to-day. Source: Tombstone City Code Section 3-1-6 (codified structure); City of Tombstone Building Inspector page (current practice).; Manufactured homes, mobile homes, and factory-built buildings: construction/installation standards for the home itself are regulated directly by the State of Arizona (Department of Fire, Building and Life Safety / Office of Manufactured Housing, A.R.S. Title 41-4001 et seq.), consistent with statewide practice; the City separately issues its own Manufactured Building Permit (flat fee $300.00, including 2 inspections, per the City's November 14, 2025 Fee Schedule) for local placement/site compliance, using its own dedicated Manufactured Building Permit Application form. Source: City of Tombstone Fee Schedule (effective 11/14/2025); Manufactured Building Permit Application (City of Tombstone).. Local amendments apply — see the Tombstone overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Tombstone building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.