EV Charger / EVSE Permit in Unincorporated Cochise County, Arizona
Cochise County has no dedicated EV-charger/EVSE permit type or fee line item. Installing a Level 2 or DC fast EV charger's dedicated circuit is administered as a Trade Permit (electrical) under the county's flat-rate trade permit schedule — the same schedule used for a service entry or other miscellaneous electrical work — since it is electrical work under NFPA 70 (2014 NEC edition, as adopted by the county). The governing schedule is Cochise County Code Chapter 14 (Development Services Fee Schedule, effective 2022-07-01, amended by Res. 24-14 effective 2024-10-01), https://cochisecounty.municipalcodeonline.com/book?type=ordinances#name=14_DEVELOPMENT_SERVICES_FEE_SCHEDULE, which supersedes the 2009 Fee Ordinance 037-09. No EV-specific line item exists in the current schedule either, but the flat-rate Miscellaneous Mechanical/Plumbing/Electrical trade permit fee — now $124, not the $50 under the superseded ordinance — is a genuine, citable, currently-applicable governing figure.
Verified 2026-07-23 · Source
When you need this permit
- Trade Permit (Electrical) required for the EV charger circuit — apply online through the Cochise County Permitting Portal (Citizenserve)
- If the installation requires a new or upgraded electrical service entry (e.g., a panel upgrade to support the charger load), it is billed as a Service Entry trade permit rather than the Misc. Electrical flat fee
- Installation must comply with NFPA 70 (National Electrical Code), 2014 Edition, as adopted by Cochise County
- Licensed-contractor information required when the work is performed by a contractor rather than the property owner
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Cochise County Code §14.15 (Residential Permits, 'Trade Permits and Flat Rate Fees'), effective 2022-07-01 and amended by Res. Show full citationHide
Cochise County Code §14.15 (Residential Permits, 'Trade Permits and Flat Rate Fees'), effective 2022-07-01 and amended by Res. 24-14 effective 2024-10-01 (https://cochisecounty.municipalcodeonline.com/book?type=ordinances#name=14_DEVELOPMENT_SERVICES_FEE_SCHEDULE), is the county's current codified fee schedule; it supersedes the 2009 Fee Ordinance 037-09, whose $50 figure is no longer current. The current schedule contains no 'EV', 'electric vehicle', or 'EVSE' language; a standalone EV charger circuit (not requiring a new service entry) most closely matches this general miscellaneous-electrical flat-rate line item, now $124.Cochise County Code §14.15, same source as above; Show full citationHide
Cochise County Code §14.15, same source as above; supersedes the earlier $50 figure from the 2009 Fee Ordinance 037-09. Applies instead of the Misc. Electrical fee if the EV charger installation includes a new or upgraded electrical service entry rather than just a new branch circuit.Review timeline
Inspection process
- 1
Rough-In / Service
Wiring/conduit or service equipment installed, verified before concealment, per NFPA 70 (2014 NEC)
- 2
Final
EVSE equipment connected and operational, breaker sizing and grounding verified
See the full Unincorporated Cochise County inspection guide — scheduling & re-inspection fees →
Tips
- Cochise County has no EV-charger-specific permit or fee — apply for the standard $124 flat-rate electrical Trade Permit (or the Service Entry trade permit if a panel/service upgrade is involved) through the Citizenserve portal.
- Confirm with Development Services (520-432-9300) whether your specific installation is billed as 'Misc. Electrical' or 'Service Entry' before applying, since the county's flat-fee schedule does not name EV chargers explicitly.
- The county's fee mechanism is Cochise County Code Chapter 14 (Development Services Fee Schedule, effective 2022-07-01, amended by Res. 24-14 effective 2024-10-01) — the flat trade-permit rate that applies to an EV charger circuit is $124, superseding the $50 figure from the earlier 2009 Fee Ordinance 037-09. No EV-specific line item exists in either version of the schedule.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Cochise County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Cochise County's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Unincorporated Cochise County yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Unincorporated Cochise County lands. Privacy.
Other permits in Unincorporated Cochise County
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Unincorporated Cochise County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Cochise County — in one checklist. Free, for any city and any number of projects.
Get started →