Electric Vehicle (EV) Charging Station Permit in Thatcher, Arizona
The Town of Thatcher has no distinct EV charger / EVSE permit type, application, or published fee. An EV charging station installation (new circuit, subpanel, or dedicated 240V branch circuit for a Level 2 charger) is permitted as standard electrical work under the Town's 2014 NEC adoption (Code of Ordinances Sec. 150.03), applied for through the same combined iWorq Citizen Portal 'Solar, Electrical, Gas or Plumbing permit' application used for all trade permits. Per Code of Ordinances Sec. 150.98, permit fees are set by Town Council resolution rather than published as a fixed schedule in the code text — the same fee gap documented for Thatcher's general electrical-permit entry. No numeric electrical/building permit fee table appears in the Town's Document Center, on the Finance Department page, in the Agendas/Meeting archive, or in the amlegal.com code library, and no archived version of a Thatcher fee schedule exists either.
Reviewed 2026-07-20 · Source
When you need this permit
- Electrical work must comply with the 2014 National Electrical Code (NEC) as adopted by the Town of Thatcher (Code of Ordinances Sec. 150.03)
- No distinct EV-charger permit type exists — apply via the iWorq Citizen Portal's combined 'Solar, Electrical, Gas or Plumbing permit' application and select Electrical
- All residential, commercial, and infrastructure permit applications are submitted online through the iWorq Citizen Portal (thatcherpermitting.portal.iworq.net) with uploaded PDF plans and contractor licensing documentation
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Town of Thatcher Code of Ordinances Sec. 150.98. Show full citationHide
Town of Thatcher Code of Ordinances Sec. 150.98. The same fee-schedule gap documented on the general electrical permit applies here, after checking the Code of Ordinances, Document Center, Finance Department page, agendas and meeting archive, and Forms Center — call the Building Inspector (928-428-2290) for current pricing.Review timeline
Inspection process
- 1
Rough-In
Wiring, box placement, and panel/subpanel connections for the EV charging circuit before walls are closed
- 2
Final
Charger installed, circuit labeled, protections verified per 2014 NEC
See the full Thatcher inspection guide — scheduling & re-inspection fees →
Tips
- There is no dedicated 'EV charger permit' in Thatcher — apply through the iWorq Citizen Portal's combined Solar/Electrical/Gas/Plumbing application and select Electrical, describing the EV charging station scope of work.
- Call the Building Inspector (928-428-2290) before applying to confirm the current council-set electrical permit fee — no fixed dollar figure is published anywhere online, including the Town's Document Center, Finance page, and code library.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Applications & forms
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Thatcher building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Thatcher's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Thatcher yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Thatcher lands. Privacy.
Other permits in Thatcher
Electric Vehicle (EV) Charging Station Permit in other cities
Compare electric vehicle (ev) charging station permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Thatcher project checklist
Describe your project once and get every permit, document, and fee it triggers in Thatcher — in one checklist. Free, for any city and any number of projects.
Get started →