Commercial Building Permit (New Construction, Tenant Improvement, Shell Building) in Unincorporated La Paz County, Arizona
Required for new commercial construction, tenant improvements, and shell buildings in the unincorporated areas of La Paz County. Fees are valuation-based per Table M-1, with tenant improvement and shell-building categories subject to per-square-foot rates published in the county fee schedule.
Verified 2026-07-07 · Source
When you need this permit
- Required for all new commercial construction, tenant improvements, remodels, and shell buildings in unincorporated La Paz County
- Apply through the iworq Citizen Portal (https://lapazcountyapplypermit.portal.iworq.net/portalhome/lapazcountyapplypermit) or in person at 1112 Joshua Ave., Ste. 202, Parker, AZ
- Submit site plan and complete construction plans; commercial cost-per-square-foot valuation follows the ICC Building Valuation Data table (Exhibit C of the fee schedule) by occupancy group and construction type
- Must use an Arizona-licensed contractor (A.R.S. §32-1151) Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing/Foundation
Before concrete pour, per 2018 IBC
- 2
Framing / Structural
After structural framing complete, before wall cover
- 3
Final
All work complete per approved plans; Certificate of Occupancy issued (included in permit fee; Temporary C of O is a separate $500 fee, renewable every 30 days)
See the full Unincorporated La Paz County inspection guide — scheduling & re-inspection fees →
Tips
- Commercial and technically complex projects can have their Substantive Review extended from 105 to up to 165 working days by written/electronic agreement per A.R.S. §11-1605(I) — factor this into project timelines.
- Temporary Certificate of Occupancy costs $500 (residential or commercial) and must be renewed every 30 days at the same $500 fee until the permanent C of O is issued.
- Shell buildings (no interior trades, no designated tenant) are billed at a flat per-square-foot rate ($50/sq ft wood, $65/sq ft concrete/masonry) rather than full ICC valuation.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated La Paz County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Unincorporated La Paz County.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Unincorporated La Paz County
Commercial Building Permit (New Construction, Tenant Improvement, Shell Building) in other cities
Look up this fee in a different city →
Now live
Build your Unincorporated La Paz County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated La Paz County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →