Plumbing Permit in Cave Creek, Arizona

Required for plumbing installation, alteration, or repair work in Cave Creek, governed by the International Plumbing Code as adopted and amended by the Town (Ordinance No. 2025-08 text cites the 2025 IPC edition; the Town's Building & Fire Code Compliance summary page separately lists 2024 IPC — the Ordinance is the authoritative source).

Verified 2026-07-06 · Source

When you need this permit

  • Plumbing permit required for installation, alteration, or repair of plumbing systems, fixtures, water heaters, and gas piping
  • Water heaters must be equipped with a temperature and pressure relief valve, terminating 6 inches above finished floor
  • Fixture unit calculation required for water service line, water meter, or well service sizing based on the current adopted code
  • Water heater change-out, like for like, is billed as a flat fee distinct from general plumbing valuation
  • Apply via the Town's SmartGov Community Platform online portal

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Water Heater — change out, like for likeTown of Cave Creek Comprehensive Fee Schedule, Other Permit Fees
$50.00
Plumbing work not otherwise separately classifiedTown of Cave Creek Comprehensive Fee Schedule does not list additional dedicated flat-fee plumbing line items beyond the water heater change-out; other plumbing scope is priced through the general valuation-based Building Permit Fee
Based on Valuation — see Building Permit Fee valuation table
Plan Review Fee, StandardTown of Cave Creek Comprehensive Fee Schedule, Plan Review Fees
65% of the permit fee (minimum $50); flat-fee permits (e.g., water heater change-out) have $0 plan review fee

Review timeline

Plan review
Not published — contact the department

How long did your Plumbing Permit permit actually take in Cave Creek?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Underslab / Underfloor Plumbing

    Before concrete pour or floor closure — verify pipe slope, materials, cleanouts

  2. 2

    Plumbing Rough Trade

    After pipes installed, before walls closed

  3. 3

    Plumbing Final

    Fixtures connected, water heater relief valve and gas connections verified, no leaks

See the full Cave Creek inspection guide — scheduling & re-inspection fees →

Tips

  • As of July 2026, the Town of Cave Creek does not appear to publish permit-specific plan review turnaround times for plumbing permits on its public website. There is no verifiable online source for this — call the Town of Cave Creek Building and Fire Safety Department directly at 480-488-6622.
  • A like-for-like water heater change-out is the only plumbing scope with its own dedicated flat fee ($50) on the Comprehensive Fee Schedule — all other plumbing work is priced through the general valuation-based Building Permit Fee.
  • The Town's own Residential Plan Review Check List has dedicated inspection tutorial checklists for Plumbing Final, Plumbing Rough Trade, and Underslab Plumbing, published separately on the Building & Fire Code Compliance page.

Frequently asked questions

Yes — a like-for-like water heater change-out is a flat $50 permit fee per the Town of Cave Creek Comprehensive Fee Schedule.

In Cave Creek, the published Water Heater — change out, like for like is: $50.00. Additional published fees: Plumbing work not otherwise separately classified — Based on Valuation — see Building Permit Fee valuation table; Plan Review Fee, Standard — 65% of the permit fee (minimum $50); flat-fee permits (e.g., water heater change-out) have $0 plan review fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Cave Creek does not publish a plan-review timeline for this permit. Contact Town of Cave Creek Building and Fire Safety Department at 480-488-1400 (Main); 480-488-6637 / 480-488-6622 (Building Official / Building Department); 480-488-6631 (Plans Examiner) for current turnaround.

You'll need: Building/Plumbing Permit Application; Plumbing section of the Residential Plan Review Check List (rev. 6/15/2026). See the required-documents checklist on this page for details on each.

Cave Creek requires 3 inspection(s) for a plumbing permit, in order: Underslab / Underfloor Plumbing, Plumbing Rough Trade, Plumbing Final. Schedule each through Town of Cave Creek Building and Fire Safety Department (480-488-1400 (Main); 480-488-6637 / 480-488-6622 (Building Official / Building Department); 480-488-6631 (Plans Examiner)).

Apply through Town of Cave Creek Building and Fire Safety Department at 37622 N. Cave Creek Road, Cave Creek, AZ 85331. Phone: 480-488-1400 (Main); 480-488-6637 / 480-488-6622 (Building Official / Building Department); 480-488-6631 (Plans Examiner), email: ahicks@cavecreekaz.gov (Adam Hicks, Building Official/Fire Marshal); jlombardo@cavecreekaz.gov (Jenifer Lombardo, Plans Examiner/Building Inspector); twilgus@cavecreekaz.gov (Tracie Wilgus, Sr. Permit Tech). Office hours: Monday - Thursday, 7 a.m. to 5 p.m. All permit applications, plan reviews, inspection requests, and payments must be submitted through the Town's online portal, the SmartGov Community Platform (twn-cavecreek-az.smartgovcommunity.com/Public/Home) — effective as the Town's exclusive permitting channel per the Town's Online Permitting and Inspection Service notice.. Official information: https://www.cavecreekaz.gov/577/Building-Fire-Code-Compliance.

Cave Creek, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. § 9-802 authorizes municipalities to adopt codes or public records by reference without setting forth their provisions in full, provided the adopting ordinance is published in full). The Town of Cave Creek independently adopts and administers its own construction codes through its Building and Fire Safety Department; it does not defer permitting to Maricopa County. Source: Town of Cave Creek Ordinance No. 2025-08 (adopted November 18, 2025, effective January 1, 2026).; 2024 International Building Code (IBC), as published by the International Code Council, adopted by reference (Town Code Title XV, Chapter 151, § 151.01), with Town of Cave Creek amendments, effective January 1, 2026. Source: Town of Cave Creek Ordinance No. 2025-08, Exhibit A.1 and A.2, Section 1.; 2024 International Residential Code (IRC), as published by the International Code Council, adopted by reference (§ 151.02), with Town of Cave Creek amendments, effective January 1, 2026. Chapter 11 (Energy Efficiency) of the 2024 IRC is deleted in its entirety and replaced with Chapter 11 of the 2018 IRC. Source: Town of Cave Creek Ordinance No. 2025-08, Section 2.; 2024 International Mechanical Code (IMC), adopted by reference (§ 151.03), with Town of Cave Creek amendments, effective January 1, 2026. Source: Town of Cave Creek Ordinance No. 2025-08, Section 3.; 2025 International Plumbing Code (IPC), adopted by reference (§ 151.04), with Town of Cave Creek amendments, effective January 1, 2026 (the Town's Building & Fire Code Compliance summary page separately lists this as the '2024 International Plumbing Code' — the governing Ordinance No. 2025-08 text itself specifies the 2025 edition; treat the Ordinance as authoritative). Source: Town of Cave Creek Ordinance No. 2025-08, Section 4.; 2023 National Electrical Code (NEC), as published by the National Fire Protection Association (NFPA 70), adopted by reference (§ 151.05), with Town of Cave Creek amendments, effective January 1, 2026. Source: Town of Cave Creek Ordinance No. 2025-08, Section 5.; 2025 International Fire Code (IFC), adopted by reference (§ 151.06) as the Town's uniform fire code, with Town of Cave Creek amendments; administered by the Building and Fire Safety Department under the Chief Building and Fire Code Official. Appendix B (Fire Flow Requirements for Buildings) and Appendix D (Fire Apparatus Access Roads) are adopted, with Appendix D.102.1 amended to require an approved fire apparatus access road capable of supporting an imposed load of fire apparatus weighing up to 50,000 pounds. Annual fire and life safety inspections are required for all occupancies and buildings except one- and two-family dwellings. Source: Town of Cave Creek Ordinance No. 2025-08, Section 6.; Town of Cave Creek Sprinkler Code (§ 151.07), originally adopted from Chapter 9 of the 2003 International Fire Code in July 2004 and unchanged since; automatic fire sprinkler systems in new and existing buildings are governed by this Town-specific sprinkler code rather than the IFC's own Section 903 (which is deleted and replaced by reference to § 151.07). Source: Town of Cave Creek Ordinance No. 2025-08, Section 6(2)-(3) and Section 7.; 2024 International Fuel Gas Code (IFGC), adopted by reference (§ 151.08), with Town of Cave Creek amendments, effective January 1, 2026. Source: Town of Cave Creek Ordinance No. 2025-08, Section 8.; 2025 International Existing Building Code (IEBC), adopted by reference (§ 151.09), with Town of Cave Creek amendments, effective January 1, 2026. Source: Town of Cave Creek Ordinance No. 2025-08, Section 9.; 2024 International Energy Conservation Code (IECC), adopted by reference (§ 151.10), effective January 1, 2026, EXCEPT that Chapters R1 through R5 of the IECC's residential section are deleted in their entirety and replaced with Chapters R1 through R5 of the 2018 IECC — so residential energy compliance in Cave Creek runs on the 2018 IECC residential provisions even though the commercial IECC baseline is 2024. Source: Town of Cave Creek Ordinance No. 2025-08, Section 10.; 2024 International Pool and Spa Code (ISPSC), adopted by reference (§ 151.11 International Swimming Pool and Spa Code), effective January 1, 2026; all swimming pools, spas, and hot tubs must comply with this code, and pool/spa/hot-tub enclosures must comply with A.R.S. § 36-1681 (Arizona's pool barrier statute). Swimming pools and spas are issued under a separate permit from the building permit. Source: Town of Cave Creek Ordinance No. 2025-08, Section 11; Town of Cave Creek Residential Plan Review Check List (rev. 6/15/2026).; ICC A117.1-2017 (Standard for Accessible and Usable Buildings and Facilities), adopted as part of the Town's code suite alongside the 2024 IBC. Source: Town of Cave Creek Ordinance No. 2025-08 (preamble); Town of Cave Creek Commercial Plan Submittal Guidelines.; All prior versions of Chapter 151 (Building Code § 151.01, Residential Code § 151.02, Mechanical Code § 151.03, Plumbing Code § 151.04, Electrical Code § 151.05, Fire Code § 151.06, Fuel Gas Code § 151.08, Existing Building Code § 151.09, and Energy Conservation Code § 151.10) were repealed in their entirety and replaced by Ordinance No. 2025-08, effective January 1, 2026; all former conflicting ordinances were repealed as of that date. Source: Town of Cave Creek Ordinance No. 2025-08, Sections 1-2 (Repeal, Effective Date).. Local amendments apply — see the Cave Creek overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cave Creek building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.