Certificate of Occupancy for Change of Use Group — Cave Creek, Arizona · Requirements sheet
Verified 2026-07-23 · Source: https://www.cavecreekaz.gov/DocumentCenter/View/7107/Comprehensive-Fee-Schedule---as-of-2-5-2026-PDF
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Certificate of Occupancy for Change of Use Group in Cave Creek, Arizona
Cave Creek's real local equivalent of a 'change of use permit' is a Certificate of Occupancy (CofO) product administered by the Building and Fire Safety Department. Where a change of occupancy classification is proposed WITHOUT any accompanying construction work, the Town charges a dedicated flat 'Request for Certificate of Occupancy for Change of Use Group without Construction' fee. Where a change of use IS accompanied by construction/alteration work, that work is instead permitted and fee'd through the standard Commercial Building Permit (valuation-based) process, per the Town's adopted 2025 International Existing Building Code (IEBC, Town Code § 151.09) change-of-occupancy provisions. The Town's Fee Schedule separately itemizes a staged Temporary Certificate of Occupancy (TCofO) fee for projects that need to occupy a building before final completion.
Verified 2026-07-23 · Source
When you need this permit
- A Certificate of Occupancy for Change of Use Group without Construction applies where a proposed change in occupancy classification (e.g., retail to office, restaurant to retail) does NOT involve any construction or alteration work
- Where a change of occupancy IS accompanied by construction or alteration work, the project must instead apply for a standard Commercial Building Permit, valued and fee'd per the general valuation-based Building Permit Fee table, with plan review against the code requirements applicable to the new occupancy classification
- Governed by the 2025 International Existing Building Code (IEBC) as adopted by the Town of Cave Creek (Town Code § 151.09), which requires compliance with the code provisions applicable to the new occupancy classification before a change of occupancy is approved
- A Temporary Certificate of Occupancy (TCofO) may be requested for a project that needs to occupy a building before all final work/inspections are complete; the fee increases the longer the temporary occupancy is extended (staged in 30-day increments)
- Apply via the Town's SmartGov Community Platform online portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Change of Use Walkthrough
Verifies life-safety compliance (egress, occupant load, fire alarm/sprinkler coverage as applicable) for the new occupancy classification where no construction is involved
- 2
Final (where construction is involved)
Standard final building inspection against approved plans, applicable when the change of use includes construction/alteration work permitted under the Commercial Building Permit
See the full Cave Creek inspection guide — scheduling & re-inspection fees →
Tips
- As of July 2026, the Town of Cave Creek does not appear to publish permit-specific plan review turnaround times for Certificate of Occupancy / change-of-use requests on its public website. Call the Building and Fire Safety Department directly at 480-488-6622 for a current estimate.
- The $61 flat CofO fee ONLY applies to a change of use group WITHOUT construction -- if any construction or alteration work accompanies the occupancy change, budget for the standard valuation-based Commercial Building Permit fee instead.
- A Temporary Certificate of Occupancy escalates quickly (3% of the building permit fee for the first 30 days, 6% for the second, 9% for the third) -- there is no published fee tier beyond the third 30-day period, so plan to complete final work within roughly 90 days of occupying under a TCofO.
- Confirm which occupancy classification your business/tenant use falls under against the 2025 IBC and 2025 IEBC (as adopted and amended by the Town) before applying -- a straightforward retail-to-retail tenant swap is more likely to qualify for the no-construction CofO path than a use requiring different occupant-load, egress, or fire-protection provisions.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cave Creek building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Cave Creek
Certificate of Occupancy for Change of Use Group in other cities
Compare certificate of occupancy for change of use group fees across Arizona →