Certificate of Occupancy / Change of Occupancy in Chandler, Arizona

Chandler's local equivalent of a 'change of use' process is its Certificate of Occupancy (C of O), issued under Section 111 of the 2024 International Building Code with Chandler amendments (Ordinance No. 5108). A C of O is issued upon completion of permitted new construction, and can also be issued on its own, without an accompanying Building Permit, for a change of occupancy or use in an existing space where no construction is involved (flat fee $100.00). A Temporary Certificate of Occupancy is available for phased occupancy. Chandler's local amendment (§29-2.15, adding Subsection 111.5) also created a distinct 'Certificate of Completion,' which may be issued for permitted work that does not change the scope of an existing C of O or does not result in a building ready for occupancy — a Certificate of Completion alone does NOT authorize occupancy of a building. Per the Development Services Division's published time frames, review is exempt from separate completeness/substantive review stages, with a 10-working-day overall review time.

Verified 2026-07-23 · Source

When you need this permit

  • A Certificate of Occupancy not associated with a Building Permit is required for a change of occupancy or use in an existing building/space where no construction work is involved; flat fee $100.00 (Fee Schedule §4.6.4(g))
  • Where the change of occupancy/use DOES involve construction, alteration, or a change of occupancy classification triggering the 2024 International Existing Building Code (IEBC) with Chandler amendments, the standard Building Permit process applies rather than the standalone C of O fee
  • A Certificate of Completion (City Code §29-2.15, Subsection 111.5) may be issued instead of a full C of O when the completed work does not change the scope of an existing C of O or does not result in a building ready for occupancy; a Certificate of Completion alone does not authorize occupancy
  • A Temporary Certificate of Occupancy may be requested for phased occupancy; fee is $100.00 for the first 30 days plus $500.00 for each 30-day renewal, to a maximum of 180 days (Fee Schedule §4.6.4(o))
  • Apply through the Citizen Access portal or walk in to 215 E. Buffalo St.; overall review is 10 working days (point of contact: Mike DeWys)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Certificate of Occupancy not associated with a Building Permit — flat feeCity of Chandler Fee Schedule, Section 4.6.4(g): 'Certificate of Occupancy not associated with a Building Permit — $100.00.' Applies to change-of-occupancy/use requests where no construction/building permit is involved.
$100.00
Temporary Certificate of OccupancyCity of Chandler Fee Schedule, Section 4.6.4(o): 'Temporary Certificate of Occupancy — $100.00 for first 30 days, $500.00 for each 30 day renewal for a maximum of 180 days.'
$100.00 for the first 30 days, then $500.00 for each 30-day renewal, to a maximum of 180 days

Review timeline

Plan reviewChandler’s published plan-review target
10–10 business days

How long did your Certificate of Occupancy / Change of Occupancy permit actually take in Chandler?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Certificate of Occupancy

    Final verification that all applicable trade inspections are approved and the building/space meets code for the occupancy classification requested, per the City's published Building Inspection Codes (Miscellaneous group, code 782).

  2. 2

    Certificate of Completion

    Issued instead of a full C of O when the completed work does not change the scope of an existing C of O or does not result in a building ready for occupancy (City Code §29-2.15, Subsection 111.5; Miscellaneous group, code 783). Does not itself authorize occupancy.

See the full Chandler inspection guide — scheduling & re-inspection fees →

Tips

  • If your project is only a change of use/occupancy in existing space with no construction work, apply for a standalone Certificate of Occupancy ($100.00 flat fee) rather than a full Building Permit.
  • A Certificate of Completion is not the same as a Certificate of Occupancy — it does not by itself authorize occupancy of a building; it applies only when work doesn't change the scope of an existing C of O or doesn't ready a space for occupancy.
  • A Temporary Certificate of Occupancy is capped at a total of 180 days (initial 30 days plus renewals).
  • Overall review for a standalone C of O is 10 working days per the Development Services Division's published time frames.

Frequently asked questions

Chandler requires a certificate of occupancy / change of occupancy permit for: A Certificate of Occupancy not associated with a Building Permit is required for a change of occupancy or use in an existing building/space where no construction work is involved; flat fee $100.00 (Fee Schedule §4.6.4(g)); Where the change of occupancy/use DOES involve construction, alteration, or a change of occupancy classification triggering the 2024 International Existing Building Code (IEBC) with Chandler amendments, the standard Building Permit process applies rather than the standalone C of O fee; A Certificate of Completion (City Code §29-2.15, Subsection 111.5) may be issued instead of a full C of O when the completed work does not change the scope of an existing C of O or does not result in a building ready for occupancy; a Certificate of Completion alone does not authorize occupancy; A Temporary Certificate of Occupancy may be requested for phased occupancy; fee is $100.00 for the first 30 days plus $500.00 for each 30-day renewal, to a maximum of 180 days (Fee Schedule §4.6.4(o)); Apply through the Citizen Access portal or walk in to 215 E. Buffalo St.; overall review is 10 working days (point of contact: Mike DeWys). If your project isn't listed, confirm with City of Chandler Development Services Department — Building Safety at 480-782-3000 before starting work.

In Chandler, the published Certificate of Occupancy not associated with a Building Permit — flat fee is: $100.00. Additional published fees: Temporary Certificate of Occupancy — $100.00 for the first 30 days, then $500.00 for each 30-day renewal, to a maximum of 180 days. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Chandler's published plan-review target for a certificate of occupancy / change of occupancy permit is 10–10 business days.

You'll need: Certificate of Occupancy Application (Form UDM-011); Final Inspection Approvals. See the required-documents checklist on this page for details on each.

Chandler requires 2 inspection(s) for a certificate of occupancy / change of occupancy permit, in order: Certificate of Occupancy, Certificate of Completion. Schedule each through City of Chandler Development Services Department — Building Safety (480-782-3000).

Apply through City of Chandler Development Services Department — Building Safety at 215 E. Buffalo St., Chandler, AZ 85225. Phone: 480-782-3000, email: prod@chandleraz.gov. Office hours: Monday – Friday 8:00 AM – 5:00 PM, except holidays; Walk-in plan review: Monday – Friday 8:00 AM – 4:30 PM. Official information: https://www.chandleraz.gov/government/departments/development-services/building-safety-plan-review-permits-and-inspections.

Chandler's equivalent process is the Certificate of Occupancy (C of O). A C of O can be issued on its own, without an accompanying Building Permit, for a change of occupancy or use in an existing space where no construction is involved — this costs a flat $100.00 fee. If the change of use does require construction or triggers change-of-occupancy provisions of the 2024 International Existing Building Code, the standard Building Permit process applies instead. Source: City of Chandler Fee Schedule §4.6.4(g) and Development Services Time Frames document.

Per City Code §29-2.15 (adding IBC Subsection 111.5), a Certificate of Completion may be issued when permitted work is finished but the work does not change the scope of an existing Certificate of Occupancy or does not result in a building ready for occupancy. A Certificate of Completion alone does NOT authorize occupancy of a building. Source: Chandler Amendments to the 2024 International Construction Codes (Ordinance No. 5108), §29-2.15.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Chandler building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.