Residential Solar Photovoltaic (PV) System Permit in Chandler, Arizona

A residential solar photovoltaic system permit is required in Chandler for rooftop solar PV installations. The flat permit fee is $150.00 (Res. 4703, Fee Schedule §4.6.4(k)). A separate solar water heating system permit fee of $150.00 also applies to solar thermal installations. Apply through the Citizen Access portal or walk-in at 215 E. Buffalo St. All plans submitted on or after July 1, 2025 must comply with the 2023 NEC with Chandler amendments and the 2024 IBC/IRC.

Verified 2026-07-16 · Source

When you need this permit

  • Apply through the Citizen Access portal or walk-in at 215 E. Buffalo St.
  • Plans submitted on or after July 1, 2025 must comply with the 2023 NEC and 2024 IBC/IRC with Chandler amendments (Ordinance No. 5108)
  • Licensed contractor required for solar installation unless owner-occupant performs work (ARS 32-1121A; does not apply to rental/lease properties) Owner-builderContractor
  • Provide panel schedule showing existing and new breakers for any electrical service work required for the solar installation

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Residential solar photovoltaic system permit fee — flat feeCity of Chandler Fee Schedule, Section 4.6.4(k): 'Residential solar photovoltaic system permit fee (Res. 4703) — $150.00.' This flat fee applies specifically to residential solar PV installations.
$150.00
Residential solar water heating system permit fee — flat feeCity of Chandler Fee Schedule, Section 4.6.4(l): 'Residential solar water heating system permit fee (Res. 4703) — $150.00.' Applies to solar thermal (hot water) systems, distinct from solar PV.
$150.00

Review timeline

Plan reviewTypical estimate — confirm current times with the Chandler building department
~1–10 business days

How long did your Residential Solar Photovoltaic (PV) System Permit permit actually take in Chandler?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough electrical (if applicable)

    If roof penetrations, conduit runs, or sub-panel work is included, rough electrical inspection prior to cover.

  2. 2

    Final inspection

    Solar PV system completed per approved plans, 2023 NEC, and 2024 IBC/IRC with Chandler amendments.

See the full Chandler inspection guide — scheduling & re-inspection fees →

Tips

  • Chandler charges a flat $150.00 permit fee for residential solar PV installations — straightforward and lower than valuation-based approaches for typical residential systems.
  • A separate $150.00 permit fee applies to solar water heating (thermal) systems, distinct from solar PV.
  • All plans must comply with the 2023 NEC (not 2024 NEC) with Chandler amendments for electrical work.

Frequently asked questions

Chandler requires a residential solar photovoltaic (pv) system permit for: Apply through the Citizen Access portal or walk-in at 215 E. Buffalo St.; Plans submitted on or after July 1, 2025 must comply with the 2023 NEC and 2024 IBC/IRC with Chandler amendments (Ordinance No. 5108); Licensed contractor required for solar installation unless owner-occupant performs work (ARS 32-1121A; does not apply to rental/lease properties); Provide panel schedule showing existing and new breakers for any electrical service work required for the solar installation. If your project isn't listed, confirm with City of Chandler Development Services Department — Building Safety at 480-782-3000 before starting work.

Chandler charges a flat fee of $150.00 for a residential solar photovoltaic system permit (Res. 4703). A separate $150.00 flat fee applies to solar water heating systems. Source: City of Chandler Fee Schedule, Section 4.6.4(k) and (l).

Plan review for a residential solar photovoltaic (pv) system permit in Chandler typically runs 1–10 business days. This is an estimate, not a published figure — confirm current review times with City of Chandler Development Services Department — Building Safety at 480-782-3000.

You'll need: Building Permit Application. See the required-documents checklist on this page for details on each.

Chandler requires 2 inspection(s) for a residential solar photovoltaic (pv) system permit, in order: Rough electrical (if applicable), Final inspection. Schedule each through City of Chandler Development Services Department — Building Safety (480-782-3000).

Apply through City of Chandler Development Services Department — Building Safety at 215 E. Buffalo St., Chandler, AZ 85225. Phone: 480-782-3000, email: prod@chandleraz.gov. Office hours: Monday – Friday 8:00 AM – 5:00 PM, except holidays; Walk-in plan review: Monday – Friday 8:00 AM – 4:30 PM. Official information: https://www.chandleraz.gov/government/departments/development-services/building-safety-plan-review-permits-and-inspections.

Chandler, Arizona has adopted: 2024 International Building Code (IBC) — adopted by Chandler City Council, Ordinance No. 5108; effective for plans submitted on or after July 1, 2025; Chandler amendments published in City Code Chapter 29, Article II (Ordinance No. 5108); 2024 International Residential Code (IRC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article VI); effective July 1, 2025; 2023 National Electrical Code (NEC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article III); effective July 1, 2025; Chandler's 2024 code set retains the 2023 NEC edition (not the 2024 NEC); 2024 International Plumbing Code (IPC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article IV); effective July 1, 2025; 2024 International Mechanical Code (IMC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article V); effective July 1, 2025; 2024 International Fuel Gas Code (IFGC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article VII); effective July 1, 2025; 2024 International Energy Conservation Code (IECC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article VIII); effective July 1, 2025; 2024 International Existing Building Code (IEBC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article IX); effective July 1, 2025; 2024 International Swimming Pool and Spa Code (ISPSC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article X); effective July 1, 2025; 2024 International Fire Code (IFC) — adopted by Ordinance No. 5108 (City Code Chapter 28); effective July 1, 2025. Local amendments apply — see the Chandler overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Chandler building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.