Commercial Building Permit (New Construction, Additions & Amenities) — Chandler, Arizona · Requirements sheet
Verified 2026-07-29 · Source: https://www.chandleraz.gov/government/departments/development-services/building-safety-plan-review-permits-and-inspections
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction, Additions & Amenities) in Chandler, Arizona
Chandler processes new commercial building construction (including additions and amenities) as a distinct license type from residential permits and from tenant improvements, per the Development Services Division's published Application Supplement (Time Frames/Point of Contact/Application Info/Appeal Rights). The overall review time frame is 60 working days (20 working days completeness review plus 40 working days substantive review, consisting of two 20-working-day review cycles). Building permit fees are valuation-based using ICC Building Valuation Data (City of Chandler Fee Schedule §4.6.1, Res. 4703) — the same fee table used for residential construction; plan review is 65% of the permit fee. A Wastewater Discharge Questionnaire (WWDQ) characterizing the wastewater flows generated by the new connection must be submitted with non-residential building permit applications. Plans submitted on or after July 1, 2025 must comply with the 2024 I-Codes and 2023 NEC with Chandler amendments (Ordinance No. 5108).
Verified 2026-07-29 · Source
When you need this permit
- Apply through the Citizen Access portal (electronic submittal recommended) or walk in to 215 E. Buffalo St.; per the City's Building Safety page, walk-in plan review (Mon–Fri 8:00 AM–4:30 PM) is offered 'for residential and small commercial projects,' with only 'a limited number of minor-scale commercial projects' eligible at the plan reviewer's discretion — most commercial projects should expect the full review track
- Plans submitted on or after July 1, 2025 must comply with the 2024 International Building Code and 2023 NEC with Chandler amendments (Ordinance No. 5108, City Code Chapter 29)
- Pre-Technical Site Plan Review is required (free of charge) for any proposed subdivision, site plan development, new building, or substantial building addition, per the City of Chandler Development Services Division
- Projects with a site development component must satisfy the Site Development Plan Review Checklist/Guide for Commercial, Industrial & Multi-Family Development (Form UDM-029/Site), covering items such as architectural site plan notes, parking standards, screening of roof- and ground-mounted mechanical equipment, ADA-accessible pedestrian circulation, and (for shopping centers/office/commercial complexes) one pedestrian-oriented design feature per 50,000 sq ft of gross floor area
- Commercial buildings adjacent to single-family residential zoning must be set back 25 feet from the residential property line, plus one additional foot of setback for each foot of building height (Zoning Code Section 1902(8)(a)1)
- Submit a Wastewater Discharge Questionnaire (WWDQ) — required with non-residential building permit applications to characterize wastewater flows from the new potable water connection; contact the Wastewater Quality Division (480-782-3720) with questions
- Include Fire Prevention Bureau plan submittal materials (Form FPB-012) as part of the application packet
- Completeness review is 20 working days; substantive review is 40 working days (two 20-working-day review cycles); overall review time frame is 60 working days, per the Development Services Division's published time frames
- Working without a permit results in doubled permit fees and possible Order to Comply or required removal of non-compliant work
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing (Inspection Code 700)
Forms, reinforcing steel, and UFER ground in place prior to concrete placement.
- 2
Rough Frame (713)
Framing, shear panels, anchors, and structural connections installed but not covered.
- 3
Rough Electric (754)
Rough-in electrical installed but not covered.
- 4
Rough Plumbing/Topout (733)
Rough-in plumbing installed and under pressure test but not covered.
- 5
Rough HVAC (720)
Rough-in mechanical/HVAC work installed but not covered.
- 6
Roof Frame (716)
Roof framing/trusses installed and inspected prior to roof covering.
- 7
Fire Sprinkler Visual (760) / Fire Alarm System Visual (763)
If the building includes fire sprinkler or fire alarm systems, visual inspections of rough-in fire protection work.
- 8
Structural Final (719), Mechanical Final (726), Plumbing Final and Water Meter Verified (745), Electrical Final (759), Fire Protection Final (770)
Trade-specific final inspections completed per approved plans and applicable codes.
- 9
Final (799)
Overall building final inspection.
- 10
Certificate of Occupancy (782)
Issued once all applicable trade finals are approved and the building meets code for the requested occupancy classification.
See the full Chandler inspection guide — scheduling & re-inspection fees →
Tips
- Pre-Technical Site Plan Review is free and required before submitting for new commercial buildings or substantial additions.
- Walk-in plan review is limited mainly to residential and small/minor-scale commercial projects at the plan reviewer's discretion — budget for the full 60-working-day review track on most commercial projects.
- The 60-working-day overall timeline is built from two 20-working-day substantive review cycles — plan for at least one round of plan-review comments.
- A Wastewater Discharge Questionnaire (WWDQ) is required with non-residential building permit applications, separate from the building plan review itself.
- There is no separate commercial-specific fee table — commercial building permit fees use the same ICC-valuation-based table as residential construction (Fee Schedule §4.6.1).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-29.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Chandler building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Chandler.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Chandler
Commercial Building Permit (New Construction, Additions & Amenities) in other cities
Compare commercial building permit (new construction, additions & amenities) fees across Arizona →