Residential Building Permit (New Home / Addition / Remodel) in Chandler, Arizona

A building permit is required for new single-family residential construction, room additions, remodels, and most structural work in Chandler. Permit applications and plan submittals are submitted electronically through the Citizen Access portal (aca-prod.accela.com/CHANDLER/) or in person at 215 E. Buffalo St. Walk-in plan review is available Monday–Friday 8:00 AM–4:30 PM for residential additions and renovations. Building permit fees are valuation-based (ICC Building Valuation Data); plan review is 65% of the permit fee. Plans submitted on or after July 1, 2025 must comply with the 2024 I-Codes and 2023 NEC (Ordinance No. 5108).

Verified 2026-06-29 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Building permit — valuation-based fee table (Res. 4703)$1.00–$500: $50.00; $501–$2,000: $50.00 for first $500 plus $1.20 per additional $100; $2,001–$25,000: $68.00 for first $2,000 plus $12.50 per additional $1,000; $25,001–$50,000: $355.50 for first $25,000 plus $9.00 per additional $1,000; $50,001–$100,000: $580.50 for first $50,000 plus $6.25 per additional $1,000; $100,001–$500,000: $893.00 for first $100,000 plus $5.00 per additional $1,000; $500,001–$1,000,000: $2,893.00 for first $500,000 plus $4.25 per additional $1,000; $1,000,001 and up: $5,018.00 for first $1,000,000 plus $2.75 per additional $1,000City of Chandler Fee Schedule (Building Safety §29-1, Res. 4703), Section 4.6.1. Valuation for new construction = ICC Building Valuation Data $/sq ft; alterations = all construction costs approved by the Building Official. Minimum fee $50.00 (valuation $500 or less). Working without a permit: fees are doubled.
Plan review fee65% of the building permit feeCity of Chandler Fee Schedule, Section 4.6.2(a). Due at time of plan submittal. Expedited plan review (at Building Official's discretion): twice the normal plan review fee (4.6.2(c)). Additional revisions to approved plans: $60.00/hour, 1-hour minimum.
Foundation Only Permit25% of the calculated building permit feeCity of Chandler Fee Schedule, Section 4.6.4(h).
Re-inspection fee$60.00/hour, 1-hour minimumCity of Chandler Fee Schedule, Section 4.6.3(b).
Permit Reinstatement (within one year of expiration)50% of current permit feeCity of Chandler Fee Schedule, Section 4.6.4(i).

Review timeline

~520 business days

Typical estimate — confirm current times with the Chandler building department

Inspection process

  1. 1

    Footings

    All forms, reinforcing steel and UFER ground in place; schedule before concrete is poured. An additional inspection is required for stems poured separately.

  2. 2

    Monolithic footing

    Reinforcing steel, UFER, forms and accessories in place, but not covered.

  3. 3

    Plumbing (groundwork)

    Under-floor building drain installed, shaded and under pressure test, but not covered.

  4. 4

    Water piping and water service (groundwork)

    Under-floor water piping installed but not covered; water service yard piping installed and under pressure but not covered.

  5. 5

    Building sewers

    Sewer piping connecting the building to the private or public sewer is installed, shaded and properly supported, but not covered.

  6. 6

    Strap and shear

    All shear panels and mechanical fasteners installed, but not covered.

  7. 7

    Rough electrical, rough plumbing, rough HVAC, and framing (concurrent)

    Inspections 10–13 are typically done concurrently: all rough-in electrical installed (not covered); all rough-in plumbing installed and under pressure (not covered); all rough-in mechanical work installed (not covered); building is 'dried in' and all framing, gussets, shear panels, anchors and all trade rough-ins are in place (not covered).

  8. 8

    Wallboard

    Wallboard installed and nailed, but not filled or taped.

  9. 9

    Lath inspection (if applicable)

    All substrate wire mesh and trim installed, ready to receive stucco, but not covered.

  10. 10

    Final Inspection

    Building completed to the requirements of the approved plans, specifications, and the City of Chandler codes.

Tips

Frequently asked questions

How do I apply for a residential building permit in Chandler?
Apply electronically through the Citizen Access portal at aca-prod.accela.com/CHANDLER/ or walk in to 215 E. Buffalo St. (walk-in available Mon–Fri 8:00 AM–4:30 PM). Submit a completed Building Permit Application, a plot plan, and full construction drawings. Plans submitted on or after July 1, 2025 must comply with the 2024 I-Codes and 2023 NEC (Ordinance No. 5108). Source: City of Chandler Building Safety — Plan Review, Permits and Inspections page and Homeowner's Building Permit Manual (Rev. 4/09/26).
How are Chandler building permit fees calculated?
Fees are valuation-based using the City of Chandler Fee Schedule (Res. 4703). Valuation for new construction is based on ICC Building Valuation Data $/sq ft; for alterations, valuation is all construction costs approved by the Building Official. A plan review fee of 65% of the permit fee is due at submittal. Example: a $100,000 project = $893.00 permit fee + $580.45 plan review = approximately $1,473.45. Source: City of Chandler Fee Schedule §4.6 and Homeowner's Building Permit Manual.

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Chandler building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Chandler

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.