Residential Pool / Spa Permit in Chandler, Arizona

All swimming pools and spas in Chandler require a permit except prefabricated pools less than 18 inches deep. The flat permit fees are $110.00 for a pool and $55.00 for a spa (Fee Schedule §4.6.4(d) and (e)). Engineering plans stamped and sealed by an engineer are required for all custom in-ground pools and spas; plans are required for pre-manufactured above-ground pools and spas. Pools must not occupy the front yard and cannot be built across a property line. The 2024 ISPSC with Chandler amendments governs pool construction. Chandler pool barrier requirements mandate a 6-foot exterior barrier; interior barriers may be 4 feet.

Verified 2026-07-16 · Source

When you need this permit

  • All pools and spas require a permit except prefabricated pools less than 18 inches deep (Homeowner's Building Permit Manual, 'Work Exempt from Permit,' item 7)
  • Engineering plans stamped and sealed by an engineer are required for all custom in-ground pools and spas; plans required for all pre-manufactured above-ground pools and spas
  • Swimming pools shall not occupy any front yard; no pool or cool decking can be built across a property line
  • Pool equipment must be 5 feet from the water's edge; pool cannot be built within 5 feet of a building foundation without an engineered surcharge design
  • All easements must be cleared by utility companies before construction
  • Glazing within 5 feet of the water's edge where the bottom edge is less than 60 inches above grade must be safety-glazed (tinting film does not satisfy this requirement)
  • Pool barrier (exterior perimeter): minimum 6 feet above finished grade including all gates and doors; interior barrier (dwelling side): minimum 4 feet high
  • Pool barrier fence: no horizontal/vertical openings allowing a 4-inch sphere to pass; maximum vertical clearance at grade 2 inches on exterior side; wire mesh or chain link maximum mesh size 2.25 inches square
  • Pedestrian access gates must be self-closing, self-latching, and open outward from the pool; gate latches at least 54 inches above finished grade or made inaccessible to small children from outside

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Residential pool permit fee — flat feeCity of Chandler Fee Schedule, Section 4.6.4(d): 'Residential pool permit fee — $110.00.'
$110.00
Residential spa permit fee — flat feeCity of Chandler Fee Schedule, Section 4.6.4(e): 'Residential spa permit fee — $55.00.'
$55.00

Review timeline

Plan reviewTypical estimate — confirm current times with the Chandler building department
~5–15 business days

How long did your Residential Pool / Spa Permit permit actually take in Chandler?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Pre-gunite inspection

    First inspection; no one needs to be home. Plans and permit must be available on site. For custom in-ground pools: reinforcing steel, forms, and structural elements before gunite/shotcrete is applied.

  2. 2

    Pre-plaster inspection (barrier inspection)

    Second inspection; homeowner must be present if the house forms part of the interior barrier or there is no interior pool fence. If an interior fence encompasses the entire pool, homeowner presence is not required. All electrical service panels must be left unlocked for the inspector. Inspections requiring entry into the home will not be conducted unless a responsible adult is present.

  3. 3

    Final inspection

    All pool/spa work completed per approved plans, 2024 ISPSC with Chandler amendments. Pool barrier compliance verified.

See the full Chandler inspection guide — scheduling & re-inspection fees →

Tips

  • Chandler's pool permit is a flat $110.00 — significantly lower than valuation-based approaches.
  • Exterior pool barrier must be at least 6 feet above grade; interior barrier (house-side) may be 4 feet. Requirements apply regardless of whether children live at the property.
  • Homeowner must be present for the pre-plaster inspection if the house forms the interior barrier or there is no separate interior fence.
  • Pool equipment must be at least 5 feet from the water's edge. In-ground pools built within 5 feet of a building foundation require an engineered surcharge design.
  • Safety glazing is required for all glazing within 5 feet of the water's edge if the bottom edge of the glazing is less than 60 inches above grade.

Frequently asked questions

Chandler requires a residential pool / spa permit for: All pools and spas require a permit except prefabricated pools less than 18 inches deep (Homeowner's Building Permit Manual, 'Work Exempt from Permit,' item 7); Engineering plans stamped and sealed by an engineer are required for all custom in-ground pools and spas; plans required for all pre-manufactured above-ground pools and spas; Swimming pools shall not occupy any front yard; no pool or cool decking can be built across a property line; Pool equipment must be 5 feet from the water's edge; pool cannot be built within 5 feet of a building foundation without an engineered surcharge design; All easements must be cleared by utility companies before construction; Glazing within 5 feet of the water's edge where the bottom edge is less than 60 inches above grade must be safety-glazed (tinting film does not satisfy this requirement); Pool barrier (exterior perimeter): minimum 6 feet above finished grade including all gates and doors; interior barrier (dwelling side): minimum 4 feet high; Pool barrier fence: no horizontal/vertical openings allowing a 4-inch sphere to pass; maximum vertical clearance at grade 2 inches on exterior side; wire mesh or chain link maximum mesh size 2.25 inches square; Pedestrian access gates must be self-closing, self-latching, and open outward from the pool; gate latches at least 54 inches above finished grade or made inaccessible to small children from outside. If your project isn't listed, confirm with City of Chandler Development Services Department — Building Safety at 480-782-3000 before starting work.

Chandler charges a flat fee of $110.00 for a residential pool permit and $55.00 for a residential spa permit. These are flat fees (not valuation-based). Source: City of Chandler Fee Schedule, Section 4.6.4(d) and (e) (Res. 4703).

Plan review for a residential pool / spa permit in Chandler typically runs 5–15 business days. This is an estimate, not a published figure — confirm current review times with City of Chandler Development Services Department — Building Safety at 480-782-3000.

You'll need: Building Permit Application; Engineer-Stamped Pool Plans; Plot Plan. See the required-documents checklist on this page for details on each.

Chandler requires 3 inspection(s) for a residential pool / spa permit, in order: Pre-gunite inspection, Pre-plaster inspection (barrier inspection), Final inspection. Schedule each through City of Chandler Development Services Department — Building Safety (480-782-3000).

Apply through City of Chandler Development Services Department — Building Safety at 215 E. Buffalo St., Chandler, AZ 85225. Phone: 480-782-3000, email: prod@chandleraz.gov. Office hours: Monday – Friday 8:00 AM – 5:00 PM, except holidays; Walk-in plan review: Monday – Friday 8:00 AM – 4:30 PM. Official information: https://www.chandleraz.gov/government/departments/development-services/building-safety-plan-review-permits-and-inspections.

Chandler, Arizona has adopted: 2024 International Building Code (IBC) — adopted by Chandler City Council, Ordinance No. 5108; effective for plans submitted on or after July 1, 2025; Chandler amendments published in City Code Chapter 29, Article II (Ordinance No. 5108); 2024 International Residential Code (IRC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article VI); effective July 1, 2025; 2023 National Electrical Code (NEC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article III); effective July 1, 2025; Chandler's 2024 code set retains the 2023 NEC edition (not the 2024 NEC); 2024 International Plumbing Code (IPC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article IV); effective July 1, 2025; 2024 International Mechanical Code (IMC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article V); effective July 1, 2025; 2024 International Fuel Gas Code (IFGC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article VII); effective July 1, 2025; 2024 International Energy Conservation Code (IECC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article VIII); effective July 1, 2025; 2024 International Existing Building Code (IEBC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article IX); effective July 1, 2025; 2024 International Swimming Pool and Spa Code (ISPSC) — adopted by Ordinance No. 5108 (City Code Chapter 29, Article X); effective July 1, 2025; 2024 International Fire Code (IFC) — adopted by Ordinance No. 5108 (City Code Chapter 28); effective July 1, 2025. Local amendments apply — see the Chandler overview page for the full list.

The exterior perimeter pool barrier (including all gates and doors) must be at least 6 feet above finished grade or floor, measured on the exterior side. An interior barrier separating a dwelling from the pool may be 4 feet in height. Pool barrier requirements apply regardless of whether children live at the property. Source: Chandler Homeowner's Building Permit Manual (Rev. 4/09/26), Pool Barrier Guidelines section and Pool Fencing Requirements page.

Sources & verification

Verified against official sources. Last reviewed 2026-07-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Chandler building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.