EV Charger / EVSE Permit — Chandler, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.chandleraz.gov/government/departments/development-services/building-safety-plan-review-permits-and-inspections
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Chandler, Arizona
Chandler has no standalone EV-charger/EVSE permit type or fee line item. Installing electric vehicle charging equipment is electrical work governed by the 2023 National Electrical Code (NEC) with Chandler amendments (Ordinance No. 5108, City Code Chapter 29 Article III), and per the electrical-permit entry it is billed under the City's existing flat-fee electrical categories — most commonly the 'Miscellaneous minor residential work (1-2 branch electrical circuits...)' flat fee ($100.00, Fee Schedule Section 4.6.4(q)) for a simple added EV charger circuit, or the 'Electrical service 400 amps or less' flat fee ($100.00, Section 4.6.4(b)) if the installation involves a service/panel upgrade to support the charger. Neither the City's Fee Schedule nor the Homeowner's Building Permit Manual carries an EV-charger, EVSE, or electric-vehicle-specific line item.
Verified 2026-07-20 · Source
When you need this permit
- EV charger circuit installation is electrical work; apply through the Citizen Access portal or walk-in to 215 E. Buffalo St., using the standard Building Permit Application
- Must comply with the 2023 NEC with Chandler amendments (Ordinance No. 5108, City Code Chapter 29, Article III)
- Provide panel schedule showing existing and new breakers; load calculations required if adding a sub-panel or upgrading service to support the charger
- Specify size and type of conductors, conduit type, and burial depth for underground runs; indicate length of above-ground or attic runs
- Licensed contractor required unless owner-occupant performs own work (ARS 32-1121A; does not apply if the property is rented or leased) Owner-builderContractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
City of Chandler Fee Schedule, Section 4.6.4(q): 'Miscellaneous minor residential work (1-6 gas outlets, 1-2 branch electrical circuits, 1-6 plumbing openings, etc.) — $100.00.' No distinct EV-charger line item exists; Show full citationHide
City of Chandler Fee Schedule, Section 4.6.4(q): 'Miscellaneous minor residential work (1-6 gas outlets, 1-2 branch electrical circuits, 1-6 plumbing openings, etc.) — $100.00.' No distinct EV-charger line item exists; a typical single dedicated EV charger circuit would likely fall under this minor-work categoryReview timeline
Inspection process
- 1
Rough-In
New circuit wiring, box placement, and panel/sub-panel connections before walls are closed, if applicable
- 2
Final
Charger unit installed, dedicated circuit capacity and wire sizing verified per the 2023 NEC with Chandler amendments
See the full Chandler inspection guide — scheduling & re-inspection fees →
Tips
- There is no separate EV-charger fee category in Chandler -- a simple added EV charger circuit most likely qualifies for the flat $100 'Miscellaneous minor residential work (1-2 branch electrical circuits)' fee, while a service/panel upgrade to support the charger would fall under the flat $100 'Electrical service 400 amps or less' fee.
- Like-for-like replacement of circuit breakers alone does not require a permit, per the Homeowner's Building Permit Manual, but adding a new dedicated EV charger circuit does.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Chandler building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Chandler's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Chandler yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Chandler lands. Privacy.
Other permits in Chandler
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Arizona →
Look up this fee in a different city →