Inspection sequence, scheduling, and re-inspection fees for building permits in Gilbert, Arizona.

Verified 2026-07-16 · Source

How to schedule

Inspections are requested through the building department below.

Address
90 E. Civic Center Drive, Gilbert, AZ 85296
Phone
(480) 503-6700
Office hours
Monday–Thursday: 7:00 AM–6:00 PM; Friday: Closed (Town Hall operates a 4-day/10-hour week; confirmed live on the Development Services department page 2026-07-16)

Inspection sequence

Applies to: Fire Sprinkler & Fire Alarm System Permit

  1. 1

    Underground Fire Line Inspection

    Inspection of underground fire main/supply piping prior to backfill, where an underground fire line is part of the system

  2. 2

    Rough-In / Aboveground Piping Inspection

    Inspection of aboveground sprinkler piping, hangers, and fittings prior to concealment, per the adopted 2016 NFPA 13/13R/13D

  3. 3

    Hydrostatic Test / Flush

    Hydrostatic pressure test and underground flush of sprinkler piping per NFPA 13

  4. 4

    Fire Alarm / Monitoring Acceptance Test

    Acceptance testing of fire alarm and/or fire sprinkler monitoring system devices and circuits per the adopted 2016 NFPA 72

  5. 5

    Final Inspection

    Final inspection confirming the fire sprinkler and/or fire alarm system is complete and code-compliant

Applies to: Residential Building Permit (New Single-Family Dwelling)

  1. 1

    Foundation / Slab Inspection

    Inspection of foundation, footings, and slab before pouring concrete

  2. 2

    Rough Framing Inspection

    Inspection of framing, masonry, firestopping, draftstopping, and bracing after roof, masonry, and all framing are in place but before covering. Per IRC §R109.1.4 (as amended), inspection includes rough plumbing, mechanical, and electrical.

  3. 3

    Rough Plumbing / Mechanical / Gas / Electrical Inspection

    Rough inspection of plumbing, mechanical, gas, and electrical systems made prior to covering or concealment and before fixtures or appliances are set or installed (per IRC §R109.1.2 as amended)

  4. 4

    Insulation Inspection

    Inspection of insulation installation for energy code compliance before covering

  5. 5

    Final Inspection

    Final inspection confirming all systems complete and structure ready for occupancy; Certificate of Occupancy issued upon passing final

Applies to: Swimming Pool / Spa Permit

  1. 1

    Pre-Gunite / Pre-Shotcrete Inspection

    Inspection of rebar/steel placement before pool shell is formed

  2. 2

    Plumbing / Mechanical Inspection

    Inspection of pool plumbing, filtration, and mechanical systems

  3. 3

    Electrical / Bonding Inspection

    Inspection of pool electrical bonding and equipment wiring per 2017 NEC

  4. 4

    Barrier / Fence Inspection

    Inspection of required pool barrier/fencing

  5. 5

    Final Inspection

    Final inspection confirming pool complete and all safety requirements met

Applies to: Commercial Building Permit (New Construction / Tenant Improvement)

  1. 1

    Rough Inspections (Plumbing / Mechanical / Electrical)

    Rough-in inspections for all trades before concealment

  2. 2

    Framing Inspection

    Structural framing inspection before covering

  3. 3

    Fire System Inspections

    Fire sprinkler and alarm system inspections per 2018 IFC as adopted

  4. 4

    Final Inspection

    Final inspection of all systems; Certificate of Occupancy issued upon passing

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation / Slab Inspection

    Inspection of foundation and slab before pouring concrete

  2. 2

    Rough Framing / Systems Inspection

    Framing, rough plumbing, mechanical, and electrical inspections

  3. 3

    Final Inspection

    Final inspection confirming ADU complete and ready for occupancy

Applies to: Certificate of Occupancy / Change of Occupancy

  1. 1

    Final Inspection (Standard Certificate of Occupancy)

    Final inspection confirming all work under an active Building Permit is complete and compliant; triggers issuance of the standard Certificate of Occupancy

  2. 2

    Fire Sprinkler System Inspection (Change of Occupancy, Fire Hazard Level 1 only)

    Required when a change of occupancy within Fire Hazard Level 1 triggers the automatic fire sprinkler system requirement under 2018 IFC §903.2.2 as locally amended, regardless of building area

Applies to: Electrical Permit

  1. 1

    Rough Electrical Inspection

    Inspection of electrical rough-in before concealment; required prior to covering or concealment

  2. 2

    Final Electrical Inspection

    Final inspection confirming all electrical work complete and compliant with 2017 NEC as amended

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough Electrical Inspection

    Inspection of the EVSE circuit rough-in before concealment; required prior to covering or concealment

  2. 2

    Final Electrical Inspection

    Final inspection confirming the EVSE circuit and unit connections are complete and compliant with 2017 NEC as amended

Applies to: Fence / Wall Permit

  1. 1

    Footing / Post Inspection

    Inspection of fence footing/post placement before pouring concrete

  2. 2

    Final Fence Inspection

    Final inspection of completed fence

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical Inspection

    Inspection of mechanical rough-in before concealment

  2. 2

    Final Mechanical Inspection

    Final inspection confirming all mechanical work complete and compliant

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing Inspection

    Inspection of plumbing rough-in before covering or concealment, and before fixtures or appliances are set (per IRC §R109.1.2 as amended)

  2. 2

    Final Plumbing Inspection

    Final inspection confirming all plumbing work complete and compliant

Applies to: Sign Permit

  1. 1

    Sign Structural / Electrical Inspection

    Inspection of sign structure, mounting, and electrical connections

  2. 2

    Final Sign Inspection

    Final inspection confirming sign installation complete and compliant

Re-inspection fees

Residential Building Permit (New Single-Family Dwelling)Re-inspection Fee · Source: Town of Gilbert Development Services Fee Schedules (doc 5883), Applied Miscellaneous Building Fees, effective July 1, 2025, Resolution 4563.
$150 per re-inspection
Commercial Building Permit (New Construction / Tenant Improvement)Re-inspection Fee · Source: Town of Gilbert Development Services Fee Schedules (doc 5883), Applied Miscellaneous Building Fees, effective July 1, 2025, Resolution 4563.
$150 per re-inspection
Electrical PermitRe-inspection Fee · Source: Town of Gilbert Development Services Fee Schedules (doc 5883), Applied Miscellaneous Building Fees, effective July 1, 2025, Resolution 4563.
$150
Plumbing PermitRe-inspection Fee · Source: Town of Gilbert Development Services Fee Schedules (doc 5883), Applied Miscellaneous Building Fees, effective July 1, 2025, Resolution 4563.
$150
Mechanical / HVAC PermitRe-inspection Fee · Source: Town of Gilbert Development Services Fee Schedules (doc 5883), Applied Miscellaneous Building Fees, effective July 1, 2025, Resolution 4563.
$150
EV Charger / EVSE PermitRe-inspection Fee · Town of Gilbert Development Services Fee Schedule (doc 5883).
$150
Swimming Pool / Spa PermitRe-inspection Fee · Source: Town of Gilbert Development Services Fee Schedules (doc 5883), Applied Miscellaneous Building Fees, effective July 1, 2025, Resolution 4563.
$150
Fire Sprinkler & Fire Alarm System PermitRe-inspection Fee · Source: Town of Gilbert Development Services Fee Schedules (doc 5883), Fire Permit & Plan Review Fees — Additional Inspection/Plan Review Fees (page 18), effective July 1, 2025, Resolution 4563. Confirmed via visual PNG render of page 18.
$150

Gilbert building permits

Get alerts for Gilbert

We'll email you when Gilbert's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.