Residential Building Permit (New Single-Family Dwelling) in Gilbert, Arizona
Required for new single-family residential construction in the Town of Gilbert. Applications are submitted through the OneStopShop portal at onestopshop.gilbertaz.gov. The Plan Review and Inspection Division reviews plans against the 2018 IBC, 2018 IRC, and Town of Gilbert Technical Codes 2020 Edition. Custom single-family homes have a 12-working-day first review target and 8-working-day subsequent review target; standardized plans have a 3-working-day target.
Verified 2026-07-16 · Source
When you need this permit
- Submit through OneStopShop portal at onestopshop.gilbertaz.gov
- Plans must comply with 2018 IBC, 2018 IRC, 2018 IECC, 2018 IMC, 2018 IPC, 2018 IFGC, and 2017 NEC as amended by the Town of Gilbert Technical Codes 2020 Edition
- Soils report required unless subdivision has one on file with the Town or applicant supplies a signed soils report waiver (call 480-503-6700 to check)
- Arizona ROC-licensed contractor required unless property owner is building for sole occupancy and property will not be offered for sale or rent within one year of completion (per A.R.S. § 32-1121.A.5) Contractor
- Permit fee must be paid prior to permit issuance
- Development fees may apply in addition to permit fees
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Source: Town of Gilbert Development Services Fee Schedules (doc 5883), Building Permit and Plan Review Fees Table, effective July 1, 2025, adopted by Town Council May 20, 2025 by Resolution 4563. Show full citationHide
Source: Town of Gilbert Development Services Fee Schedules (doc 5883), Building Permit and Plan Review Fees Table, effective July 1, 2025, adopted by Town Council May 20, 2025 by Resolution 4563. Valuation determined from the ICC Building Valuation Data table, updated July 1 of each year by the Building Official.Review timeline
Inspection process
- 1
Foundation / Slab Inspection
Inspection of foundation, footings, and slab before pouring concrete
- 2
Rough Framing Inspection
Inspection of framing, masonry, firestopping, draftstopping, and bracing after roof, masonry, and all framing are in place but before covering. Per IRC §R109.1.4 (as amended), inspection includes rough plumbing, mechanical, and electrical.
- 3
Rough Plumbing / Mechanical / Gas / Electrical Inspection
Rough inspection of plumbing, mechanical, gas, and electrical systems made prior to covering or concealment and before fixtures or appliances are set or installed (per IRC §R109.1.2 as amended)
- 4
Insulation Inspection
Inspection of insulation installation for energy code compliance before covering
- 5
Final Inspection
Final inspection confirming all systems complete and structure ready for occupancy; Certificate of Occupancy issued upon passing final
See the full Gilbert inspection guide — scheduling & re-inspection fees →
Tips
- Custom single-family homes: 12/8 working-day review goals (1st/2nd reviews); standardized plans: 3/3 days. Targets are A.R.S. § 9-835 max time frames.
- All permit applications go through OneStopShop at onestopshop.gilbertaz.gov — not a walk-in counter process.
- Permits expire if substantial work is not started and inspections are not requested within 180 days of issuance. One 180-day extension may be requested in writing.
- Work-before-permit-issuance doubles the permit fee (penalty equals the full permit fee per Gilbert's IBC §109.4 amendment).
- Up to 80% of permit and plan review fees are refundable if no work is done or application is withdrawn; written request required from original permittee.
- Soils reports: call (480) 503-6700 before assuming you need a new one — your subdivision may already have one on file.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-16.
Fee schedules
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Gilbert building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Gilbert's permit history is searchable by address
195,893 permits in our copy of Gilbert's register — searchable by street address, with permit type, status, issued date and valuation where the city publishes them. This is what we hold, not a statement of everything Gilbert has issued.
All 195,893 carry an issued date, running from 1983 to 2026.
84% of Gilbert's records carry a street address to match against, so a search that finds nothing here means we could not look — not that the property is clear.
Other permits in Gilbert
Residential Building Permit (New Single-Family Dwelling) in other cities
Compare residential building permit (new single-family dwelling) fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Gilbert project checklist
Describe your project once and get every permit, document, and fee it triggers in Gilbert — in one checklist. Free, for any city and any number of projects.
Get started →