Electrical Permit in Gilbert, Arizona

Required for new electrical installations, alterations, repairs, replacements, and additions to electrical systems in the Town of Gilbert. Governed by the 2017 NEC with Town of Gilbert amendments (Code Chapter 10-32). Like-for-like replacements of equipment by Arizona licensed contractors may qualify as Over the Counter (OTC) review. Electrical permits for commercial projects have a 3/3 working-day review goal. An individual electrical permit (flat fee) is available for certain residential and commercial work.

Verified 2026-07-16 · Source

When you need this permit

  • Submit through OneStopShop portal at onestopshop.gilbertaz.gov
  • Arizona ROC-licensed electrical contractor required (owner-builder exemptions may apply for owner-occupied residential) Owner-builderContractor
  • Work must comply with 2017 NEC as amended by Town of Gilbert Code Chapter 10-32
  • No permit required for serving utility agency work in exercise of its serving function (NEC amendment IBC Appendix K §K103.2 Exception 6)
  • No permit required for area lighting and associated wiring installed and maintained under contract with the serving agency
  • Solar PV systems installed by an Arizona licensed contractor are exempt from permit (IBC §105.2 Building item 16, cross-referenced in Appendix K §K103.2 Exception 7) Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Individual Electrical Permit (Residential) — flat feeSource: Town of Gilbert Development Services Fee Schedules (doc 5883), Applied Miscellaneous Building Fees — Individual Electrical Permit, Residential, effective July 1, 2025, Resolution 4563.
$150
Individual Electrical Permit (Commercial) — flat feeSource: Town of Gilbert Development Services Fee Schedules (doc 5883), Applied Miscellaneous Building Fees — Individual Electrical Permit, Commercial, effective July 1, 2025, Resolution 4563.
$300
Building Permit Fee — valuation-based (for larger electrical projects)Source: Town of Gilbert Development Services Fee Schedules (doc 5883), Building Permit and Plan Review Fees Table, effective July 1, 2025, Resolution 4563. Applies when electrical work is valued and permit fee calculated from the standard valuation table rather than the flat individual permit fee.
Same valuation-based table as building permits; $50.00 minimum for work valued $1.00–$1,100.00
Plan Review Fee (where plan review is required)Source: Town of Gilbert Development Services Fee Schedules (doc 5883), effective July 1, 2025, Resolution 4563.
65% of the calculated Building Permit Fee
Re-inspection FeeSource: Town of Gilbert Development Services Fee Schedules (doc 5883), Applied Miscellaneous Building Fees, effective July 1, 2025, Resolution 4563.
$150

Review timeline

Plan reviewGilbert’s published plan-review target
3–3 business days

How long did your Electrical Permit permit actually take in Gilbert?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical Inspection

    Inspection of electrical rough-in before concealment; required prior to covering or concealment

  2. 2

    Final Electrical Inspection

    Final inspection confirming all electrical work complete and compliant with 2017 NEC as amended

See the full Gilbert inspection guide — scheduling & re-inspection fees →

Tips

  • Commercial electric permits have a 3/3 working-day review goal.
  • Solar PV systems installed by an Arizona licensed contractor are exempt from electrical permit per Gilbert's local amendment IBC §105.2 item 16. Contractor
  • No electrical system or equipment may be located on a lot other than the lot served, except within legally established easements (NEC Amendment §E3601.8 / IBC Appendix K §K102.3.1).
  • Individual flat-fee electrical permits: $150 residential, $300 commercial (adopted July 1, 2025).

Frequently asked questions

No — solar PV systems installed by an Arizona licensed contractor are exempt from permit per Town of Gilbert's local amendment to IBC §105.2 (item 16). This same exemption covers like-for-like replacements of gas and electric water heating systems/appliances and HVAC equipment replacements by AZ licensed contractors.

In Gilbert, the published Individual Electrical Permit (Residential) — flat fee is: $150. Additional published fees: Individual Electrical Permit (Commercial) — flat fee — $300; Building Permit Fee — valuation-based (for larger electrical projects) — Same valuation-based table as building permits; $50.00 minimum for work valued $1.00–$1,100.00; Plan Review Fee (where plan review is required) — 65% of the calculated Building Permit Fee; Re-inspection Fee — $150. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Gilbert's published plan-review target for an electrical permit is 3–3 business days.

You'll need: Electrical Permit Application. Depending on your project, Gilbert may also ask for: Electrical Plans / Load Calculations. See the required-documents checklist on this page for details on each.

Gilbert requires 2 inspection(s) for an electrical permit, in order: Rough Electrical Inspection, Final Electrical Inspection. Schedule each through Town of Gilbert Development Services Department — Plan Review and Inspection Division ((480) 503-6700).

Apply through Town of Gilbert Development Services Department — Plan Review and Inspection Division at 90 E. Civic Center Drive, Gilbert, AZ 85296. Phone: (480) 503-6700, email: onestopshop@gilbertaz.gov. Office hours: Monday–Thursday: 7:00 AM–6:00 PM; Friday: Closed (Town Hall operates a 4-day/10-hour week; confirmed live on the Development Services department page 2026-07-16). Official information: https://www.gilbertaz.gov/departments/development-services.

Gilbert, Arizona has adopted: 2018 International Building Code (IBC), with Appendices C, I, and K, and Town of Gilbert amendments — effective January 1, 2020 (Ordinance 2739, Town of Gilbert Technical Codes 2020 Edition); 2018 International Residential Code (IRC), with Appendices H, P, and Q, and Town of Gilbert amendments — effective January 1, 2020 (Ordinance 2739); 2018 International Mechanical Code (IMC), with Town of Gilbert amendments — effective January 1, 2020 (Ordinance 2739); 2018 International Plumbing Code (IPC), with Town of Gilbert amendments — effective January 1, 2020 (Ordinance 2739); 2018 International Energy Conservation Code (IECC), with Town of Gilbert amendments — effective January 1, 2020 (Ordinance 2739); 2018 International Fuel Gas Code (IFGC), with Town of Gilbert amendments — effective January 1, 2020 (Ordinance 2739); 2018 International Fire Code (IFC), with Town of Gilbert amendments — effective January 1, 2020 (Ordinance 2739); 2018 International Green Construction Code (IgCC) — voluntary adoption only — effective January 1, 2020 (Ordinance 2739); 2017 National Electrical Code (NEC), with Town of Gilbert amendments — effective January 1, 2020 (Ordinance 2739); 2010 ADA Standards for Accessible Design — effective January 1, 2020 (Ordinance 2739); Town of Gilbert Technical Codes 2020 Edition — local amendment overlay (Code of Gilbert Chapter 10, Sections 10-31 and 10-32) incorporating December 2023 amendments per gilbertaz.gov Document 35111. Local amendments apply — see the Gilbert overview page for the full list.