Goodyear building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Goodyear, Arizona.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
1900 N. Civic Square, 2nd Floor, Goodyear, AZ 85395
Phone
623-932-3910
Office hours
Development Center, 1900 N. Civic Square, Goodyear, AZ 85395; general Development Services line 623-932-3910; development counter/fee questions 623-932-3004 option 2; project fee estimate requests developmentcounter@goodyearaz.gov

Inspection sequence

Applies to: Commercial Building Permit (New Commercial Construction)

  1. 1

    Foundation/Footing

    Before concrete pour -- foundation and rebar per approved plans and 2018 IBC

  2. 2

    Framing / Structural

    Structural framing and connections per approved plans and 2018 IBC

  3. 3

    Rough Mechanical/Electrical/Plumbing

    Rough-in of mechanical, electrical, and plumbing systems before concealment

  4. 4

    Fire (where applicable)

    Fire sprinkler, alarm, or suppression system rough-in and final testing, reviewed separately under the Fire Plan Review Fee where the scope includes fire-code-regulated systems

  5. 5

    Final / Certificate of Occupancy

    Final inspection required for Certificate of Occupancy before the building may be occupied

Applies to: Residential Building Permit (New Construction / Custom Single-Family Home)

  1. 1

    Foundation/Footing

    Before concrete pour — foundation and rebar per approved plans

  2. 2

    Framing

    Structural framing per approved plans and 2018 IRC

  3. 3

    Rough Mechanical/Electrical/Plumbing

    Rough-in of mechanical, electrical, and plumbing systems before wall closure

  4. 4

    Final

    Final inspection for Certificate of Occupancy or Certificate of Completion, included in the building permit fee

Applies to: Accessory Dwelling Unit / Detached Guest House / Casita Permit

  1. 1

    Foundation/Footing

    Before concrete pour for the detached structure

  2. 2

    Framing

    Structural framing per approved plans

  3. 3

    Final

    Final inspection for occupancy of the accessory structure

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Rough Mechanical/Electrical/Plumbing

    Rough-in of any altered or added mechanical, electrical, or plumbing systems before concealment

  2. 2

    Fire (where applicable)

    Fire sprinkler, alarm, or suppression system rough-in and final testing where the TI scope alters fire-code-regulated systems

  3. 3

    Final / Certificate of Occupancy

    Final inspection required before the tenant space may be occupied under the new scope of work

Applies to: Residential Addition / Alteration / Remodel Permit

  1. 1

    Footing/Foundation

    Required before concrete pour for additions, detached garages, or casitas

  2. 2

    Framing

    Structural framing and connections to the existing structure

  3. 3

    Final

    All work complete per approved plans

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring, box placement, and panel connections before wall closure

  2. 2

    Final

    Devices installed, panel labeled, protections verified per 2017 NEC

Applies to: EV Charger / Electric Vehicle Charging Station Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement verified before concealment

  2. 2

    Final

    New circuit, breaker sizing, and disconnect verified before the charger is energized

Applies to: Fence, Wall, and Retaining Wall Permit

  1. 1

    Footing

    Required for engineered retaining walls before backfill

  2. 2

    Final

    Completed fence/wall verified against approved plans

Applies to: Fire Sprinkler and Fire Alarm System Permit

  1. 1

    Rough-In / Underground

    Sprinkler piping, alarm wiring, and device placement verified before concealment, per the City of Goodyear Fire Department Fire Prevention Division

  2. 2

    Final Acceptance Test

    Hydrostatic/flow acceptance test (fire sprinkler systems) or full functional test (fire alarm systems) witnessed by the City of Goodyear Fire Department before the system is placed in service

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and equipment rough-in before wall closure

  2. 2

    Final

    Equipment operational, clearances and venting verified per 2018 IMC

Applies to: Plumbing Permit

  1. 1

    Rough-In

    Pipe installation before wall closure or concealment

  2. 2

    Final

    All fixtures connected, water heater T&P valve verified, no leaks

Applies to: Sign Permit

  1. 1

    Rough-In (Electrical, if illuminated)

    Wiring and connections verified before the sign face/cabinet is closed, for illuminated signs only

  2. 2

    Final

    Sign construction, location, and height verified against the approved sign permit and/or Comprehensive Sign Package, plus electrical connections where applicable

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final

    Panel mounting, racking attachment, roof penetration sealing, and interconnection point verified

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Goodyear building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Goodyear building permits

Get alerts for Goodyear

We'll email you when Goodyear's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.