Commercial Building Permit (New Commercial Construction) in Goodyear, Arizona

Required for new commercial building construction in Goodyear, billed under the Development Services Fee Schedule's Commercial Fees 'New Construction and Additions' line item and reviewed against the 2018 IBC and City of Goodyear amendments (City Code Section 9-1-1) plus ICC A117.1-2009 accessibility standards. Tenant improvement work to an existing commercial building is NOT folded into this entry: although the 'New Construction and Additions' and 'Tenant Improvement' fee lines in the Commercial Fees table are billed identically (65% plan review + Table 1-A permit fee + $86 Planning and Zoning + $102 Application), the City's own Plan Review Target Time Frames page lists them as two separate rows under 'Commercial Construction' with materially different target windows -- New Commercial at 5/25/15 business days versus Tenant Improvement at 5/15/10 business days -- so tenant improvement is documented as its own commercial-tenant-improvement-permit entry in this file.

Verified 2026-08-01 · Source

When you need this permit

  • Building permit required for new commercial building construction; reviewed against the 2018 IBC and City of Goodyear amendments (City Code Section 9-1-1, 'Adoption by reference'), plus ICC A117.1-2009 and the 2010 ADA Standards for Accessible Design
  • 'Commercial permits require plan review by Building Safety personnel,' per the header of the Commercial Fees section of the Development Services Fee Schedule
  • New Commercial construction is billed under the Commercial Fees 'New Construction and Additions' line: 65% of the Table 1-A permit fee for plan review, plus the Table 1-A valuation-based permit fee itself (the same valuation table used for the Residential Building Permit in this file), an $86 Planning and Zoning fee, and a $102 application fee
  • Subject to Development Impact Fees in addition to permit and plan review fees -- the Commercial Fees table specifically asterisks the 'New Construction and Additions*' line item with 'Subject to Development Impact Fees in addition to those shown above,' due at permit issuance and varying by zone (North, South, Northwest Rainbow Valley)
  • Fire Plan Review Fees (35% of the calculated permit fee, minimum charge per application) apply in addition to Building Plan Review Fees where the scope includes fire-code-regulated systems (sprinkler, alarm, hood suppression, etc.)
  • Application submitted via the City's Accela Citizen Access (ACA) online portal, the same portal used for residential submittals -- Goodyear does not use a separate email-based commercial intake process
  • Building/Fire plan review is valid for 180 days from plan approval (one 180-day extension available by written request); building/fire permits are valid for 180 days from issuance or the last passed inspection, whichever is later (one 180-day extension available)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

New Construction and Additions (Commercial Building Permit)City of Goodyear Development Services Fee Schedule (PDF, 10/13/2023), Commercial Fees, 'New Construction and Additions*' line item; the standard text extraction of this PDF misaligns the two-column fee table, so this figure was confirmed by direct word-position (bbox) extraction of the source PDF cross-referencing each fee value's vertical position against its row label. Uses the same Table 1-A valuation brackets documented under the Residential Building Permit entry in this file.
65% of Permit Fee (Plan Review) + Table 1-A Permit Fee + $86 Planning and Zoning + $102 Application
Development Impact Fees (New Commercial only)City of Goodyear Development Services Fee Schedule, Commercial Fees -- the 'New Construction and Additions*' line is explicitly asterisked as impact-fee-subject; effective April 1, 2024 per the City's Development Impact Fees update
Varies by zone (North, South, Northwest Rainbow Valley); charged in addition to permit/plan review fees
Fire Plan Review FeeCity of Goodyear Development Services Fee Schedule, Building Safety Fees overview; applies where the project scope includes fire-code-regulated systems
35% of the calculated permit fee (minimum charge per application)
Temporary Certificate of Occupancy or Certificate of CompletionCity of Goodyear Development Services Fee Schedule, Miscellaneous Fees; confirmed by direct read of the raw PDF text. No separate standard (non-temporary) Certificate of Occupancy fee line was found published -- the final Certificate of Occupancy inspection appears to be included in the base permit fee, consistent with how the Residential Building Permit entry in this file documents its Final/C.O. inspection.
$500 initial request (valid 45 calendar days); renewal at 5% of the original permit fee paid (minimum $200)

Review timeline

Plan reviewGoodyear’s published plan-review target
5–25 business days

How long did your Commercial Building Permit (New Commercial Construction) permit actually take in Goodyear?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour -- foundation and rebar per approved plans and 2018 IBC

  2. 2

    Framing / Structural

    Structural framing and connections per approved plans and 2018 IBC

  3. 3

    Rough Mechanical/Electrical/Plumbing

    Rough-in of mechanical, electrical, and plumbing systems before concealment

  4. 4

    Fire (where applicable)

    Fire sprinkler, alarm, or suppression system rough-in and final testing, reviewed separately under the Fire Plan Review Fee where the scope includes fire-code-regulated systems

  5. 5

    Final / Certificate of Occupancy

    Final inspection required for Certificate of Occupancy before the building may be occupied

See the full Goodyear inspection guide — scheduling & re-inspection fees →

Tips

  • New Commercial construction has a Plan Review Target Time Frame of 5 (prescreen) / 25 (1st department review) / 15 (2nd+ review) business days per the City's Review Times page (updated 2/12/2026) -- noticeably slower than the 5/15/10 target for Tenant Improvement under the same 'Commercial Construction' category, even though both are billed on the identical fee line structure.
  • The 'New Construction and Additions*' fee line carries an explicit Development Impact Fee asterisk that the 'Tenant Improvement' line does not -- consistent with impact fees generally applying to new floor area rather than interior work in an existing building.
  • Fire Plan Review (35% of permit fee) is billed separately from Building Plan Review (65% of permit fee) where fire-code-regulated systems are part of the project scope, per the City's Building Safety Fees overview.
  • No standard (non-temporary) Certificate of Occupancy fee was found in the published Fee Schedule; only a Temporary Certificate of Occupancy/Completion fee ($500 initial, 45-day validity) is separately listed under Miscellaneous Fees.

Frequently asked questions

Goodyear requires a commercial building permit (new commercial construction) for: Building permit required for new commercial building construction; reviewed against the 2018 IBC and City of Goodyear amendments (City Code Section 9-1-1, 'Adoption by reference'), plus ICC A117.1-2009 and the 2010 ADA Standards for Accessible Design; 'Commercial permits require plan review by Building Safety personnel,' per the header of the Commercial Fees section of the Development Services Fee Schedule; New Commercial construction is billed under the Commercial Fees 'New Construction and Additions' line: 65% of the Table 1-A permit fee for plan review, plus the Table 1-A valuation-based permit fee itself (the same valuation table used for the Residential Building Permit in this file), an $86 Planning and Zoning fee, and a $102 application fee; Subject to Development Impact Fees in addition to permit and plan review fees -- the Commercial Fees table specifically asterisks the 'New Construction and Additions*' line item with 'Subject to Development Impact Fees in addition to those shown above,' due at permit issuance and varying by zone (North, South, Northwest Rainbow Valley); Fire Plan Review Fees (35% of the calculated permit fee, minimum charge per application) apply in addition to Building Plan Review Fees where the scope includes fire-code-regulated systems (sprinkler, alarm, hood suppression, etc.); Application submitted via the City's Accela Citizen Access (ACA) online portal, the same portal used for residential submittals -- Goodyear does not use a separate email-based commercial intake process; Building/Fire plan review is valid for 180 days from plan approval (one 180-day extension available by written request); building/fire permits are valid for 180 days from issuance or the last passed inspection, whichever is later (one 180-day extension available). If your project isn't listed, confirm with City of Goodyear Development Services — Building Safety Division at 623-932-3910 before starting work.

New commercial construction is billed under the 'New Construction and Additions' Commercial Fees line: 65% of the Table 1-A permit fee for plan review, the Table 1-A valuation-based permit fee itself, an $86 Planning and Zoning fee, and a $102 application fee, plus Development Impact Fees (which vary by zone) due at permit issuance. Fire Plan Review (35% of the permit fee) applies in addition where fire-code-regulated systems are part of the scope.

Per the City of Goodyear's Plan Review Target Time Frames (updated 2/12/2026), 'New Commercial' construction has a target of 5 business days for prescreen, 25 business days for 1st department review, and 15 business days for 2nd-and-subsequent reviews. These are staff targets, not the statutory maximum review times required under Arizona SB 1598.

You'll need: Building Permit Application; Construction / Building Plans. Depending on your project, Goodyear may also ask for: Project Fee Estimate Form. See the required-documents checklist on this page for details on each.

Goodyear requires 5 inspection(s) for a commercial building permit (new commercial construction), in order: Foundation/Footing, Framing / Structural, Rough Mechanical/Electrical/Plumbing, Fire (where applicable), Final / Certificate of Occupancy. Schedule each through City of Goodyear Development Services — Building Safety Division (623-932-3910).

Apply through City of Goodyear Development Services — Building Safety Division at 1900 N. Civic Square, 2nd Floor, Goodyear, AZ 85395. Phone: 623-932-3910, email: buildingsafety@goodyearaz.gov. Office hours: Development Center, 1900 N. Civic Square, Goodyear, AZ 85395; general Development Services line 623-932-3910; development counter/fee questions 623-932-3004 option 2; project fee estimate requests developmentcounter@goodyearaz.gov. Official information: https://www.goodyearaz.gov/government/departments/engineering-development-services/development-services/building-safety-division/currently-adopted-building-codes.

Goodyear, Arizona has adopted: Arizona has no mandatory statewide building code for general construction — the state legislature does not adopt a single edition binding all municipalities; each Arizona city/town or county adopts and amends its own building code by ordinance (contrast with counties, which are directed by A.R.S. Title 11 to adopt at least the most recent edition or the immediately preceding edition of the ICC codes for unincorporated areas). The City of Goodyear operates its own Development Services / Building Safety Division and administers its own adopted codes and permitting program within city limits — it does not defer to Maricopa County. Source: City of Goodyear Building Safety Division, Currently Adopted Building Codes page.; 2018 International Building Code (IBC) — City of Goodyear, with local amendments, effective November 27, 2019. Source: City of Goodyear Currently Adopted Building Codes page; 2018 International Residential Code for One- and Two-Family Dwellings (IRC) — City of Goodyear, with local amendments, effective November 27, 2019, plus City of Goodyear Residential Design Standards (Table 301.2(1)); 2018 International Mechanical Code (IMC) — City of Goodyear, with local amendments, effective November 27, 2019; 2018 International Plumbing Code (IPC) — City of Goodyear, with local amendments, effective November 27, 2019 (Arizona municipalities generally use the IPC rather than the Uniform Plumbing Code); 2018 International Fuel Gas Code (IFGC) — City of Goodyear, with local amendments, effective November 27, 2019; 2018 International Energy Conservation Code (IECC) — City of Goodyear, with local amendments, effective November 27, 2019; 2018 International Existing Building Code (IEBC) — City of Goodyear, with local amendments, effective November 27, 2019; 2018 International Property Maintenance Code (IPMC) — City of Goodyear, with local amendments, effective November 27, 2019; 2018 International Fire Code (IFC) — City of Goodyear, with local amendments, effective November 27, 2019; City Code Fire Code amendments codified at Section 5-2-1 (International Fire Code Adopted); 2017 National Electrical Code (NEC) — City of Goodyear (Goodyear retains the 2017 NEC rather than a later edition as of this review); ICC A117.1-2009 Accessible and Usable Buildings and Facilities — American National Standards Institute / International Code Council; 2010 ADA Standards for Accessible Design — U.S. Department of Justice; NFPA 99 (2018 Edition), Standard for Health Care Facilities Code — National Fire Protection Association; Technical Building Codes amendments codified at City Code Section 9-1-1 ('Adoption by reference'). Source: City of Goodyear Currently Adopted Building Codes page (Building Safety Division). Local amendments apply — see the Goodyear overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-08-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Goodyear building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Goodyear.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.