Required for new single-family residential construction in Goodyear, including custom homes and standard (production) plans. Reviewed against the 2018 IRC and 2018 IECC as adopted by the City of Goodyear with local amendments. Applications are submitted through the City's Accela Citizen Access (ACA) online portal; fees are valuation-based per the Development Services Fee Schedule, using ICC Building Valuation Data updated each March 1 and September 1.

Verified 2026-07-03 · Source

When you need this permit

  • Building permit required for new single-family and custom-home construction; plans must comply with the 2018 IRC and 2018 IECC as adopted by the City of Goodyear
  • Custom Single-Family Residence permits are billed 65% of the Table 1-A permit fee for plan review, plus the Table 1-A valuation-based permit fee itself, a $86 Planning and Zoning fee, and a $102 application fee (in addition to any applicable civil engineering permit/plan review fees and Development Impact Fees)
  • Standard Plan – Single Family (a previously-approved standard plan on file) uses the same 65%-of-permit-fee plan review structure but may qualify for Express Lane review (target under 7 working days) if using an approved standard plan; new production homes may alternatively use the EZ Permit Application track (target 5/6/6 business days per the Review Times schedule)
  • Application submitted via the City's Accela Citizen Access (ACA) online portal
  • Fee payments up to $2,000,000 may be made via a zero-fee eCheck (ACH); credit card payments are accepted up to $75,000 at a 2.75% service fee (effective per the Fees for Development Services page)
  • Subject to Development Impact Fees (North Zone, South Zone, or Northwest Rainbow Valley) in addition to permit and plan review fees, due at permit issuance

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Project Valuation $1-$10,000City of Goodyear Development Services Fee Schedule, Valuation Table 1-A (10/13/2023)
$100 flat fee (no Building Plan Review)
Project Valuation $10,001-$25,000City of Goodyear Development Services Fee Schedule, Valuation Table 1-A
$294 for the first $10,000, plus $18 for each additional $1,000 or fraction thereof
Project Valuation $25,001-$50,000City of Goodyear Development Services Fee Schedule, Valuation Table 1-A
$564 for the first $25,000, plus $14 for each additional $1,000 or fraction thereof
Project Valuation $50,001-$100,000City of Goodyear Development Services Fee Schedule, Valuation Table 1-A
$914 for the first $50,000, plus $10 for each additional $1,000 or fraction thereof
Project Valuation $100,001-$500,000City of Goodyear Development Services Fee Schedule, Valuation Table 1-A
$1,416 for the first $100,000, plus $8 for each additional $1,000 or fraction thereof
Project Valuation $500,001-$1,000,000City of Goodyear Development Services Fee Schedule, Valuation Table 1-A
$4,616 for the first $500,000, plus $7 for each additional $1,000 or fraction thereof
Project Valuation $1,000,001 and aboveCity of Goodyear Development Services Fee Schedule, Valuation Table 1-A
$8,116 for the first $1,000,000, plus $3 for each additional $1,000 or fraction thereof
Building/Fire Plan Review Fee (Tier 1, above $10,000 valuation)City of Goodyear Development Services Fee Schedule; not applicable to Tier 1 ($1-$10,000, which has no plan review fee)
65% of Permit Fee
Custom Single-Family Residence — Planning and Zoning fee / Application feeCity of Goodyear Development Services Fee Schedule, Residential Fees
$86 Planning and Zoning + $102 Application
Building/Fire Plan Review — 3rd and subsequent reviewsCity of Goodyear Development Services Fee Schedule, Valuation Table 1-A
$97 per hour (minimum 1 hour)

Review timeline

Plan reviewGoodyear’s published plan-review target
5–25 business days

How long did your Residential Building Permit (New Construction / Custom Single-Family Home) permit actually take in Goodyear?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour — foundation and rebar per approved plans

  2. 2

    Framing

    Structural framing per approved plans and 2018 IRC

  3. 3

    Rough Mechanical/Electrical/Plumbing

    Rough-in of mechanical, electrical, and plumbing systems before wall closure

  4. 4

    Final

    Final inspection for Certificate of Occupancy or Certificate of Completion, included in the building permit fee

See the full Goodyear inspection guide — scheduling & re-inspection fees →

Tips

  • Single Family — Custom Home has a Plan Review Target Time Frame of 5 (prescreen) / 15 (1st department review) / 10 (2nd+ review) business days per the City's Review Times page (updated 2/12/2026); these are staff targets, not the SB 1598 statutory maximums.
  • A Standard Plan Single Family Residence (previously approved plan on file) instead targets 5/15/10 business days for standard review, or may qualify for Express Lane treatment (under 7 working days) or the EZ Permit track (5/6/6 business days) for new production homes.
  • The City updates ICC Building Valuation Data twice yearly (March 1 and September 1), which changes the per-square-foot valuation used to calculate permit fees.
  • Development Impact Fees are separate from permit/plan review fees and are charged at permit issuance; they vary by zone (North, South, Northwest Rainbow Valley) — use the Project Estimate Form or email developmentcounter@goodyearaz.gov for a full cost breakdown before applying.

Frequently asked questions

Goodyear requires a residential building permit (new construction / custom single-family home) for: Building permit required for new single-family and custom-home construction; plans must comply with the 2018 IRC and 2018 IECC as adopted by the City of Goodyear; Custom Single-Family Residence permits are billed 65% of the Table 1-A permit fee for plan review, plus the Table 1-A valuation-based permit fee itself, a $86 Planning and Zoning fee, and a $102 application fee (in addition to any applicable civil engineering permit/plan review fees and Development Impact Fees); Standard Plan – Single Family (a previously-approved standard plan on file) uses the same 65%-of-permit-fee plan review structure but may qualify for Express Lane review (target under 7 working days) if using an approved standard plan; new production homes may alternatively use the EZ Permit Application track (target 5/6/6 business days per the Review Times schedule); Application submitted via the City's Accela Citizen Access (ACA) online portal; Fee payments up to $2,000,000 may be made via a zero-fee eCheck (ACH); credit card payments are accepted up to $75,000 at a 2.75% service fee (effective per the Fees for Development Services page); Subject to Development Impact Fees (North Zone, South Zone, or Northwest Rainbow Valley) in addition to permit and plan review fees, due at permit issuance. If your project isn't listed, confirm with City of Goodyear Development Services — Building Safety Division at 623-932-3910 before starting work.

In Goodyear, the published Project Valuation $1-$10,000 is: $100 flat fee (no Building Plan Review). Additional published fees: Project Valuation $10,001-$25,000 — $294 for the first $10,000, plus $18 for each additional $1,000 or fraction thereof; Project Valuation $25,001-$50,000 — $564 for the first $25,000, plus $14 for each additional $1,000 or fraction thereof; Project Valuation $50,001-$100,000 — $914 for the first $50,000, plus $10 for each additional $1,000 or fraction thereof; Project Valuation $100,001-$500,000 — $1,416 for the first $100,000, plus $8 for each additional $1,000 or fraction thereof; Project Valuation $500,001-$1,000,000 — $4,616 for the first $500,000, plus $7 for each additional $1,000 or fraction thereof; Project Valuation $1,000,001 and above — $8,116 for the first $1,000,000, plus $3 for each additional $1,000 or fraction thereof; Building/Fire Plan Review Fee (Tier 1, above $10,000 valuation) — 65% of Permit Fee; Custom Single-Family Residence — Planning and Zoning fee / Application fee — $86 Planning and Zoning + $102 Application; Building/Fire Plan Review — 3rd and subsequent reviews — $97 per hour (minimum 1 hour). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the City of Goodyear's Plan Review Target Time Frames (updated 2/12/2026), Single Family — Custom Home has a target of 5 business days for prescreen, 15 business days for 1st department review, and 10 business days for 2nd-and-subsequent reviews. These are staff targets, not the statutory maximum review times required under SB 1598.

You'll need: Building Permit Application; Construction Drawings. Depending on your project, Goodyear may also ask for: Project Fee Estimate Form. See the required-documents checklist on this page for details on each.

Goodyear requires 4 inspection(s) for a residential building permit (new construction / custom single-family home), in order: Foundation/Footing, Framing, Rough Mechanical/Electrical/Plumbing, Final. Schedule each through City of Goodyear Development Services — Building Safety Division (623-932-3910).

Apply through City of Goodyear Development Services — Building Safety Division at 1900 N. Civic Square, 2nd Floor, Goodyear, AZ 85395. Phone: 623-932-3910, email: buildingsafety@goodyearaz.gov. Office hours: Development Center, 1900 N. Civic Square, Goodyear, AZ 85395; general Development Services line 623-932-3910; development counter/fee questions 623-932-3004 option 2; project fee estimate requests developmentcounter@goodyearaz.gov. Official information: https://www.goodyearaz.gov/government/departments/engineering-development-services/development-services/building-safety-division/currently-adopted-building-codes.

Goodyear, Arizona has adopted: Arizona has no mandatory statewide building code for general construction — the state legislature does not adopt a single edition binding all municipalities; each Arizona city/town or county adopts and amends its own building code by ordinance (contrast with counties, which are directed by A.R.S. Title 11 to adopt at least the most recent edition or the immediately preceding edition of the ICC codes for unincorporated areas). The City of Goodyear operates its own Development Services / Building Safety Division and administers its own adopted codes and permitting program within city limits — it does not defer to Maricopa County. Source: City of Goodyear Building Safety Division, Currently Adopted Building Codes page.; 2018 International Building Code (IBC) — City of Goodyear, with local amendments, effective November 27, 2019. Source: City of Goodyear Currently Adopted Building Codes page; 2018 International Residential Code for One- and Two-Family Dwellings (IRC) — City of Goodyear, with local amendments, effective November 27, 2019, plus City of Goodyear Residential Design Standards (Table 301.2(1)); 2018 International Mechanical Code (IMC) — City of Goodyear, with local amendments, effective November 27, 2019; 2018 International Plumbing Code (IPC) — City of Goodyear, with local amendments, effective November 27, 2019 (Arizona municipalities generally use the IPC rather than the Uniform Plumbing Code); 2018 International Fuel Gas Code (IFGC) — City of Goodyear, with local amendments, effective November 27, 2019; 2018 International Energy Conservation Code (IECC) — City of Goodyear, with local amendments, effective November 27, 2019; 2018 International Existing Building Code (IEBC) — City of Goodyear, with local amendments, effective November 27, 2019; 2018 International Property Maintenance Code (IPMC) — City of Goodyear, with local amendments, effective November 27, 2019; 2018 International Fire Code (IFC) — City of Goodyear, with local amendments, effective November 27, 2019; City Code Fire Code amendments codified at Section 5-2-1 (International Fire Code Adopted); 2017 National Electrical Code (NEC) — City of Goodyear (Goodyear retains the 2017 NEC rather than a later edition as of this review); ICC A117.1-2009 Accessible and Usable Buildings and Facilities — American National Standards Institute / International Code Council; 2010 ADA Standards for Accessible Design — U.S. Department of Justice; NFPA 99 (2018 Edition), Standard for Health Care Facilities Code — National Fire Protection Association; Technical Building Codes amendments codified at City Code Section 9-1-1 ('Adoption by reference'). Source: City of Goodyear Currently Adopted Building Codes page (Building Safety Division). Local amendments apply — see the Goodyear overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Goodyear building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.