Residential Building Permit (New Construction / Custom Single-Family Home) in Goodyear, Arizona

Verified

Required for new single-family residential construction in Goodyear, including custom homes and standard (production) plans. Reviewed against the 2018 IRC and 2018 IECC as adopted by the City of Goodyear with local amendments. Applications are submitted through the City's Accela Citizen Access (ACA) online portal; fees are valuation-based per the Development Services Fee Schedule, using ICC Building Valuation Data updated each March 1 and September 1.

Verified 2026-07-03 · Source

From$100Project Valuation $1-$10,000 — see all 10 fees below

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Project Valuation $1-$10,000$100 flat fee (no Building Plan Review)City of Goodyear Development Services Fee Schedule, Valuation Table 1-A (10/13/2023)
Project Valuation $10,001-$25,000$294 for the first $10,000, plus $18 for each additional $1,000 or fraction thereofCity of Goodyear Development Services Fee Schedule, Valuation Table 1-A
Project Valuation $25,001-$50,000$564 for the first $25,000, plus $14 for each additional $1,000 or fraction thereofCity of Goodyear Development Services Fee Schedule, Valuation Table 1-A
Project Valuation $50,001-$100,000$914 for the first $50,000, plus $10 for each additional $1,000 or fraction thereofCity of Goodyear Development Services Fee Schedule, Valuation Table 1-A
Project Valuation $100,001-$500,000$1,416 for the first $100,000, plus $8 for each additional $1,000 or fraction thereofCity of Goodyear Development Services Fee Schedule, Valuation Table 1-A
Project Valuation $500,001-$1,000,000$4,616 for the first $500,000, plus $7 for each additional $1,000 or fraction thereofCity of Goodyear Development Services Fee Schedule, Valuation Table 1-A
Project Valuation $1,000,001 and above$8,116 for the first $1,000,000, plus $3 for each additional $1,000 or fraction thereofCity of Goodyear Development Services Fee Schedule, Valuation Table 1-A
Building/Fire Plan Review Fee (Tier 1, above $10,000 valuation)65% of Permit FeeCity of Goodyear Development Services Fee Schedule; not applicable to Tier 1 ($1-$10,000, which has no plan review fee)
Custom Single-Family Residence — Planning and Zoning fee / Application fee$86 Planning and Zoning + $102 ApplicationCity of Goodyear Development Services Fee Schedule, Residential Fees
Building/Fire Plan Review — 3rd and subsequent reviews$97 per hour (minimum 1 hour)City of Goodyear Development Services Fee Schedule, Valuation Table 1-A

Review timeline

525 business days

Goodyear’s published plan-review target

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour — foundation and rebar per approved plans

  2. 2

    Framing

    Structural framing per approved plans and 2018 IRC

  3. 3

    Rough Mechanical/Electrical/Plumbing

    Rough-in of mechanical, electrical, and plumbing systems before wall closure

  4. 4

    Final

    Final inspection for Certificate of Occupancy or Certificate of Completion, included in the building permit fee

Tips

Frequently asked questions

How long does a custom single-family building permit take to review in Goodyear?
Per the City of Goodyear's Plan Review Target Time Frames (updated 2/12/2026), Single Family — Custom Home has a target of 5 business days for prescreen, 15 business days for 1st department review, and 10 business days for 2nd-and-subsequent reviews. These are staff targets, not the statutory maximum review times required under SB 1598.

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Goodyear building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Goodyear

Residential Building Permit (New Construction / Custom Single-Family Home) in other cities

Compare residential building permit (new construction / custom single-family home) fees across Arizona

Project checklist — coming soon

Describe your project once and get every permit, document, and fee it triggers in Goodyear — in one checklist. Leave your email and we'll tell you when it's ready.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.