Change of Use / Certificate of Occupancy Permit — Goodyear, Arizona · Requirements sheet
Reviewed 2026-08-04 · Source: https://goodyear.municipal.codes/ZoningOrds/1-3-6
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use / Certificate of Occupancy Permit in Goodyear, Arizona
Required whenever a building or land's use fails to conform with the Zoning Ordinance and applicable codes -- Goodyear Zoning Ordinance Section 1-3-6 ('Building Permits and Certificates of Occupancy') states that neither building permits nor certificates of occupancy may be issued until the use of the building(s) and land conform with the Ordinance and all other applicable codes and ordinances, and that Development Services staff processes and releases all Certificates of Occupancy. Separately, City Code Section 9-8-9 ('Calculation and collection of development fees') requires development fees to be recalculated whenever a structure is occupied by a use inconsistent with the development category originally used to calculate those fees, with additional fees due no later than the Building Permit or Certificate of Occupancy application for the new use. This review confirmed the underlying legal requirement in detail but could NOT confirm a specific dollar fee figure for a standalone Change of Use / Change of Occupancy application -- see fee notes.
Reviewed 2026-08-04 · Source
When you need this permit
- A building or tenant space's use/occupancy must conform to the Zoning Ordinance and all applicable codes before a building permit or Certificate of Occupancy may be issued, per Zoning Ordinance Section 1-3-6 (Building Permits and Certificates of Occupancy); Development Services staff processes and releases all Certificates of Occupancy
- Development fees are recalculated whenever a structure is occupied by a use inconsistent with the Category of Development originally used to calculate those fees; additional fees owed must be paid upon discovery by City staff of the change in occupancy, but no later than upon an application for a Building Permit or Certificate of Occupancy related to that occupancy, per City Code Section 9-8-9 (Calculation and collection of development fees)
- If a Certificate of Occupancy has already been issued before the discrepancy is found, any additional development fees owed must be paid within 30 days of receipt of a bill for those fees, per City Code Section 9-8-9
- No Certificate of Occupancy may be issued until all applicable development fees have been paid
- Goodyear has adopted the 2018 International Building Code (IBC) and 2018 International Existing Building Code (IEBC) with local amendments (documented elsewhere in this file's codesAdopted list), which govern change-of-occupancy code-compliance review generally; this review did not independently confirm Goodyear-specific amendments to the IBC/IEBC change-of-occupancy provisions beyond what is already documented in this file
- Apply through the City of Goodyear Development Services, Building Safety Division (1900 N. Civic Square), consistent with the application channel (Accela Citizen Access / in-person Development Counter) used for other Building Safety permit types documented in this file
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Occupancy Inspection
Verifies the building or space meets currently adopted code for the new occupancy classification before a Certificate of Occupancy is issued for the changed use
See the full Goodyear inspection guide — scheduling & re-inspection fees →
Tips
- Even without any construction work, a change in a building's or tenant space's use can require Building Safety Division review to confirm the space meets current code for the new occupancy classification before a Certificate of Occupancy can be issued for that use -- verify with Building Safety before signing a lease or opening a business in an existing space that previously had a different use.
- Goodyear's development-fee code (City Code Section 9-8-9) treats a change in occupancy inconsistent with the category originally used to calculate development fees as a trigger for fee recalculation -- additional fees can be owed even when no construction/building permit is otherwise required for the space itself.
- This entry's specific fee amount could not be confirmed during this review -- contact Development Services (623-932-3004 / developmentcounter@goodyearaz.gov) to confirm current Change of Use / Certificate of Occupancy fees before applying.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-08-04.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Goodyear building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Goodyear
Change of Use / Certificate of Occupancy Permit in other cities
Compare change of use / certificate of occupancy permit fees across Arizona →