Commercial Tenant Improvement (TI) Permit in Litchfield Park, Arizona

Required for interior build-out, alteration, or fit-out of existing commercial tenant space in Litchfield Park. This is a genuinely distinct permit category from new commercial shell construction: the City's Citywide Fee Schedule bills tenant improvement work under its own dedicated per-square-foot fee lines (varying by use type), separate from the 'Shell Building' fee used for new core-and-shell construction, and the City's official Building Permit Questions and Answers page publishes a separate, shorter review timeframe for 'Commercial tenant improvement' than for 'New commercial building shells.'

Verified 2026-08-01 · Source

When you need this permit

  • Building permit required for changes, alterations, upgrades, and interior build-out of existing commercial tenant space
  • Billed under the Citywide Fee Schedule's dedicated 'Tenant Improvement' fee category, using Based-on-Valuation per-square-foot rates that vary by use type: Office/Mercantile and Vanilla Shell at $20/sq ft, Restaurant/Medical at $40/sq ft -- a distinct fee methodology from the 80%-of-Valuation-Chart 'Shell Building' fee used for new commercial core-and-shell construction
  • Application submitted on the same City Building Permit Application used for all commercial work, selecting 'Commercial' as the project Type -- the application form itself does not have a separate Tenant Improvement checkbox; the New Build/TI distinction is made at the fee-schedule and review-timeline level only
  • Reviewed against the 2018 IBC (and 2018 IEBC where the scope involves alteration of an existing building) and City of Litchfield Park amendments
  • Commercial trade permits (electrical, plumbing, mechanical) tied to a tenant improvement scope are billed at the same 15%-of-permit-fee rate used for new commercial construction
  • Certificate of Occupancy (Commercial), $200 per building, required before the tenant space may be occupied

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Tenant Improvement -- Office/MercantileCity of Litchfield Park Citywide Fee Schedule, Section 3, Tenant Improvement; verified by direct PDF fetch and page-by-page read 2026-08-01
BOV of $20 per sq. ft.
Tenant Improvement -- Restaurant/MedicalCity of Litchfield Park Citywide Fee Schedule, Section 3, Tenant Improvement
BOV of $40 per sq. ft.
Tenant Improvement -- Vanilla ShellCity of Litchfield Park Citywide Fee Schedule, Section 3, Tenant Improvement; the Fee Schedule does not further define 'Vanilla Shell' beyond this line item -- confirm the exact scope this category covers with Building Safety before budgeting
BOV of $20 per sq. ft.
Plan Review (new submittal)City of Litchfield Park Citywide Fee Schedule, Section 3, Plan Review
65% of calculated permit fee
Electrical / Plumbing / Mechanical -- Commercial (if part of TI scope)City of Litchfield Park Citywide Fee Schedule, Section 3, Electrical/Plumbing/Mechanical
15% of Permit Fee each
Certificate of Occupancy/Completion -- Commercial, per buildingCity of Litchfield Park Citywide Fee Schedule, Section 3, Certificate of Occupancy/Completion
$200
Expedited ReviewCity of Litchfield Park Citywide Fee Schedule, Section 3, Plan Review
Double plan review fee

Review timeline

Plan reviewLitchfield Park’s published plan-review target
5–10 business days

How long did your Commercial Tenant Improvement (TI) Permit permit actually take in Litchfield Park?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In (MEP)

    Electrical/mechanical/plumbing rough-in verified before walls/ceiling closed

  2. 2

    Final / Certificate of Occupancy

    Completed tenant build-out verified against approved plans; Certificate of Occupancy issued ($200 fee per building)

See the full Litchfield Park inspection guide — scheduling & re-inspection fees →

Tips

  • Per the City's official Building Permit Questions and Answers page, 'Commercial tenant improvement' carries a published review timeframe of 5-10 business days -- notably faster than 'New commercial building shells' (15-20 business days) on the same page.
  • Fee basis differs meaningfully by use type: Restaurant/Medical tenant improvements are billed at double the per-square-foot rate ($40/sq ft) of Office/Mercantile or Vanilla Shell space ($20/sq ft each) -- confirm the correct use-type category with Building Safety before budgeting.
  • The City's Building Permit Application form does not have a distinct 'Tenant Improvement' checkbox (only a single 'Commercial' checkbox) -- the TI/new-construction distinction exists only in the Citywide Fee Schedule's separate fee lines and the published review-timeframe table, not on the application form itself.

Frequently asked questions

Litchfield Park requires a commercial tenant improvement (ti) permit for: Building permit required for changes, alterations, upgrades, and interior build-out of existing commercial tenant space; Billed under the Citywide Fee Schedule's dedicated 'Tenant Improvement' fee category, using Based-on-Valuation per-square-foot rates that vary by use type: Office/Mercantile and Vanilla Shell at $20/sq ft, Restaurant/Medical at $40/sq ft -- a distinct fee methodology from the 80%-of-Valuation-Chart 'Shell Building' fee used for new commercial core-and-shell construction; Application submitted on the same City Building Permit Application used for all commercial work, selecting 'Commercial' as the project Type -- the application form itself does not have a separate Tenant Improvement checkbox; the New Build/TI distinction is made at the fee-schedule and review-timeline level only; Reviewed against the 2018 IBC (and 2018 IEBC where the scope involves alteration of an existing building) and City of Litchfield Park amendments; Commercial trade permits (electrical, plumbing, mechanical) tied to a tenant improvement scope are billed at the same 15%-of-permit-fee rate used for new commercial construction; Certificate of Occupancy (Commercial), $200 per building, required before the tenant space may be occupied. If your project isn't listed, confirm with City of Litchfield Park Building Safety Department at 623-935-1066 before starting work.

Based on Valuation, at $20 per square foot for Office/Mercantile or Vanilla Shell space, or $40 per square foot for Restaurant/Medical space, per the City of Litchfield Park Citywide Fee Schedule, Section 3 (Tenant Improvement), plus a 65%-of-permit-fee plan review charge.

Litchfield Park's published plan-review target for a commercial tenant improvement (ti) permit is 5–10 business days.

You'll need: Building Permit Application; Construction Documents / Floor Plan. Depending on your project, Litchfield Park may also ask for: Site/Plot Plan. See the required-documents checklist on this page for details on each.

Litchfield Park requires 2 inspection(s) for a commercial tenant improvement (ti) permit, in order: Rough-In (MEP), Final / Certificate of Occupancy. Schedule each through City of Litchfield Park Building Safety Department (623-935-1066).

Apply through City of Litchfield Park Building Safety Department at 214 W. Wigwam Boulevard, Litchfield Park, AZ 85340. Phone: 623-935-1066, email: building@litchfieldpark.gov. Office hours: Monday - Friday, 7:00 a.m. to 4:00 p.m. Fax: 623-935-5427. Chief Building Official: Brian Bertucci (623-889-6222, bbertucci@litchfieldpark.gov). Building Safety & Public Works Administrative Assistant: Stacey Frederico (sfrederico@litchfieldpark.gov). Applications submitted at City Hall or online via the City's building permit application system; inspections can also be scheduled by emailing Building Safety.. Official information: https://www.litchfieldpark.gov/57/Building-Safety.

Litchfield Park, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Litchfield Park runs its own Building Safety Department, independently adopts and administers its own construction codes, and does not defer permitting to Maricopa County. Source: City of Litchfield Park Building Safety page (litchfieldpark.gov/57/Building-Safety).; 2018 International Building Code (IBC), as adopted by the Mayor and Council of the City of Litchfield Park, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes (effective January 1, 2020) and the City's Building Safety page, which lists this as a 'Current Adopted Code' (verified live as of July 2026, with no newer edition adoption found on the City's site, municipal code, or in web searches for 2021/2024 code-cycle updates).; 2018 International Residential Code (IRC), adopted by reference, with City of Litchfield Park amendments (including an amended Table R301.2(1) Climatic and Geographic Design Criteria and amended Table R301.5 Live Loads), effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2018 International Mechanical Code (IMC), adopted by reference, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes; City of Litchfield Park Building Safety page.; 2018 International Plumbing Code (IPC), adopted by reference, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes; City of Litchfield Park Building Safety page.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association (NFPA 70), adopted by reference (Section 101.4.9 of the amended IBC, applying to all buildings except one- and two-family dwellings which fall under the IRC electrical provisions), with City amendments. Note: the electrical code cycle is one edition behind the 2018 ICC set, consistent with typical AZ practice. Source: City of Litchfield Park Amendments to 2018 International Codes; City of Litchfield Park Building Safety page.; 2018 International Fuel Gas Code (IFGC), adopted by reference, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2018 International Existing Building Code (IEBC), adopted by reference, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2018 International Energy Conservation Code (IECC), adopted by reference, with City amendments, effective January 1, 2020. Energy codes have applied to new construction since 2009 per the City's Residential Energy Improvements guideline brochure (Brochure #8, July 2017), requiring energy-efficient windows/doors, higher insulation levels, and energy-efficient A/C for homes built after that date. Source: City of Litchfield Park Amendments to 2018 International Codes; 'Guidelines When Building Within the City' Brochure #8 — Residential Energy Improvements.; 2018 International Property Maintenance Code (IPMC), adopted by reference. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2018 International Fire Code (IFC), adopted by reference as the City's uniform fire code, with City amendments; adopted appendices are limited to Appendix B (Fire Flow Requirements), Appendix D (Fire Apparatus Access Roads), and Appendix H (Hazardous Materials Management Plan/Hazardous Materials Inventory Statement Instructions) — all other IFC appendices are NOT adopted unless specifically referenced. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2010 ADA Standards for Accessible Design, together with ICC A117.1 Accessibility code, the Arizonans with Disabilities Act (A.R.S. Title 41, Chapter 9, Article 8), and its Implementing Rules (A.A.C. Title 10, Chapter 3, Article 4); in the event of a conflict between codes, the more restrictive standard applies. Source: City of Litchfield Park Amendments to 2018 International Codes (IBC Section 101.4.8 amendment); City of Litchfield Park Building Safety page.; Permit expiration/abandonment rule (amended Section 106.4.3 of the Building Code and Section 105.3.1 of the Fire Code): an application for a permit for any proposed work is deemed abandoned 180 days after the date of filing unless pursued in good faith or a permit has been issued; the Building Official may grant one extension of up to 180 days upon written request showing justifiable cause, provided no changes have been made to the original construction documents and the suspension/abandonment has not exceeded one year. Source: City of Litchfield Park Amendments to 2018 International Codes.. Local amendments apply — see the Litchfield Park overview page for the full list.

Functionally yes, though not as a separate application form. Tenant improvement work is billed under its own dedicated per-square-foot fee lines in the Citywide Fee Schedule (Office/Mercantile and Vanilla Shell at $20/sq ft, Restaurant/Medical at $40/sq ft) -- distinct from the 80%-of-Valuation-Chart fee for new shell construction -- and the City's Building Permit Questions and Answers page publishes its own, faster review timeframe (5-10 business days) for tenant improvement versus new commercial shells (15-20 business days).

Sources & verification

Verified against official sources. Last reviewed 2026-08-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Litchfield Park building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Litchfield Park.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.