EV Charger / Electric Vehicle Charging Station Permit in Litchfield Park, Arizona

The City of Litchfield Park's Building Safety fee schedule has no dedicated EV-charger, EVSE, or electric-vehicle-charging line item -- unlike Photovoltaic Systems, which get their own fee table. Installing a Level 2 (240V) home EV charger requires a City of Litchfield Park Electrical Permit reviewed against the adopted 2017 NEC. If the installation requires a panel repair, replacement, or upsizing, it is billed under the schedule's 'Electrical -- Repair/Replace/Add Panel' fee tiers; a simple new circuit added to an existing panel with no other listed electrical work would fall under the schedule's residual 'All Other Projects Not Listed Above' (Based on Valuation) category -- Building Safety should be asked to confirm which line applies to a specific installation.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical work reviewed against the City's adopted 2017 National Electrical Code (NEC)
  • If the EV charger installation involves a panel repair, replacement, or amperage upgrade, it is billed under the schedule's amperage-tiered 'Repair/Replace/Add Panel' fee lines
  • If the installation requires temporary power during construction, the Temporary Power fee line applies separately
  • A simple new dedicated circuit added to an existing panel, with no panel work, is not explicitly itemized on the fee schedule and would likely fall under 'All Other Projects Not Listed Above' (Based on Valuation) -- confirm the applicable line with Building Safety before applying
  • Simple electrical permits such as panel work may be issued over the counter per the City's Building Permit Q&A page

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Repair/Replace/Add Panel, 400 amps or less (if the EV charger install requires panel work)City of Litchfield Park Citywide Fee Schedule FY2026 (effective 8/1/2025), Section 3, Building Safety, Electrical, re-confirmed live 2026-07-20 by direct PDF fetch and full-text extraction -- no distinct 'EV charger'/'EVSE' line item exists; this is the panel-work fee an EV charger install would fall under if it also touches the panel
$100
Repair/Replace/Add Panel, 401-999 ampsCity of Litchfield Park Citywide Fee Schedule FY2026, Section 3
$150
Temporary Power (if needed during installation)City of Litchfield Park Citywide Fee Schedule FY2026, Section 3
$100
All Other Projects Not Listed Above (if the install is a standalone new circuit with no panel work)City of Litchfield Park Citywide Fee Schedule FY2026, Section 3 -- residual valuation-based category for electrical work not otherwise itemized on the fee schedule; confirm classification with Building Safety before applying
BOV (Based on Valuation)

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / Electric Vehicle Charging Station Permit permit actually take in Litchfield Park?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Inspection

    New circuit, breaker sizing, and disconnect (if required by the charger manufacturer) verified by City of Litchfield Park Building Safety before energizing

See the full Litchfield Park inspection guide — scheduling & re-inspection fees →

Tips

  • There is no dedicated 'EV charger' or 'EVSE' line item on Litchfield Park's Citywide Fee Schedule -- unlike Photovoltaic Systems, which have their own fee table, an EV charger circuit falls under the general Electrical fee categories or the residual 'All Other Projects Not Listed Above' line.
  • If your installation also involves panel repair, replacement, or an amperage upgrade, expect the tiered panel fee ($100-$250 depending on amperage); a standalone new circuit with no panel work is likely billed under the valuation-based residual category instead.
  • Simple electrical permits such as panel work can often be issued over the counter -- ask Building Safety whether your EV charger installation qualifies for over-the-counter issuance.
  • Confirm the correct fee line with City of Litchfield Park Building Safety before applying, since the published schedule does not explicitly classify a standalone EV charger circuit.

Frequently asked questions

Litchfield Park requires an ev charger / electric vehicle charging station permit for: Electrical work reviewed against the City's adopted 2017 National Electrical Code (NEC); If the EV charger installation involves a panel repair, replacement, or amperage upgrade, it is billed under the schedule's amperage-tiered 'Repair/Replace/Add Panel' fee lines; If the installation requires temporary power during construction, the Temporary Power fee line applies separately; A simple new dedicated circuit added to an existing panel, with no panel work, is not explicitly itemized on the fee schedule and would likely fall under 'All Other Projects Not Listed Above' (Based on Valuation) -- confirm the applicable line with Building Safety before applying; Simple electrical permits such as panel work may be issued over the counter per the City's Building Permit Q&A page. If your project isn't listed, confirm with City of Litchfield Park Building Safety Department at 623-935-1066 before starting work.

If the install requires panel work, $100 (400 amps or less) to $250 (over 1,000 amps) per the Repair/Replace/Add Panel fee tiers. If it's a standalone new circuit with no panel work, the fee is Based on Valuation under the schedule's residual category -- confirm with Building Safety before applying.

Litchfield Park does not publish a plan-review timeline for this permit. Contact City of Litchfield Park Building Safety Department at 623-935-1066 for current turnaround.

You'll need: City of Litchfield Park Electrical Permit application. See the required-documents checklist on this page for details on each.

Litchfield Park requires 1 inspection(s) for an ev charger / electric vehicle charging station permit, in order: Electrical Inspection. Schedule each through City of Litchfield Park Building Safety Department (623-935-1066).

Apply through City of Litchfield Park Building Safety Department at 214 W. Wigwam Boulevard, Litchfield Park, AZ 85340. Phone: 623-935-1066, email: building@litchfieldpark.gov. Office hours: Monday - Friday, 7:00 a.m. to 4:00 p.m. Fax: 623-935-5427. Chief Building Official: Brian Bertucci (623-889-6222, bbertucci@litchfieldpark.gov). Building Safety & Public Works Administrative Assistant: Stacey Frederico (sfrederico@litchfieldpark.gov). Applications submitted at City Hall or online via the City's building permit application system; inspections can also be scheduled by emailing Building Safety.. Official information: https://www.litchfieldpark.gov/57/Building-Safety.

Litchfield Park, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Litchfield Park runs its own Building Safety Department, independently adopts and administers its own construction codes, and does not defer permitting to Maricopa County. Source: City of Litchfield Park Building Safety page (litchfieldpark.gov/57/Building-Safety).; 2018 International Building Code (IBC), as adopted by the Mayor and Council of the City of Litchfield Park, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes (effective January 1, 2020) and the City's Building Safety page, which lists this as a 'Current Adopted Code' (verified live as of July 2026, with no newer edition adoption found on the City's site, municipal code, or in web searches for 2021/2024 code-cycle updates).; 2018 International Residential Code (IRC), adopted by reference, with City of Litchfield Park amendments (including an amended Table R301.2(1) Climatic and Geographic Design Criteria and amended Table R301.5 Live Loads), effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2018 International Mechanical Code (IMC), adopted by reference, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes; City of Litchfield Park Building Safety page.; 2018 International Plumbing Code (IPC), adopted by reference, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes; City of Litchfield Park Building Safety page.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association (NFPA 70), adopted by reference (Section 101.4.9 of the amended IBC, applying to all buildings except one- and two-family dwellings which fall under the IRC electrical provisions), with City amendments. Note: the electrical code cycle is one edition behind the 2018 ICC set, consistent with typical AZ practice. Source: City of Litchfield Park Amendments to 2018 International Codes; City of Litchfield Park Building Safety page.; 2018 International Fuel Gas Code (IFGC), adopted by reference, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2018 International Existing Building Code (IEBC), adopted by reference, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2018 International Energy Conservation Code (IECC), adopted by reference, with City amendments, effective January 1, 2020. Energy codes have applied to new construction since 2009 per the City's Residential Energy Improvements guideline brochure (Brochure #8, July 2017), requiring energy-efficient windows/doors, higher insulation levels, and energy-efficient A/C for homes built after that date. Source: City of Litchfield Park Amendments to 2018 International Codes; 'Guidelines When Building Within the City' Brochure #8 — Residential Energy Improvements.; 2018 International Property Maintenance Code (IPMC), adopted by reference. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2018 International Fire Code (IFC), adopted by reference as the City's uniform fire code, with City amendments; adopted appendices are limited to Appendix B (Fire Flow Requirements), Appendix D (Fire Apparatus Access Roads), and Appendix H (Hazardous Materials Management Plan/Hazardous Materials Inventory Statement Instructions) — all other IFC appendices are NOT adopted unless specifically referenced. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2010 ADA Standards for Accessible Design, together with ICC A117.1 Accessibility code, the Arizonans with Disabilities Act (A.R.S. Title 41, Chapter 9, Article 8), and its Implementing Rules (A.A.C. Title 10, Chapter 3, Article 4); in the event of a conflict between codes, the more restrictive standard applies. Source: City of Litchfield Park Amendments to 2018 International Codes (IBC Section 101.4.8 amendment); City of Litchfield Park Building Safety page.; Permit expiration/abandonment rule (amended Section 106.4.3 of the Building Code and Section 105.3.1 of the Fire Code): an application for a permit for any proposed work is deemed abandoned 180 days after the date of filing unless pursued in good faith or a permit has been issued; the Building Official may grant one extension of up to 180 days upon written request showing justifiable cause, provided no changes have been made to the original construction documents and the suspension/abandonment has not exceeded one year. Source: City of Litchfield Park Amendments to 2018 International Codes.. Local amendments apply — see the Litchfield Park overview page for the full list.

No. The City of Litchfield Park's Citywide Fee Schedule has no dedicated EV-charger or EVSE permit type or fee line. A home Level 2 charger is permitted as an Electrical Permit reviewed under the 2017 NEC, billed under the schedule's general panel-work fees if panel work is involved, or under the residual 'All Other Projects Not Listed Above' valuation-based category otherwise.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Litchfield Park building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.