Required for heating, ventilation, and air conditioning installation or replacement in Litchfield Park, governed by the 2018 International Mechanical Code (IMC) as adopted and amended by the City. Current codes require a minimum SEER rating of 18 for new units.

Verified 2026-07-06 · Source

When you need this permit

  • Mechanical permit required for installation, replacement, or relocation of HVAC equipment and ductwork
  • Governed by the 2018 IMC as adopted by the City of Litchfield Park
  • Current building codes require a minimum SEER rating of 18 for new HVAC units
  • New codes require all ductwork to be insulated; a duct test can reveal leaks in existing systems
  • Simple HVAC replacement permits can typically be issued over the counter

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

HVAC — Residential new unit/ReplacementCity of Litchfield Park Citywide Fee Schedule FY2026, Section 3, Building Safety
$150
HVAC — With new/additional ductwork (add to above fee)City of Litchfield Park Citywide Fee Schedule FY2026, Section 3
$35
HVAC — Commercial unit replacement (each)City of Litchfield Park Citywide Fee Schedule FY2026, Section 3
$150
HVAC — Hotel Repair/Replacement, per unitCity of Litchfield Park Citywide Fee Schedule FY2026, Section 3
$75
Mechanical — Residential New ConstructionCity of Litchfield Park Citywide Fee Schedule FY2026, Section 3
$50
Mechanical — Commercial New ConstructionCity of Litchfield Park Citywide Fee Schedule FY2026, Section 3
15% of Permit fee
Mechanical — Repair/ReplacementCity of Litchfield Park Citywide Fee Schedule FY2026, Section 3
$35

Review timeline

Plan reviewLitchfield Park’s published plan-review target
2–10 business days

How long did your Mechanical / HVAC Permit permit actually take in Litchfield Park?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Ductwork and equipment placement before walls closed

  2. 2

    Final

    Equipment operational, clearances and combustion air verified; residential inspection fee $50

See the full Litchfield Park inspection guide — scheduling & re-inspection fees →

Tips

  • Per the City's official Building Permit Questions and Answers page, residential mechanical/HVAC improvements have a published review timeframe of 2-10 business days.
  • If an existing HVAC unit is more than 5 years old, replacing it with a current SEER-18-minimum unit can increase efficiency by over 25%, per the City's Residential Energy Improvements guideline (an efficiency note, not a permit requirement).

Frequently asked questions

Litchfield Park requires a mechanical / hvac permit for: Mechanical permit required for installation, replacement, or relocation of HVAC equipment and ductwork; Governed by the 2018 IMC as adopted by the City of Litchfield Park; Current building codes require a minimum SEER rating of 18 for new HVAC units; New codes require all ductwork to be insulated; a duct test can reveal leaks in existing systems; Simple HVAC replacement permits can typically be issued over the counter. If your project isn't listed, confirm with City of Litchfield Park Building Safety Department at 623-935-1066 before starting work.

$150 for a residential new unit or replacement, per the City of Litchfield Park Citywide Fee Schedule (Section 3, Building Safety), plus $35 if new or additional ductwork is included.

Litchfield Park's published plan-review target for a mechanical / hvac permit is 2–10 business days.

You'll need: Building/Mechanical Permit Application. See the required-documents checklist on this page for details on each.

Litchfield Park requires 2 inspection(s) for a mechanical / hvac permit, in order: Rough-In, Final. Schedule each through City of Litchfield Park Building Safety Department (623-935-1066).

Apply through City of Litchfield Park Building Safety Department at 214 W. Wigwam Boulevard, Litchfield Park, AZ 85340. Phone: 623-935-1066, email: building@litchfieldpark.gov. Office hours: Monday - Friday, 7:00 a.m. to 4:00 p.m. Fax: 623-935-5427. Chief Building Official: Brian Bertucci (623-889-6222, bbertucci@litchfieldpark.gov). Building Safety & Public Works Administrative Assistant: Stacey Frederico (sfrederico@litchfieldpark.gov). Applications submitted at City Hall or online via the City's building permit application system; inspections can also be scheduled by emailing Building Safety.. Official information: https://www.litchfieldpark.gov/57/Building-Safety.

Litchfield Park, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Litchfield Park runs its own Building Safety Department, independently adopts and administers its own construction codes, and does not defer permitting to Maricopa County. Source: City of Litchfield Park Building Safety page (litchfieldpark.gov/57/Building-Safety).; 2018 International Building Code (IBC), as adopted by the Mayor and Council of the City of Litchfield Park, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes (effective January 1, 2020) and the City's Building Safety page, which lists this as a 'Current Adopted Code' (verified live as of July 2026, with no newer edition adoption found on the City's site, municipal code, or in web searches for 2021/2024 code-cycle updates).; 2018 International Residential Code (IRC), adopted by reference, with City of Litchfield Park amendments (including an amended Table R301.2(1) Climatic and Geographic Design Criteria and amended Table R301.5 Live Loads), effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2018 International Mechanical Code (IMC), adopted by reference, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes; City of Litchfield Park Building Safety page.; 2018 International Plumbing Code (IPC), adopted by reference, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes; City of Litchfield Park Building Safety page.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association (NFPA 70), adopted by reference (Section 101.4.9 of the amended IBC, applying to all buildings except one- and two-family dwellings which fall under the IRC electrical provisions), with City amendments. Note: the electrical code cycle is one edition behind the 2018 ICC set, consistent with typical AZ practice. Source: City of Litchfield Park Amendments to 2018 International Codes; City of Litchfield Park Building Safety page.; 2018 International Fuel Gas Code (IFGC), adopted by reference, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2018 International Existing Building Code (IEBC), adopted by reference, with City amendments, effective January 1, 2020. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2018 International Energy Conservation Code (IECC), adopted by reference, with City amendments, effective January 1, 2020. Energy codes have applied to new construction since 2009 per the City's Residential Energy Improvements guideline brochure (Brochure #8, July 2017), requiring energy-efficient windows/doors, higher insulation levels, and energy-efficient A/C for homes built after that date. Source: City of Litchfield Park Amendments to 2018 International Codes; 'Guidelines When Building Within the City' Brochure #8 — Residential Energy Improvements.; 2018 International Property Maintenance Code (IPMC), adopted by reference. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2018 International Fire Code (IFC), adopted by reference as the City's uniform fire code, with City amendments; adopted appendices are limited to Appendix B (Fire Flow Requirements), Appendix D (Fire Apparatus Access Roads), and Appendix H (Hazardous Materials Management Plan/Hazardous Materials Inventory Statement Instructions) — all other IFC appendices are NOT adopted unless specifically referenced. Source: City of Litchfield Park Amendments to 2018 International Codes.; 2010 ADA Standards for Accessible Design, together with ICC A117.1 Accessibility code, the Arizonans with Disabilities Act (A.R.S. Title 41, Chapter 9, Article 8), and its Implementing Rules (A.A.C. Title 10, Chapter 3, Article 4); in the event of a conflict between codes, the more restrictive standard applies. Source: City of Litchfield Park Amendments to 2018 International Codes (IBC Section 101.4.8 amendment); City of Litchfield Park Building Safety page.; Permit expiration/abandonment rule (amended Section 106.4.3 of the Building Code and Section 105.3.1 of the Fire Code): an application for a permit for any proposed work is deemed abandoned 180 days after the date of filing unless pursued in good faith or a permit has been issued; the Building Official may grant one extension of up to 180 days upon written request showing justifiable cause, provided no changes have been made to the original construction documents and the suspension/abandonment has not exceeded one year. Source: City of Litchfield Park Amendments to 2018 International Codes.. Local amendments apply — see the Litchfield Park overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Litchfield Park building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.