Residential Building Permit (New Construction) — Litchfield Park, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://www.litchfieldpark.gov/487/Building-Permit-Questions-and-Answers
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction) in Litchfield Park, Arizona
Required for new single-family dwelling construction in the City of Litchfield Park. Reviewed against the 2018 IRC and City of Litchfield Park amendments (effective January 1, 2020). Applications are submitted at the Building Safety office, 214 W. Wigwam Blvd., using the City's Building Permit Application.
Verified 2026-07-06 · Source
When you need this permit
- Building permit required for new single-family dwelling construction within Litchfield Park city limits
- Plans must comply with the 2018 IRC and City amendments, including the amended Climatic and Geographic Design Criteria (90 mph wind, Exposure B; Seismic Design Category B; 34°F winter design temperature; moderate-to-heavy termite potential; 12-inch frost depth)
- City Code requires each residence to provide covered parking for two vehicles
- Construction documents must be submitted per the City's Residential Drawing Submittal Package requirements
- Application submitted in person at the Building Safety office (214 W. Wigwam Blvd.) using the Building Permit Application form, selecting 'Residential' as the project type
- Building permit fee is Based on Valuation (BOV), using the current Building Valuation Data jointly published by Building Safety Journal and the International Code Council
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Before concrete pour
- 2
Framing
Structural framing, connections, egress, per 2018 IRC and City design criteria
- 3
Final / Certificate of Occupancy
All work complete per approved plans; Certificate of Occupancy issued per building ($100 fee)
See the full Litchfield Park inspection guide — scheduling & re-inspection fees →
Tips
- Per the City's official Building Permit Questions and Answers page, new residential buildings have a published review timeframe of 5-10 business days.
- The Citywide Fee Schedule (effective August 1, 2025) is the sole fee authority for Building Safety — the ICC codes' own fee sections (e.g., IBC 108.4) are explicitly deleted and superseded by City Council-set fees.
- Homeowners can act as their own contractor, but if the value of work performed by a hired party exceeds $1,000, an Arizona contractor's license (ROC) is required. Contractor
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Litchfield Park building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Litchfield Park
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Arizona →
Look up this fee in a different city →