Litchfield Park building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Litchfield Park, Arizona.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 214 W. Wigwam Boulevard, Litchfield Park, AZ 85340
- Phone
- 623-935-1066
- Office hours
- Monday - Friday, 7:00 a.m. to 4:00 p.m. Fax: 623-935-5427. Chief Building Official: Brian Bertucci (623-889-6222, bbertucci@litchfieldpark.gov). Building Safety & Public Works Administrative Assistant: Stacey Frederico (sfrederico@litchfieldpark.gov). Applications submitted at City Hall or online via the City's building permit application system; inspections can also be scheduled by emailing Building Safety.
- Website
- Official site
Inspection sequence
Applies to: Plumbing Permit
- 1
Underground/Slab
Before concrete pour — verify pipe slope, materials, cleanouts
- 2
Rough-In
After pipes installed, before walls closed
- 3
Final
Fixtures connected, water heater and gas connections verified, no leaks; residential inspection fee $50
Applies to: Residential Addition / Remodel Permit
- 1
Foundation/Footing
Required before concrete pour for additions
- 2
Framing
Structural connections to existing structure; fire separation for garage conversions
- 3
Final
Completed work verified against approved plans
Applies to: Residential Building Permit (New Construction)
- 1
Foundation/Footing
Before concrete pour
- 2
Framing
Structural framing, connections, egress, per 2018 IRC and City design criteria
- 3
Final / Certificate of Occupancy
All work complete per approved plans; Certificate of Occupancy issued per building ($100 fee)
Applies to: Swimming Pool / Spa Permit
- 1
Pre-Gunite
Before shotcrete/gunite application on in-ground pool shell
- 2
Pre-Plaster
Before interior plaster finish application
- 3
Final / Barrier Compliance
Barrier height, gate self-closing/self-latching hardware, and anti-entrapment suction covers verified; above-ground pools/manufactured spas require only this single inspection
Applies to: Electrical Permit
- 1
Rough-In
Wiring, box placement, and panel connections before walls are closed (commercial/new construction)
- 2
Final / Meter Clearance
Devices installed and panel verified per 2017 NEC; residential inspection fee is $50, commercial is 15% of permit fee each
Applies to: Fencing Permit
- 1
Footing
Required for masonry/retaining wall footings before backfill
- 2
Final
Completed fence/wall verified against approved plans
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and equipment placement before walls closed
- 2
Final
Equipment operational, clearances and combustion air verified; residential inspection fee $50
Applies to: Patio Cover / Ramada / Gazebo Permit
- 1
Footing
Required for post footings before concrete pour
- 2
Final
Structure completed per approved plans
Applies to: Residential Solar Photovoltaic (PV) / Solar Water Heater Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final
Panel mounting, racking attachment, roof penetration sealing, and electrical interconnection verified
Final inspection only: Demolition Permit, EV Charger / Electric Vehicle Charging Station Permit, Re-Roofing Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Litchfield Park building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Litchfield Park building permits
Get alerts for Litchfield Park
We'll email you when Litchfield Park's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.