Certificate of Occupancy / Change of Use — Colorado City, Arizona · Requirements sheet
Reviewed 2026-07-23 · Source: https://www.tocc.us/building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Certificate of Occupancy / Change of Use in Colorado City, Arizona
Colorado City has no separately named 'change of use permit' or 'certificate of occupancy permit' product, application, checklist, or fee distinct from its general Building Permit (CITY INSPECT) process. However, the Town has genuinely adopted a Certificate of Occupancy requirement: the 2006 International Building Code as adopted by the Town (Town Code § 150.01) includes IBC § 110 (Certificate of Occupancy), and the Town specifically amended IBC § 110.1 (Use and Occupancy) to add 'Exception: R-3 and U Occupancies' (Town Code § 150.01(C)) -- meaning the Town's own ordinance text confirms that occupancy classifications OTHER than R-3 (residential) and U (utility/miscellaneous) require the Building Official to issue a Certificate of Occupancy before use, occupancy, or a change in occupancy classification. Where a proposed change of use involves no construction, the Town's general Land Use Application offers a 'Land Use Verification/Other' category (paired with a published $50 Zoning Verification Letter Fee) that appears to be the applicable zoning-compliance route.
Reviewed 2026-07-23 · Source
When you need this permit
- Under the 2006 IBC as adopted by the Town (Town Code § 150.01), a building or structure may not be used or occupied, and its occupancy classification may not be changed, until the Building Official issues a Certificate of Occupancy (IBC § 110, § 110.1 Use and Occupancy)
- The Town's own amendment to IBC § 110.1 adds 'Exception: R-3 and U Occupancies' (Town Code § 150.01(C)) -- confirming that R-3 (residential) and U (utility/miscellaneous) occupancies are exempt from the Certificate of Occupancy requirement, while all other occupancy classifications (commercial, business, mercantile, assembly, educational, institutional, storage, factory/industrial, etc.) require one
- No standalone 'Change of Use Permit' or 'Certificate of Occupancy Permit' application, checklist, or fee distinct from the general CITY INSPECT Building Permit process was found published by the Town as of this review
- Where a proposed change of use involves construction or alteration, it is processed as a Building Permit through the CITY INSPECT portal, culminating in the Building Official's Certificate of Occupancy determination
- Where no construction is involved, the Town's general Land Use Application (tocc.us/applications) includes a 'Land Use Verification/Other' category with 'Existing Use' and 'Proposed Use' fields -- paired with a published $50.00 Zoning Verification Letter Fee (Resolution 2026-08 Exhibit A) -- which appears to be the applicable route for confirming zoning compliance of a use change without a building permit
- Any new business operating in Colorado City must separately obtain an annual Town business license regardless of whether the space's occupancy classification is changing (Town Code § 110.02; flat $28.00/year fee under § 110.05), administered by the Town Clerk rather than the Building Department or Zoning Administrator
Required documents
Check off what you have — your progress is saved on this device.
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection (Certificate of Occupancy)
Required before the Building Official may issue a Certificate of Occupancy for any occupancy classification other than R-3/U, confirming compliance with approved plans and applicable code (IBC § 110, Town Code § 150.01(C))
See the full Colorado City inspection guide — scheduling & re-inspection fees →
Tips
- The Town's own IBC amendment (Town Code § 150.01(C), adding 'Exception: R-3 and U Occupancies' to IBC § 110.1) is the clearest direct evidence that Colorado City DOES require Certificates of Occupancy for non-residential/non-utility uses -- despite having no separately named 'change of use' or 'CO' permit product, checklist, or fee.
- If a change of use involves no physical construction, the more likely applicable Town process is the general Land Use Application's 'Land Use Verification/Other' category ($50 Zoning Verification Letter Fee) rather than a Building Permit -- confirm directly with Community Development, since no dedicated 'change of use' checklist was found.
- Don't conflate the Town's business license requirement ($28/year flat fee, Town Clerk's office, Town Code Chapter 110) with a zoning/building change-of-use requirement -- they are administered by different offices and are not substitutes for each other.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Colorado City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Colorado City
Certificate of Occupancy / Change of Use in other cities
Compare certificate of occupancy / change of use fees across Arizona →
Look up this fee in a different city →