EV Charger / EVSE Permit in South Tucson, Arizona

No dedicated electric-vehicle-charging-station permit, application, or fee line is published by the City of South Tucson. An EV charger installation is permitted as an Electrical Permit under the City's existing general process (2017 NEC as adopted and amended under Ordinance No. 25-01) — the same valuation-based mechanism as the City's Electrical Permit and Solar PV Permit. If the installation also involves structural/mounting work, a separate Building Permit (2018 IBC/IRC as adopted) would apply. Neither the City's Development Services/Permits pages, Ordinance No. 25-01, nor the City's Online Permit and Code Complaint Portal (effective 3/2/2026) publishes an EV-specific fee line. Cost is valuation-dependent and quoted at application time by Development Services (520-792-2424).

Reviewed 2026-07-20 · Source

When you need this permit

  • Electrical Permit required for the EV charging circuit, governed by the 2017 NEC as adopted and amended under Ordinance No. 25-01 — same process as the City's standard Electrical Permit
  • Building Permit additionally required only if structural/mounting work is involved beyond the electrical circuit itself
  • Apply via the City's Online Permit Portal, in person, or by mail to City Hall
  • No dedicated EV/EVSE application form, checklist, or valuation-fee table is published by the City

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Electrical permit fee (no EV/EVSE-specific line exists)City Code Ch. 4, Art. II, Div. 3, Section 4-57. A dedicated EV charger branch circuit is billed under the standard electrical unit-fee schedule; residential appliances are $5.50 each and power apparatus is $5.50 to $89.10 by rating.
$28.60 permit fee, plus Section 4-57 unit fees, plus a plan review fee of 25 percent of the total electrical permit fee

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in South Tucson?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Wiring, box placement, and panel connections before walls are closed

  2. 2

    Final

    Charging equipment installed and circuit verified per 2017 NEC

See the full South Tucson inspection guide — scheduling & re-inspection fees →

Tips

  • South Tucson has no dedicated EV charger permit — apply for a standard Electrical Permit under the same process documented for general electrical work and solar PV connections in this City.
  • Neither the City's website, Ordinance No. 25-01, nor the City's online permit portal publishes an EV-specific fee line; confirm the current cost directly with Development Services before applying.
  • Inspections in South Tucson are conducted only Mondays and Wednesdays, 7:00-9:00 a.m., with requests due the business day before — budget for this limited inspection window.

Frequently asked questions

South Tucson requires an ev charger / evse permit for: Electrical Permit required for the EV charging circuit, governed by the 2017 NEC as adopted and amended under Ordinance No. 25-01 — same process as the City's standard Electrical Permit; Building Permit additionally required only if structural/mounting work is involved beyond the electrical circuit itself; Apply via the City's Online Permit Portal, in person, or by mail to City Hall; No dedicated EV/EVSE application form, checklist, or valuation-fee table is published by the City. If your project isn't listed, confirm with City of South Tucson Planning, Zoning and Development Services Department (Development Services Division) at 520-792-2424 before starting work.

In South Tucson, the published Electrical permit fee (no EV/EVSE-specific line exists) is: $28.60 permit fee, plus Section 4-57 unit fees, plus a plan review fee of 25 percent of the total electrical permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

South Tucson does not publish a plan-review timeline for this permit. Contact City of South Tucson Planning, Zoning and Development Services Department (Development Services Division) at 520-792-2424 for current turnaround.

You'll need: City of South Tucson Permit Application (Online Permit Portal). See the required-documents checklist on this page for details on each.

South Tucson requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In, Final. Schedule each through City of South Tucson Planning, Zoning and Development Services Department (Development Services Division) (520-792-2424).

Apply through City of South Tucson Planning, Zoning and Development Services Department (Development Services Division) at South Tucson City Hall, 1601 S. 6th Ave., South Tucson, AZ 85713. Phone: 520-792-2424, email: submittals@southtucsonaz.gov. Office hours: Monday - Friday, 8:00 a.m. - 5:00 p.m. Permit applications are submitted through the City's Online Permit Portal (live effective March 2, 2026), in person, or by mail/shipment to City Hall; applications require 2 digital copies of a site plan and a floor plan. Inspections are conducted Mondays and Wednesdays, 7:00-9:00 a.m., with requests submitted the business day before.. Official information: https://www.southtucsonaz.gov/devservices/page/permits.

South Tucson, Arizona has adopted: South Tucson is a separately incorporated city (population roughly 5,000, land area approximately 1 square mile) that is entirely surrounded by, but administratively and legally independent of, the City of Tucson -- it is sometimes called 'The Pueblo within a City.' South Tucson runs its own Planning, Zoning and Development Services Department, which independently reviews building plans and issues its own building, electrical, plumbing, mechanical/HVAC, sign, demolition, and remodel permits; it does NOT contract building-permit administration to the City of Tucson or to Pima County. Source: City of South Tucson Development Services and Permits page (southtucsonaz.gov/devservices) and City of South Tucson Permits page (southtucsonaz.gov/devservices/page/permits), both confirming an independent Development Services Division that 'reviews and conducts all inspections related to construction and enforcement within the City.'; Arizona has no mandatory statewide building code floor -- code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9). The City of South Tucson's currently adopted codes (per 'City of South Tucson Adopted Building Codes, Ordinance No. 25-01') are: 2018 International Building Code (IBC); 2018 International Residential Code (IRC); 2017 National Electrical Code (NEC) (one edition behind the 2018-cycle ICC set); 2018 International Mechanical Code (IMC); 2018 International Plumbing Code (IPC); 2018 International Fuel Gas Code (IFGC); 2018 International Energy Conservation Code (IECC); 2018 International Existing Building Code (IEBC); 2018 International Property Maintenance Code (IPMC); 2018 International Swimming Pool and Spa Code (ISPSC); 2018 International Fire Code (IFC); the 2012 City of Tucson/Pima County Outdoor Lighting Code; Arizona Administrative Code Title 18, Chapter 5, Article 2 (Public and Semipublic Swimming Pools and Spas); and ICC A117.1-2009 (Accessible and Usable Buildings and Facilities). Source: 'CITY OF SOUTH TUCSON ADOPTED BUILDING CODES, ORDINANCE NO: 25-01' (southtucsonaz.gov/media/10481) and southtucsonaz.gov/devservices/page/permits.; These 2018-cycle codes and the 2017 NEC are older than the 2024-cycle codes and 2023 NEC adopted in the neighbouring City of Tucson and unincorporated Pima County, so requirements can differ across the city line. South Tucson has not moved to the 2024 ICC cycle. Source: Ordinance No. 25-01 (southtucsonaz.gov/media/10486) and the individual 'ST 2018 [Code] AMENDMENTS' documents published on the Permits page.; Each adopted code carries City of South Tucson local amendments published as standalone PDFs per code (e.g., 'ST 2018 International Building Code AMENDMENTS', 'ST 2017 National Electrical Code AMENDMENTS', etc.), all linked from the Permits page. Source: southtucsonaz.gov/devservices/page/permits.; New construction, alterations, modifications, or tenant improvements to commercial properties/structures require construction plans drawn by a professional licensed and registered with the Arizona Board of Technical Registration (architect, mechanical engineer, plumbing engineer, or electrical engineer as applicable to the scope); all such registered professionals conducting business within City limits must also hold an active City of South Tucson business license. Source: southtucsonaz.gov/devservices/page/permits.; All contractors, whether working on residential or commercial properties, must be licensed through the Arizona Registrar of Contractors in the applicable classification, and must hold an active City of South Tucson business license to conduct business within city limits. Source: southtucsonaz.gov/devservices/page/permits.. Local amendments apply — see the South Tucson overview page for the full list.

No. The City has no EV/EVSE-specific permit, application, or fee line. An EV charger installation requires the City's standard Electrical Permit (2017 NEC as adopted), the same valuation-based process with no published numeric fee schedule used for other electrical work and the electrical component of solar PV installs.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the South Tucson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

South Tucson's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for South Tucson yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when South Tucson lands. Privacy.